ºÝºÝߣ

ºÝºÝߣShare a Scribd company logo
Welcome to Project cost and schedule
           control


  Your trainer is   Mike Kerrigan
Project Management Basics




The Project manager is responsible for delivering all
                        three
Managing the project

       Plan



Act                 Do



      Check
Completed 1.5 km                       An example




                              How is the project doing?
Project:
    Build 5 km railway               End of month 2:

    Time allowed: 5 months               Cost?

    Budget: ?100,000                     Schedule?
                                         Completion %?
Completed 1.5 km                                  An example




                          How is the project doing?
End of month 2:
    Time passed: 40% of duration
    1.5 km of railway completed = 30% of requirement
    Spend to date: ?38,000 = 38% of budget
    How are we doing? 30/38/40% complete?
Gantt schedule
Gantt with baseline and Critical Path
Milestone chart
17/04/2011




26/02/2011




07/01/2011

                                                 SDR Complete
                                                 Subsys 1 complete
18/11/2010
                                                 Subsys 2 complete
                                                 Subsys 3 complete
                                                 IVV Complete
29/09/2010
                                                 System Delivered
                                                 Acceptance complete
                                                 Reference
10/08/2010




21/06/2010




02/05/2010
             M0   M1   M2   M3   M4   M5    M6
Traditional monitoring
Cost:
¨C What percentage of the budget has been spent?
¨C What is our estimate to complete?
¨C How much will it cost at completion?


                                160
                                140
                                120
                                100
                                                                   Budget
                                 80

                            ?
                                                                   Actual
                                 60
                                 40
                                 20
                                  0




                                                              10
                                      0

                                          2

                                              4

                                                    6

                                                          8
                                                  Month
Baseline plan                                Back to the example
                                               Embankment
                   Bridge




  Km 1           Km 2           Km 3           Km 4           Km 5
  Budget ?15k    Budget ?33k    Budget ?15k    Budget ?22k    Budget ?15k
  Time 1 mth     Time 1.5 mth   Time 0.5 mth   Time 1.5 mth   Time 0.5 mth


Project:
    Build 5 km of railway
    Budgeted cost: ?100,000
    Delivery timescale: 5 months
Where are we?
   Schedule end of month 2
                                                  Embankment
                      Bridge




    Km 1            Km 2           Km 3           Km 4           Km 5
    Budget ?15k     Budget ?33k    Budget ?15k    Budget ?22k    Budget ?15k
    Time 1 mth      Time 1.5 mth   Time 0.5 mth   Time 1.5 mth   Time 0.5 mth


Value of work planned to be completed:
In month 1 = ?15k
In month 2 = (1/1.5 x ?33k) = ?22k
Planned value = ?15k + ?22k = ?37k
Where are we?
   Schedule end of month 2
                                                Embankment
                     Bridge




    Km 1          Km 2           Km 3           Km 4           Km 5
    Budget ?15k   Budget ?33k    Budget ?15k    Budget ?22k    Budget ?15k
    Time 1 mth    Time 1.5 mth   Time 0.5 mth   Time 1.5 mth   Time 0.5 mth

Value of work completed:
Km1 = ?15k
Km2 = 50% of ?33k = ?16.5k
Earned value = ?15K + ?16.5k = ?31.5k (31.5% of total value)
Where are we?
   Schedule end of month 2
                                                Embankment
                     Bridge




    Km 1          Km 2           Km 3           Km 4           Km 5
    Budget ?15k   Budget ?30k    Budget ?15k    Budget ?25k    Budget ?15k
    Time 1 mth    Time 1.5 mth   Time 0.5 mth   Time 1.5 mth   Time 0.5 mth

Earned value = ?31.5k = 31.5%
Planned value = ?37k = 37%
Conclusion: Value of work done is 5.5% less than planned
Behind by ?5.5k value of work
Where are we?
   Costs end of month 2
                                                   Embankment
                       Bridge




    Km 1             Km 2           Km 3           Km 4           Km 5
    Budget ?15k      Budget ?30k    Budget ?15k    Budget ?25k    Budget ?15k
    Time 1 mth       Time 1.5 mth   Time 0.5 mth   Time 1.5 mth   Time 0.5 mth

Earned value = ?31.5k = 31.5% of budget
Actual costs = ?38k = 38% of budget
Conclusion: Spent 38% of budget doing 31.5% of the work
Overspent by ?6.5k
How are we doing?

1800


1600


1400


1200
                                                         Planned

1000

                                                         Actual
800


600
                                                         Earned

400


200


   0
       0   1   2   3   4   5   6   7   8   9   10   11
How are we doing?

