1. BAM is seeking local subcontractors and suppliers with experience in areas like construction, facilities management, cleaning, and maintenance to work on the Central and East Quads PPP project.
2. The project will employ approximately 2,500 construction workers and 65 long-term facilities management staff.
3. BAM will focus on meeting the goals of the Grangegorman Employment Charter, reserving 20% of jobs for local residents and 10% for long-term unemployed or new labor market entrants.
1 of 91
Downloaded 15 times
More Related Content
Presentations from Meet the Buyer event for the DIT Grangegorman Campus PPP project
11. Meet the Buyer Event
Grangegorman Project Overview
Michael Hand
Chief Executive Officer
13th
August, 2014
13. Grangegorman Development Agency Act 2005
Functions of Agency:
Accept the site
Consult with relevant stakeholders
Prepare a Masterplan and Strategic Plan
Decide appropriate procurement strategies
Procure and manage all the developments
Dispose of DIT properties
Return new facilities to DIT/HSE and other bodies on
completion
14. Milestones
Consultants
Report
Nov 2001
Chairman GDA
John Fitzgerald
Appointed
April 2006
Health Needs
Assessment
April 2010
Government
decision
April 2002
Gerry Murphy
Appointed CEO
June 2007
MRY and DMOD
Master Planner
Appointed
by GDA
Nov 2007
Government
decision
1999
NDP Inclusion
of project 2007
Joining the Dots
Employment Study
May 2009
Masterplan
Approved
2008
Cabinet
Decision
July 2010
&
Government
Launch
September
2010
GDA Act 2005
15. Milestones
Strategic Plan
Feb 2011
SDZ Planning
Scheme
Adopted by
DCC July 2011
Michael Hand
Appointed CEO
December 2010
Education
Related
Lands
Transferre
d Feb 2012
to GDA
Replacement
Mental Health
Facility Project on
site October 2010
New
Implementation
Programmes for
DIT May 2012
Funding
Deferred
Nov 2011
Government
announce
revised
funding
arrangements
July 2012SDZ Planning
Approval
May 2012
Employment
Charter
Agreed
March 2012
Arts
Strategy
Approved
2013
John Monahan
Appointed as
Chairperson
2012
Government
appoint
New Board
February 2013
16. Milestones
December 2013
Taoiseach Turns
Sod on SIPR
Contract
March 2013
Phoenix Care
Centre Opens
March 2014
Minister for Public
Expenditure and
Reform Launches
New
Employment
Studies
September 2013
Minister for
Education and
Skills officially
Launches PPP
Project Targets
September 2014 -
1000 Students
School of Art & Design
Greenway Hub
September 2015
Environmental Sustainability
Health Institute (ESHI)
September 2017
10,000 Students
DIT Central Quad (Food, Sciences,
Health & Engineering)
&
DIT East Quad (Creative & Cultural
Industries)
18. Grangegorman Urban Regeneration
For the HSE Securing Social Capital
Resolves the current poor accommodation of mental health patients
Adds new community health facilities for the north west city
For DIT Developing Human Capital
Consolidates 22,000 students and 2,000 staff ( 9% of sector) to a single location
Facilitates a new paradigm in third level education
Enhances the student experience through sport, cultural activities
Resolves poor accommodation and inadequate facilities
Enables growth in research, incubation, science and technology business synergies
Creates a more efficient organisation
19. Grangegorman Urban Regeneration
For the City- Providing Physical, Social & Intellectual Capital
Links this large site back into the north inner city fabric
Creates a major public resource and amenity parkland/sports
Creates a node of science/technology activity to regenerate the area
For the Local community Underpinning Social capital Urban transformation
New health and education facilities
New parks and sports amenities
New primary school for 400 pupils
New Dublin City Council branch library co-located with DIT library a first for Ireland
Valuable job opportunities
Major urban regeneration
21. 2009 Urban Design Award US Institute of Architects
2009 World Architecture Festival
2010 Chicago Athenaeum 2010 American Architecture Award
2012 American Institute of Architects (AIA) National Honor Award for Regional & Urban Design
