1.0     PROJECT BACKGROUND




2.0     SCOPE OF WORKS

The components in this flood mitigation project comprise of two (2) interrelated flood diversion
schemes :

        i)      New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds.
        ii)     Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the
                enlarged Batu Detention Pond.
        iii)    Benteng and Puah conceptional detail design.
2.1   GOMBAK DIVERSIONS WORK
Upgrading of the existing Gombak Diversion system:

      i.    Gombak Diversion (3.375 km)
      ii.   Gombak barrage at Gombak River downstream of Gombak Diversion
      iii.  Low overflow weir from Gombak River to Gombak Diversion
      iv.   Inlet gate to Gombak Diversion
      v.    Gombak Diversion outfall structure
      vi.   Ogee weir from regulating pond to Batu Pond
      vii.  Enlargement of Batu Pond capacity to 4.5 million cubic meter
      viii. Control gate for Batu Pond outlet to Batu River
      ix.   Flood walls along Gombak River
2.2   KEROH DIVERSIONS WORK
i.    New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km)
         ii.   Keroh barrage at downstream of Seri Segambut Pond
         iii.  Low overflow weir from Keroh river to Seri Segambut Pond
         iv.   Inlet gate to Keroh Diversion
         v.    Keroh Diversion outfall
         vi.   Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million
               cubic meter
         vii.  Control gate at Nanyang Pond outlet
         viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond
         ix.   Control gate at Taman Wahyu and Delima Pond outlet
         x.    Flood walls along Keroh River
3.0      CONTRACTUAL INFORMATION

i)      Nama Kontrak :                 Projek Mengatasi Masalah Banjir Di Kuala Lumpur
                                       Package B  Batu / Jinjang Ponds And Related Flood
                                       Diversion

ii)     No. Kontrak :                  JPS/IP/S/5/02

iii)    Pemilik Projek :               Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam
                                       Sekitar

iv)     Jabatan Pelaksana :            Jabatan Pengairan dan Saliran, Malaysia

v)      Kontraktor Utama :             PECD Construction Sdn. Bhd.
                                       5th Floor, Block E, Peremba Square
                                       Saujana Resort, Seksyen U2,
                                       40150 Shah Alam
                                       Selangor Darul Ehsan

vi)     Perunding Rekabentuk dan       RPM Engineers Sdn. Bhd.
        Penyeliaan:                    34A, Jalan SS21/39,
                                       Damansara Utama
                                       47400 Petaling Jaya,
                                       Selangor Darul Ehsan

vii)    Perunding Jurukur Bahan :      Perunding Ukur Bahan RB,
                                       Unit G1, Taman Tunku,
                                       Bukit Tunku, 50480 Kuala Lumpur

viii)   Harga Kontrak Asal :           RM 804,993,894.00

ix)     Kos Pembinaan:                 RM 528,880,519.00

x)      Tempoh Kontrak :               45 Bulan (25 Ogos 2003  24 Mei 2007)
                                       EOT 1 ( 27 Disember 2007 )
                                       EOT 2 ( 26 Mei 2008 )
                                       EOT 3 ( 25 September 2008 )
                                       EOT 4 ( 24 Disember 2008 )
                                       EOT 5 (24 Ogos 2009)
Project Information 060709[1]

More Related Content

Project Information 060709[1]

  • 1. 1.0 PROJECT BACKGROUND 2.0 SCOPE OF WORKS The components in this flood mitigation project comprise of two (2) interrelated flood diversion schemes : i) New diversion channel to divert Sg. Keroh flood flow to Jinjang Detention Ponds. ii) Upgrading Gombak Diversion to allow more discharge diversion from Sg. Gombak to the enlarged Batu Detention Pond. iii) Benteng and Puah conceptional detail design.
  • 2. 2.1 GOMBAK DIVERSIONS WORK
  • 3. Upgrading of the existing Gombak Diversion system: i. Gombak Diversion (3.375 km) ii. Gombak barrage at Gombak River downstream of Gombak Diversion iii. Low overflow weir from Gombak River to Gombak Diversion iv. Inlet gate to Gombak Diversion v. Gombak Diversion outfall structure vi. Ogee weir from regulating pond to Batu Pond vii. Enlargement of Batu Pond capacity to 4.5 million cubic meter viii. Control gate for Batu Pond outlet to Batu River ix. Flood walls along Gombak River 2.2 KEROH DIVERSIONS WORK
  • 4. i. New diversion scheme from Sungai Keroh to Jinjang Ponds (2.2 km) ii. Keroh barrage at downstream of Seri Segambut Pond iii. Low overflow weir from Keroh river to Seri Segambut Pond iv. Inlet gate to Keroh Diversion v. Keroh Diversion outfall vi. Enlargement of Nanyang pond, Taman Wahyu and Delima Pond capacity to 2.5 million cubic meter vii. Control gate at Nanyang Pond outlet viii. Deepening of the channel connecting Nanyang and Taman Wahyu Pond ix. Control gate at Taman Wahyu and Delima Pond outlet x. Flood walls along Keroh River 3.0 CONTRACTUAL INFORMATION i) Nama Kontrak : Projek Mengatasi Masalah Banjir Di Kuala Lumpur Package B Batu / Jinjang Ponds And Related Flood Diversion ii) No. Kontrak : JPS/IP/S/5/02 iii) Pemilik Projek : Kerajaan Malaysia, Kementerian Sumber Asli Dan Alam Sekitar iv) Jabatan Pelaksana : Jabatan Pengairan dan Saliran, Malaysia v) Kontraktor Utama : PECD Construction Sdn. Bhd. 5th Floor, Block E, Peremba Square Saujana Resort, Seksyen U2, 40150 Shah Alam Selangor Darul Ehsan vi) Perunding Rekabentuk dan RPM Engineers Sdn. Bhd. Penyeliaan: 34A, Jalan SS21/39, Damansara Utama 47400 Petaling Jaya, Selangor Darul Ehsan vii) Perunding Jurukur Bahan : Perunding Ukur Bahan RB, Unit G1, Taman Tunku, Bukit Tunku, 50480 Kuala Lumpur viii) Harga Kontrak Asal : RM 804,993,894.00 ix) Kos Pembinaan: RM 528,880,519.00 x) Tempoh Kontrak : 45 Bulan (25 Ogos 2003 24 Mei 2007) EOT 1 ( 27 Disember 2007 ) EOT 2 ( 26 Mei 2008 ) EOT 3 ( 25 September 2008 ) EOT 4 ( 24 Disember 2008 ) EOT 5 (24 Ogos 2009)