1800


1600


1400


1200
                                                          Planned

1000
                                                          Actual

 800
                                                          Earned
 600


 400


 200


   0
       0   1   2   3   4   5   6   7   8   9    10   11
Estimate at Complete (EAC)

If we continued to perform as we have to date:



EAC =        Budget     x   Actual cost
                             Earned
Change




                                   Change!


                       Impact



Change in requirements will impact Time and Cost

More Related Content

Project Cost and Schedule Control

  • 1. Welcome to Project cost and schedule control Your trainer is Mike Kerrigan
  • 2. Project Management Basics The Project manager is responsible for delivering all three
  • 3. Managing the project Plan Act Do Check
  • 4. Completed 1.5 km An example How is the project doing? Project: Build 5 km railway End of month 2: Time allowed: 5 months Cost? Budget: ?100,000 Schedule? Completion %?
  • 5. Completed 1.5 km An example How is the project doing? End of month 2: Time passed: 40% of duration 1.5 km of railway completed = 30% of requirement Spend to date: ?38,000 = 38% of budget How are we doing? 30/38/40% complete?
  • 7. Gantt with baseline and Critical Path
  • 8. Milestone chart 17/04/2011 26/02/2011 07/01/2011 SDR Complete Subsys 1 complete 18/11/2010 Subsys 2 complete Subsys 3 complete IVV Complete 29/09/2010 System Delivered Acceptance complete Reference 10/08/2010 21/06/2010 02/05/2010 M0 M1 M2 M3 M4 M5 M6
  • 9. Traditional monitoring Cost: ¨C What percentage of the budget has been spent? ¨C What is our estimate to complete? ¨C How much will it cost at completion? 160 140 120 100 Budget 80 ? Actual 60 40 20 0 10 0 2 4 6 8 Month
  • 10. Baseline plan Back to the example Embankment Bridge Km 1 Km 2 Km 3 Km 4 Km 5 Budget ?15k Budget ?33k Budget ?15k Budget ?22k Budget ?15k Time 1 mth Time 1.5 mth Time 0.5 mth Time 1.5 mth Time 0.5 mth Project: Build 5 km of railway Budgeted cost: ?100,000 Delivery timescale: 5 months
  • 11. Where are we? Schedule end of month 2 Embankment Bridge Km 1 Km 2 Km 3 Km 4 Km 5 Budget ?15k Budget ?33k Budget ?15k Budget ?22k Budget ?15k Time 1 mth Time 1.5 mth Time 0.5 mth Time 1.5 mth Time 0.5 mth Value of work planned to be completed: In month 1 = ?15k In month 2 = (1/1.5 x ?33k) = ?22k Planned value = ?15k + ?22k = ?37k
  • 12. Where are we? Schedule end of month 2 Embankment Bridge Km 1 Km 2 Km 3 Km 4 Km 5 Budget ?15k Budget ?33k Budget ?15k Budget ?22k Budget ?15k Time 1 mth Time 1.5 mth Time 0.5 mth Time 1.5 mth Time 0.5 mth Value of work completed: Km1 = ?15k Km2 = 50% of ?33k = ?16.5k Earned value = ?15K + ?16.5k = ?31.5k (31.5% of total value)
  • 13. Where are we? Schedule end of month 2 Embankment Bridge Km 1 Km 2 Km 3 Km 4 Km 5 Budget ?15k Budget ?30k Budget ?15k Budget ?25k Budget ?15k Time 1 mth Time 1.5 mth Time 0.5 mth Time 1.5 mth Time 0.5 mth Earned value = ?31.5k = 31.5% Planned value = ?37k = 37% Conclusion: Value of work done is 5.5% less than planned Behind by ?5.5k value of work
  • 14. Where are we? Costs end of month 2 Embankment Bridge Km 1 Km 2 Km 3 Km 4 Km 5 Budget ?15k Budget ?30k Budget ?15k Budget ?25k Budget ?15k Time 1 mth Time 1.5 mth Time 0.5 mth Time 1.5 mth Time 0.5 mth Earned value = ?31.5k = 31.5% of budget Actual costs = ?38k = 38% of budget Conclusion: Spent 38% of budget doing 31.5% of the work Overspent by ?6.5k
  • 15. How are we doing? 1800 1600 1400 1200 Planned 1000 Actual 800 600 Earned 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11
  • 16. How are we doing? 1800 1600 1400 1200 Planned 1000 Actual 800 Earned 600 400 200 0 0 1 2 3 4 5 6 7 8 9 10 11
  • 17. Estimate at Complete (EAC) If we continued to perform as we have to date: EAC = Budget x Actual cost Earned
  • 18. Change Change! Impact Change in requirements will impact Time and Cost