2012 Honor Award - Society for College and University Planning
Masterplan 2008
24. 2014
DIT
West
Quad
DIT
Academic
Hub
LIBRARY
DIT
Student
Accommo
-dation
DIT
Indoor
Sports
Site Infrastructure
and Public Realm
HSE
Community
Nursing Unit
HSE
Mental
Health
Facility
(occupied)
HSE
Primary
Care
DIT
Demolitions
Contracts 1
& 2
DIT
Research
Hub
Central
Quad
East Quad
Broadsto
ne Gate
Prussia
St. Gate
DIT
Adaptive
Reuse
Contracts 1
& 2
DIT
Stabilisatio
n works
Energy
Centre
DIT
Adaptive
Re-use
Contract 3
DoES
Primary
School
DIT
PPPs
Complete / Occupied
Design - Planning
Preliminary
Design - Tender
Contract / Construction
Car
Parking
31. Post 2017
Science
Industry
Park
Central Quad
Library I
FOCAS
EHSI
East Quad I
Student Hub I
Phoenix
Primary
care
Primary
School
Sports
West
Quad
Business
Student
Hub
II
Fields
Clocktower
Student
accommodation
Energy
Centre
2017 delivery
Priorities
Self-funding
36. Meet the Buyer Event
13th
August 2014
in association with
Enterprise Ireland &
The Dept. for Social Protection
and the contracting authorities
The NDFA, GDA & DIT
DIT Grangegorman:
Central & East Quads PPP
Project
37. Who are BAM PPP?
Operating since the 1990s BAM PPP focuses on delivering
Excellence in PPP
We deliver diverse projects across all sectors;
Universities, Schools, Railways, Motorways, Prisons, Hospitals, Police HQs
Local Irish presence with our Head Office, Kill Co Kildare
39. Who are BAM Contractors?
A part of the Royal BAM Group
BAM Contractors were founded here in 1958
Operating across 32 counties with
600 + direct employees and we are
Responsible for some of Irelands Landmark Buildings & Civil Engineering
Projects
In PPP in Ireland we deliver;
Building, Civil Engineering & Facilities Management
All aspects of design; Architectural, C&S, M&E, Landscaping etc.
We provide Funding & Equity
40. BAM PPP Ireland in Pictures
PPP ACCOMMODATION PROJECTS; SCHOOLS BUNDLE 3 62,000m2 and 5,700 Pupils
Creagh College,
Gorey
rd Scoil na Mara,
Tramore
Merlin College
STN, Doon Col叩iste AilighBallinamore CSMerlin Woods Primary
Athlone CC
ROADS PROJECTS
M1 Dundalk Bypass N25 Waterford BypassM7/M8 Portlaoise
N7 / N11
Newlands Cross PPP
41. The BAM Group of
Companies in Ireland
have locations
throughout the country
42. 42
BAM across Ireland in Pictures
Did you drive on one of our roads or pass one of our projects today?
Curraheen Hospital
Cork Airport Carlow Arts Centre
Cork Co. Hall &
Library
Suir Bridge,
Waterford Bypass PPP
The Cliffs of Moher
Visitor Centre
N7 / N11
Newlands Cross
PPP
M7 M8 Portlaoise
Motorway PPP
Engineering Building
NUIGUCC IT Building St. James & Beaumont NPRO
CWU HQ
43. BAM Europe the Home Countries
Storm Surge Barrier,
Rotterdam NL
Roland Levinsky Building,
University of Plymouth
The Cooperative HQ, Manchester 02 World Arena, Berlin
NHL Hogeschool
Leeuwarden, NL
44. BAM International
Dutch Embassy, Ghana
Park
Place,
Dubai
Tempo
Scan,
Jakarta
Soccer City,
Johannesburg, SA
Welcome Pavilion, Ferrari World, Abu Dhabi Al Ain Stadium, Abu Dhabi
45. Employment coverage
on 1 PPP Project
8 Schools on 7 Sites
PPP Projects are Large but Local
Schools Bundle 3;
A Case Study
46. BAM Building & BAM FM in PPP
BAM Building:
On a typical PPP Project will;
Have on Ave. 150 workers a day / site and
The building of the Central & East Quads will employ approx. 2,500 people
BAM FM:
On typical PPP projects will;
Deliver up to 16 services for 25 years, in the Central & East Quads 10 services will
be delivered
Contract Management, Helpdesk, Cleaning, Building & Asset Maintenance, Waste Management, Pest
Control, Security, Caretaking Services, H&S Management & Energy & Utilities Management
Hold Lifecycle responsibility;
Handing the facilities back in 25 years in a near new condition with a significant Residual Life
The Central & East Quads will employ approx. 65 direct local staff for 25 years
47. PPP Projects are true turnkey projects
PPP Project - Schools Bundle 3 - Col叩iste Ailigh,
Letterkenny Winner RIAI Best Educational Building Award 2014
All Building
Elements
Complete Social & Circulation Spaces Complete Rooms including all FF&E and Consumables
