Navneet Dwivedi
PGDM-Operations and Supply Chain
 To define few Key Production Performance
Indicators (Production KPIs)
 OEE (Overall Equipment Effectiveness)
 Direct Efficiency
 Productivity
 Direct Efficiency
 Productivity
Efficiency of workers
involved in production
activity only
Efficiency and effectiveness
of all the workers enrolled
in the company
Efficiency ?? Effectiveness??
Ratio of input and output
Ability to do thing correctly
Direct Efficiency=
$  諮
 諮
Productivity=
$  諮
 諮
Theoretical Produced Hours ??
Paid Hours ??
Worked Hours ??
Direct Presence Hours
Delegation Hours
Standard Hours
Punching
(2 min)
Trimming
(1 min)
Drawing
(3 min)
Buffing (2
min)
Packaging
(2 min)
Cutting
(1 min)
Deburring
(1 min)
Drilling
(3 min)
Bending
(5min)
Washing
(2 min)
(a)
(b)
Process Process Flow Total
Time
10 min
12 min
Thus we have Total Time Cycle for Process (a) TTCa =10 minutes
Total Time Cycle for Process (a) TTCb =12 minutes
Standard Hour (Item (a) STHa= (10/60) =0.1667 hrs/unit
Standard Hour (Item (a) STHb= (12/60) =0.2 hrs/unit
 Daily Production Report
Manpower Details Production Quantity
Total Enrolled (TE) 11 Item (b) Item (b)
Total Present (TP) 10 Total Produced 183 100
Setup Man 1 Good Items 180 100
Short Leave (hrs) (SL) 4 Scrap 3 0
Overtime (hrs) (OT) 1 Total Time Cycle (min) 10 12
Delegated to Other Dept.
Department Nos Duration(hrs) Manhours
Stores 1 8 8
Technical
Quality 1 4 4
Washing
Rework
Admin Work 2 4 8
Other Misc
Shift Time (ST) 8.5
Break Time (BT) 0.5
Summary Report
Shift Time 8.5
Break Time 0.5
Net Shift Time 8
Production Hour 50
Direct Presence hours 77
Delegated Hours 20
Worked Hours 57
Paid Hours 90.5
Direct Eff. 87.7%
Productivity 55.2%
Production Hour= (STHa*Qtya) + (STHb*Qtyb
= ((10/60)*180)+ ((12/60)*100)
= 50 hrs
.
Net Shift Time(NST)=Shift Time-Break Time
=8.5 -0.5= 8 hrs
Direct Presence Hours= (NST*TP)+OT-SL
= (8*10)+1-4 = 77 hrs
Delegated Hours = Sum(all delegation man-hours)
= 20 hrs
Worked Hours = D.Presence Hrs- Delegated Hrs
= 77-20 = 57 hrs
Paid Hours=(ST*TE)+OT-SL =(11*8.5)+1-4
= 90.5 hrs
Direct Efficiency=
$  諮
 諮
Productivity=
$  諮
 諮
87.7 %
55.2 %
Channel Name: e-learninghub
https://www.youtube.com/channel/UCf21bSHsbacu48YuKgdUfgg
Follow us on Facebook
https://www.facebook.com/navneetelearninghub

More Related Content

Productivity and Direct Efficiency

  • 2. To define few Key Production Performance Indicators (Production KPIs) OEE (Overall Equipment Effectiveness) Direct Efficiency Productivity
  • 3. Direct Efficiency Productivity Efficiency of workers involved in production activity only Efficiency and effectiveness of all the workers enrolled in the company Efficiency ?? Effectiveness?? Ratio of input and output Ability to do thing correctly
  • 4. Direct Efficiency= $ 諮 諮 Productivity= $ 諮 諮
  • 5. Theoretical Produced Hours ?? Paid Hours ?? Worked Hours ?? Direct Presence Hours Delegation Hours Standard Hours
  • 6. Punching (2 min) Trimming (1 min) Drawing (3 min) Buffing (2 min) Packaging (2 min) Cutting (1 min) Deburring (1 min) Drilling (3 min) Bending (5min) Washing (2 min) (a) (b) Process Process Flow Total Time 10 min 12 min Thus we have Total Time Cycle for Process (a) TTCa =10 minutes Total Time Cycle for Process (a) TTCb =12 minutes Standard Hour (Item (a) STHa= (10/60) =0.1667 hrs/unit Standard Hour (Item (a) STHb= (12/60) =0.2 hrs/unit
  • 7. Daily Production Report Manpower Details Production Quantity Total Enrolled (TE) 11 Item (b) Item (b) Total Present (TP) 10 Total Produced 183 100 Setup Man 1 Good Items 180 100 Short Leave (hrs) (SL) 4 Scrap 3 0 Overtime (hrs) (OT) 1 Total Time Cycle (min) 10 12 Delegated to Other Dept. Department Nos Duration(hrs) Manhours Stores 1 8 8 Technical Quality 1 4 4 Washing Rework Admin Work 2 4 8 Other Misc Shift Time (ST) 8.5 Break Time (BT) 0.5
  • 8. Summary Report Shift Time 8.5 Break Time 0.5 Net Shift Time 8 Production Hour 50 Direct Presence hours 77 Delegated Hours 20 Worked Hours 57 Paid Hours 90.5 Direct Eff. 87.7% Productivity 55.2% Production Hour= (STHa*Qtya) + (STHb*Qtyb = ((10/60)*180)+ ((12/60)*100) = 50 hrs . Net Shift Time(NST)=Shift Time-Break Time =8.5 -0.5= 8 hrs Direct Presence Hours= (NST*TP)+OT-SL = (8*10)+1-4 = 77 hrs Delegated Hours = Sum(all delegation man-hours) = 20 hrs Worked Hours = D.Presence Hrs- Delegated Hrs = 77-20 = 57 hrs Paid Hours=(ST*TE)+OT-SL =(11*8.5)+1-4 = 90.5 hrs Direct Efficiency= $ 諮 諮 Productivity= $ 諮 諮 87.7 % 55.2 %
  • 9. Channel Name: e-learninghub https://www.youtube.com/channel/UCf21bSHsbacu48YuKgdUfgg Follow us on Facebook https://www.facebook.com/navneetelearninghub