Which of the following is not a part of Five Ms?
a. Material
b. Machine
c. Motion
d. Method
(Ans:c)
The correct sequence of operations in production planning and control is
a. Routing-Scheduling-Dispatching-Follow up
b. Scheduling-Routing- Dispatching-Follow up
c. Dispatching-Routing-Scheduling- Follow up
d. Routing-Scheduling-Follow up-Dispatching
(Ans:a)
Which of the following is true for Routing?
a. It is flow of work in the plant
b. Route sheets include list of machine tools that are to be followed
c. It depends upon material handling facilities
d. All of the above
(Ans:d)
Loading may be defined as
a. Sending the raw material to the machine
b. Sending the finished material to the store
c. Assign the work to the facilities
d. Uploading a software in machine control panel
(Ans:c)
Dispatching authorizes the start of production operations by
i. Release of material and components from stores to first process
ii. Release of material from process to process
iii. Issue of drawings instruction sheets
Which of the following is (are) true?
a. Only i
b. Only ii
c. i & ii
d. i , ii & iii
(Ans:d)
The bill of material does not consists of
a. Part number
b. Specifications of part
c. Name of the part
d. Price of the part
(Ans:d)
Procurement cycle time is time consumed for
a. Receiving of raw material
b. Inspection of various raw materials
c. Inspection of purchased components parts
d. All of the above
(Ans:d)
The transit time consist of
a. Time taken by raw material from machine to machine
b. Time consumed in moving the work between various departments
c. Time taken by a worker to machine a component
d. None of the above
(Ans:b)
Master schedule is prepared for
a. Single product continuous production
b. Multi product batch production
c. Assembly product continuous production
d. Single product batch production
(Ans:c)
Which of the following chart is drawn Machine vs time?
a. Man machine chart
b. The load chart
c. The progress chart
d. Curve chart
(Ans:b)
Gantt chart is mostly used for
a. Routing
b. Scheduling
c. Follow up
d. Inspection and quality control
(Ans:b)
Key to chart is provided in
a. Man machine chart
b. The load chart
c. The progress chart
d. Gantt chart
(Ans:d)
Centralized and decentralized are the types of
a. Routing
b. Dispatching
c. Scheduling
d. Follow up
(Ans:b)

More Related Content

Ppc mc qs

  • 1. Which of the following is not a part of Five Ms? a. Material b. Machine c. Motion d. Method (Ans:c) The correct sequence of operations in production planning and control is a. Routing-Scheduling-Dispatching-Follow up b. Scheduling-Routing- Dispatching-Follow up c. Dispatching-Routing-Scheduling- Follow up d. Routing-Scheduling-Follow up-Dispatching (Ans:a) Which of the following is true for Routing? a. It is flow of work in the plant b. Route sheets include list of machine tools that are to be followed c. It depends upon material handling facilities d. All of the above (Ans:d) Loading may be defined as a. Sending the raw material to the machine b. Sending the finished material to the store c. Assign the work to the facilities d. Uploading a software in machine control panel (Ans:c) Dispatching authorizes the start of production operations by i. Release of material and components from stores to first process ii. Release of material from process to process iii. Issue of drawings instruction sheets Which of the following is (are) true? a. Only i b. Only ii c. i & ii d. i , ii & iii (Ans:d) The bill of material does not consists of a. Part number b. Specifications of part c. Name of the part d. Price of the part (Ans:d) Procurement cycle time is time consumed for a. Receiving of raw material b. Inspection of various raw materials c. Inspection of purchased components parts d. All of the above
  • 2. (Ans:d) The transit time consist of a. Time taken by raw material from machine to machine b. Time consumed in moving the work between various departments c. Time taken by a worker to machine a component d. None of the above (Ans:b) Master schedule is prepared for a. Single product continuous production b. Multi product batch production c. Assembly product continuous production d. Single product batch production (Ans:c) Which of the following chart is drawn Machine vs time? a. Man machine chart b. The load chart c. The progress chart d. Curve chart (Ans:b) Gantt chart is mostly used for a. Routing b. Scheduling c. Follow up d. Inspection and quality control (Ans:b) Key to chart is provided in a. Man machine chart b. The load chart c. The progress chart d. Gantt chart (Ans:d) Centralized and decentralized are the types of a. Routing b. Dispatching c. Scheduling d. Follow up (Ans:b)