Complete
Landscaping
48. What BAM need from today?
Subcontractors & Suppliers who are;
Local
Professional
Experienced
Qualified
High Quality
49. Important messages from today?
The Grangegorman Employment Charter & Social
Inclusion
20% of jobs will be available to residents of D7 and
Grangegorman
10% of jobs will be created with new entrants to the labour
market or the long term unemployed
2.5% of jobs will be created using trainees
53. STRICTLY CONFIDENTIAL | PAGE 53
Consortium comprised of market leaders in UK and Ireland PPPs
GRANGEGORMAN CONSORTIUM
OVERVIEW
Macquarie Group
Pre-eminent infrastructure and PPP sponsor and financial
adviser with strong experience in working with procuring
authorities in Ireland and established relationships with key
local partners
Successful lead of various large-scale, complex PPP in
extremely difficult market conditions, including::
Mersey Gateway Bridge project (728m)
Dublin Waste to Energy (500m)
Irish Schools PPP Bundle 1 and Bundle 2 (187m)
Leeds BSF Phase 1 & 2 (181m)
University of Canberra (69m)
Enniskillen hospital (336m)
45-year
history
Market
Capitalisation of
13.0bn
as at July 2014
13,900+
employees across
28
countries
~290bn
assets under
management at March
2014
A-/A3
credit rating
No. 1
Total number of
completed & announced
M&A deals since 2005
Local Presence Know the client
Partnership
approach
Know the market
54. STRICTLY CONFIDENTIAL | PAGE 54
Leading international partners with outstanding PPP experience, commercial focus and
strong financial standing
GRANGEGORMAN CONSORTIUM
OVERVIEW
Irelands largest and most successful
construction company
One of the leading Spanish construction
groups
Founded in 1859 and based in Dublin, Ireland
Robust international business with diverse interests in
construction, healthcare, distribution, manufacturing and
property development in Europe and the Middle East
Significant success in delivering PPP schemes in Ireland as
winner of 7 Irish PPP projects:
Irish Schools PPP Bundle 2 (75m)
Dublin National Conference Centre (226m)
Pilot PPP Schools Bundle (60m)
Cork School of Music (52m)
M8 Rathcormac Fermoy Bypass (172m)
Limerick Tunnel (360m)
M17/M18 Gort to Tuam (250m)
Established track record in the university sector, including:
UCD Science Centre (65m)
NIBRT at UCD (15.3m)
Source: Company website (as of July 2014)
Founded in 1893 and based in Barcelona, Spain
Key highlights:
6th largest contractor in Europe by Turnover
14th largest construction contractor globally
2nd largest Sponsor globally by number of projects
Significant experience in Ireland with delivery of several PPP projects
since 2005:
Enniskillen hospital (336m), in cooperation with Macquarie
M50 Motorway, Ireland (250m) in cooperation with Macquarie
N6 Galway-Ballinasloe Road (337m)
Highlights on university expertise:
Gdansk University (25m)
Madrid College of Architects (27m)
Navarra University (12.4m )
Valencia University (34.1m)
Relevant PPPs completed with Macquarie include also Mersey
Gateway Bridge project (728m)
55. STRICTLY CONFIDENTIAL | PAGE 55
GRANGEGORMAN CONSORTIUM
OVERVIEW
Source: Company website (as of July 2014)
Education PPP specialist with experience
ranging from schools to universities
Largest home grown facilities
management contractor
FTSE 250 listed company with a turnover of 2bn in 2012
Mitie Facilities Management Limited is the Irish subsidiary of
Mitie Group plc employing over 1,300 employees throughout
Ireland
Provides facilities, property and energy management as well as
