This document contains information about stakeholders, milestones, activity durations, cost estimates, risks, communication plans, and performance reporting for a project. Key stakeholders include the VP of Finance as project sponsor and a Finance Manager as subject matter expert. Critical milestones like system development and testing are overdue. Risks include issues related to system design, coding, operations, schedule, and infrastructure. Performance reports show the project is under budget but behind schedule.
1 of 10
Download to read offline
More Related Content
Project Management Plan Templates
1. ID Name Title Role Power Interest Expectations Concerns
1 John Hall VP of Finance Project Sponsor Project to be delivered on
time and within budget
Management
dashboard
2 Mary Anne Finance Manager Subject Matter
Expert
Complete 6 core modules
and 28 key features
Analytics and big data
3 Francis Doe Business Analyst Project Team
Member
Gather complete
requirements for 3 core
modules
Key User Cooperation
4
5
6
7
8
9
10
STAKEHOLDER ANALYSIS
2. No Milestone Mandatory/
Optional
Start Date End Date Status Comments
01 Project Start Mandatory 00/00/0000 00/00/0000 Completed
02 Risk Management Workshop Optional 00/00/0000 00/00/0000 Completed
03 Gather Requirements Mandatory 00/00/0000 00/00/0000 Completed
04 System Design Mandatory 00/00/0000 00/00/0000 Completed
05 Build Prototype Mandatory 00/00/0000 00/00/0000 In Progress
06 System Development (coding) Mandatory 00/00/0000 00/00/0000 Overdue
07 Testing Mandatory 00/00/0000 00/00/0000 Overdue
08 Pilot Implementation Optional 00/00/0000 00/00/0000 Not Started
09 User Training Optional 00/00/0000 00/00/0000 Not Started
10 Live Implementation Mandatory 00/00/0000 00/00/0000 Not Started
MILESTONE LIST
3. Activity Resource(s) Optimistic Most Likely Pessimistic
Estimated Activity
Duration
Reserve
A Francis Doe 30 hrs. 35 hrs. 40 hrs. 35 hrs. +/- 8 hrs.
B Remy Bobbit 45 hrs. 50 hrs. 55 hrs. 50 hrs. +/- 12 hrs.
C Lee Chan 55 hrs. 60 hrs. 65 hrs. 60 hrs. +/- 16 hrs.
DURATIONS ESTIMATE
4. Communication
Type
Objective of
Communication
Medium Frequency Audience Owner Deliverable
Project Kickoff Meeting Meeting to initiate the project
and brief project stakeholders on
project objective, scope,
schedule and project team.
Face to Face Once Project Sponsor
Project Team
Stakeholders
Project Manager Agenda
Kickoff 際際滷s
Meeting
Minutes
Project Team Meetings Discuss project status with
project team members.
Face to Face
Conference Call
Weekly Project Team Project Manager Agenda
Meeting
Minutes
Project schedule
Technical Meetings Discuss technical related issues
with solution architect and
programmers.
Face to Face Weekly Project Technical
Staff
Technical Lead Agenda
Meeting
Minutes
Project Steering
Committee Meetings
Report on the status of the
project to project steering
committee. Highlight any issues
and risks.
Face to Face
Conference Call
Monthly PMO Project Manager Agenda
Project schedule
Meeting
Minutes
Issues and Risks
Status
Project Reports Report the status of the project
including activities, risk, issues.
Email Weekly Project Sponsor
Project Team
Stakeholders
PMO
Project Manager Project Status
Report
Project schedule
COMMUNICATION MATRIX
5. WBS
ID
WBS Element Resource Direct
Costs
Indirect
Costs
Reserve Estimate Method Assumptions/
Constraints
Additional
Information
2.1.1 Development of
Registration Module
Junior Programmer
for 50 hours
50 hrs @
$18.00
= $900
$0 $18.00 $918.00 Parametric Resource approved
by functional
manager
2.1.2 Development of
Reporting Module
Junior Programmer
for 50 hours
50 hrs @
$18.00
= $900
$0 $18.00 $918.00 Parametric Resource approved
by functional
manager
2.1.2 Development of
Reporting Module
3 months license
extension for
Crystal Report
$0 $3,000 $0 $3,000 Quotation
from Vendor
Budget for
license
extension is
approved
2.1.3 Development of
Management
Dashboard
Senior Programmer
For 60 hours
60 hrs @
$28.00
= $1,680
$0 $33.60 $1,713.60 Parametric Functional
manager will
release resource
on schedule
ACTIVITY COST ESTIMATES
6. Risk
ID
Date
Raised
Risk
Description
Risk
Category
Probability Impact Severity Risk Owner
Risk Response
Strategy
R001 00/00/0000 Risk Description 1 System
Design
Low Medium 3 Francis Doe Risk Response 1
R002 00/00/0000 Risk Description 2 Coding Medium Medium 5 Remy Bobbit Risk Response 2
R003 00/00/0000 Risk Description 3 Operation High Low 4 Lee Chan Risk Response 3
R004 00/00/0000 Risk Description 4 Schedule Medium High 8 Francis Doe Risk Response 4
R005 00/00/0000 Risk Description 5 IT Infra Low High 6 Remy Bobbit Risk Response 5
R006 00/00/0000 Risk Description 6 IT Infra High Medium 7 Lee Chan Risk Response 6
R007 00/00/0000 Risk Description 7 IT Infra Low Low 1 Robert Brown Risk Response 7
R008 00/00/0000 Risk Description 8 IT Infra High High 9 Robert Brown Risk Response 8
RISK REGISTER
7. Project Planning
Project
Sponsor
Project
Manager
Project
Champion
Business
Analyst
System
Analyst
Developer Tester
Determine Detailed Requirements & Finalize
Project Scope
Create Activity List & Prepare WBS
Develop Project Schedule
Assess What To Purchase & Prepare
Procurement Document
Determine Project Team, Roles &
Responsibilities
Prepare Project Management Plan,
Communication, Risk & Quality Management
Plan
Conduct Kick-off Meeting
I A
C
RACI MATRIX
R
R
R
R
C R
A R R
R A C C
C I I
A C
I
I R
I I
I
A
I I I I I I
R A C
I C C C
C
C
R A I I I I I
I
8. Issue Description
Priority
(H, M, L)
Category Reported By
Assigned
To
Status
Date
Resolved
Resolution/ Comments
001 Issue 1 M Resources Remy Bobbit Lee Chan Closed 00/00/0000
002 Issue 2 H Schedule Lee Chan Francis Doe Open 00/00/0000
003 Issue 3 L Scope Francis Doe Remy Bobbit Closed 00/00/0000
004 Issue 4 L Scope Francis Doe Lee Chan Open 00/00/0000
005 Issue 5 M Scope Lee Chan Francis Doe Open 00/00/0000
006 Issue 6 M Scope Francis Doe Remy Bobbit Open 00/00/0000
007 Issue 7 L Scope Remy Bobbit Remy Bobbit Open 00/00/0000
ISSUE LOG