infrastructure consultancy for a wide range of public and private
sector business
Mitie is currently involved in 103 education facilities
management projects
Education PPP experience includes Building schools for the
Future Programmes
Relevant facilities management experience in the university
sector: Durham University, Cambridge University, Greenwich
University, St Georges University, Northumbria University,
Birmingham City University and many more
Founded in 1977 and headquartered in Dublin
Extensive experience in the education sector for over
23 years
Well established track record in the provision of
general facilities services
Employs over 7,000 people in Ireland and works with
over 1,700 clients throughout Ireland and the UK
University highlights: Dublin Institute of Technology,
Trinity College Dublin, Dun Laoghaire Institute of Art,
Design and Technology, University College Dublin,
Dundalk Institute of Technology, University of Limerick,
University of Ulster and Dublin Business School
Partnership between Irelands biggest facilities management provider and most experienced
education PPP partner
56. STRICTLY CONFIDENTIAL | PAGE 56
Experienced consortium with strong track record in Irish PPP/PFI
PREVIOUS PROJECTS /PPP INITIATIVES
Project Project Value (m) Financial Close Concession Period
Irish Schools Bundle Two 106 2nd
June 2010 25
Irish Schools Bundle One 81 9th
March 2009 25
Schools Bundle Pilot 30 2003 25
Cork School of Music 70 5th
September 2005 25
M50 290 27th
September 2007 35
N6 330 5th
April 2007 30
Limerick Tunnel 278 18th
August 2006 35
National Conference Centre 252 5th
April 2007 25
57. STRICTLY CONFIDENTIAL | PAGE 57
Identify new Sub-contractors & Suppliers
Provide potential Sub-contractors & Suppliers with specific
information on the project, giving them opportunity to access
potential opportunities
Engage with diverse range of suppliers and social enterprises
Develop improved understanding on the range of local services
available to support the project
Develop improved understanding of the current and previous
experience within the local supply chain
Identify key personnel and open communication channels
Provide the opportunity to gain access to our approved sub-
contractor / supplier database
OBJECTIVES FOR THE EVENT
58. STRICTLY CONFIDENTIAL | PAGE 58
Our policy is to sponsor collaborative partnering of SMEs with
larger specialist providers, allowing SMEs to secure works
packages and provide potential for company development & up-
skilling of employees
Collaborative approach
Sharing of Client deliverables and objectives
Open to new ideas and ways of working
Development of clear communication channels
Support supplier development of practices and processes eg
EH&S
Support supplier sustainability development
Development of business continuity plans
Supply chain events and forums
In order to reduce environmental impacts on the project, we are
looking to identify local businesses for site services such as plant
hire, catering, cleaning & site consumables
WORK WITH SUB-SUPPLIERS AND SUB-
CONTRACTORS
The Eriugena consortium will proactively manage our procurement process to ensure the project provides benefits &
business opportunities to local SMEs, ensuring that SMEs which are not of a suitable size for the main works
packages have opportunity to compete for elements of packages,
59. STRICTLY CONFIDENTIAL | PAGE 59
Past experience on projects of similar value, nature, complexity, and
size. With emphasis on experience of previous 3rd
level experience.
Capacity of resources
Commercial strength
Satisfactory financial robustness-financial accounts
Health and safety records and ability to meet with Construction and
Operations H&S expectations
Proven ability to perform and deliver to schedule
Proven ability to achieve competitive pricing in the market
Current and future workload schedules and available resources
Management resources and personnel for Project
Off-site production facilities with capability and capacity to deliver
this project
QA / QC procedures
Plant and Equipment
FM eSourcing platform - www.mitiesourcing.com
Clear process for supplier selection
Reliability track record in service delivery supported by references
SUPPLIER COMPLIANCE CRITERIA
For the selection and tendering for subcontracted works, the project scope documents are broken down into
elemental or trade packages with enquiries which contain all relevant contract documentation typically sent to four or
five subcontractors. The rationale used in the selection of Tenderers include;
62. DIT Campus at Grangegorman Central and East Quads PPP
DIT Grangegorman
Meet the Buyer
Caron Dunlop, Community Engagement Manager,
Brookfield Multiplex
63. [Presentation title and date]
DIT Campus at Grangegorman Central and East Quads PPP
Get connected at DIT Grangegorman
SPONSORS CONSTRUCTION FACILITIES
DIT Campus Grangegorman 13th
August 2014
64. [Presentation title and date]
DIT Campus at Grangegorman Central and East Quads PPP
Objectives for Today
DIT Campus Grangegorman 13th
August 2014
65. [Presentation title and date]
DIT Campus at Grangegorman Central and East Quads PPP
Past Projects
Kajima and infra1red
50 PPP projects in their
portfolio
792 million
Mercury Engineering
20 Educational Schemes
in their portfolio
60 million
Brookfield Multiplex
12 educational projects
delivered around the
globe in the last 5 years
660 million
Walls Construction
Over 20 projects
delivered in the last 5
years
220 million
DIT Campus Grangegorman 13th
August 2014
66. [Presentation title and date]
DIT Campus at Grangegorman Central and East Quads PPP
Procurement Process
DIT Campus Grangegorman 13th
August 2014
67. [Presentation title and date]
DIT Campus at Grangegorman Central and East Quads PPP
Selection Criteria
DIT Campus Grangegorman 13th
August 2014
68. DIT Campus at Grangegorman Central and East Quads PPP
Get connected to
DIT Grangegorman
71. Department of Social Protection
Pathways to Work
Supports for Grangegorman Development Employers
72. Grangegorman Employment Charter
The purpose of the Charter is to ensure that the local
community benefit from any employment opportunities that
may arise from the project
The Charter sets out what is required of contractors and sub-
contractors in respect of employing local labour. All
contractors and sub-contractors, who are awarded contracts,
will be required to implement the Charter
73. Grangegorman Employment Charter
The Charter is seeking to ensure that a minimum of 20% of
new jobs created on projects will be on offer to residents of
the Grangegorman neighbourhood and the surrounding areas
Where appropriate the contractor will be encouraged to use
all reasonable steps to fill 10% of new jobs created with long
term unemployed.
75. We have been given a mandate to change and
we are changing.with a dual focus
Put simply, no-one who loses
his/her job should be allowed to
drift, with no support, into long
term unemployment.
To assist employers in recruiting
employees from the Live Register
and to incentivise employers to
offer opportunities to unemployed
people particularly
long-term unemployed people.
76. A change that is as focussed on employers as it
is on unemployed people
78. With innovative financial supports
that can deliver real savings to employers
JobsPlus New Jobs, Less Cost
Available from July 2013
An employment grant paid monthly in respect of employees hired from the live
register
Two Levels of Payment
An employee who was unemployed for 12 mths 24 mths: 7,500
An employee who was unemployed for 2 years of more: 10,000
Full- time employment over 30 hours per week
For new vacancies, which do not displace existing employees
Time spent on Jobbridge and other schemes counts towards eligibility
79. and address some time-worn excuses
I lose my medical card if I take
up work
I cant take up a temporary
jobif I do I have to re-apply
all over again
I cant take up part-time work
Wrong! Unemployed people can
keep their medical card for 3 years
after taking up work
Wrong! Unemployed people can
suspend their claim for up to 8
weeks to take-up temporary work
Wrong! Casual and Part-time work
can be facilitated
80. So what next make contact
Portlaoise Employment Services Office
Ph: 057 8632900
For a list of Intreo or Employment Services Offices in your
locality, please go to:
www.welfare.ie
National Contact Centre
Freephone: 1800 611116
83. Getting the most out of the speed meeting &
networking session
Orlagh Murphy
Senior Market Adviser
Enterprise Ireland
13th August 2014
85. 8 things to remember
1) What is your speed pitch? Have you decided who you want to
meet & what you want to say to them in your 5 minute meeting?
2) Which information zone is the most appropriate for your company?
Construction zone
Products and equipment
Facilities Management
3) Your ToolKit - your Business Cards, Summary Profiles, Literature
Consider the supplier questionnaires
4) Plan to meet and speak with all 3 shortlisted bidder teams
86. 8 things to remember
5) Visit the Enterprise Support Zone
- organisations to advise you on key aspects of your business
6) Visit the Delegate Networking Hub
-speak with other attendees, not just your colleagues
7) Follow up after todays event
8) Register on www.etenders.gov.ie