Technical and Business Offer
     e-commerce site
        束 ArtCase 損
         2012-07-30
         ORN186C1




                               1/26
sommaire


1 needs understanding
2 our approach


3 our commercial bid
4 our resources



                        2/26
our understanding
   of the need




                    3/26
your need               our understanding of the need



>   project ArtCase organized in 3 phases :
     -   phase 1:
               launch on Sosh.fr through a corner on their accessories shop
               a personalization module to integrate into the Sosh customer journey
               planning forecast : November 2012
     -   phase 2:
               Artcase standalone site for France with customer journey from A to Z
               planning forecast : Q1 2013                       1st launch on Sosh.fr, then Artcase standalone site
     -   phase 3:
               replication of Artcase standalone site for          Q4 2012          Q1 2013
                France in OK and Spain.                                        Corner Artcase on SOSH accessories
               all sites must be optimized for tablets                       shop
                                                                              Totally integrated into the Sosh customer journey.
                                                                              Exclusive artists on Sosh.

>   constraints :                                                                                    Artcase.com eShop (FR
                                                                                                    then UK tbc)
     -   design, customer experience and visual design                                              Standalone eshop
                                                                                                    Cross link with Orange Shop
         will be done by a web agency
                                                                                                                                 Mid term opportunity
     -   furniture of templates, zoning and PSD                                                                                  ArtCase corner on
                                                                                                                                 Orange accessories
                                                                                                                                 eshop?
                                                                    10                         interne France T辿l辿com - Orange




                                                             4/26
your need       the goals



> accessible and intuitive
> full functional coverage : content management, catalog and
  products management, customer spaces, order management, ...
> exchange security
    - compliance with norms and standards, best practices, 
    - lock access between servers
> ability to interface with your information system
> scalable solution to internal processes
> reduce your internal load and increase your Marketing chances
> respect of project schedule



                                    5/26
project management
methodology and process




                          6/26
Project methodology         A team working with agile software development methods

> Sequence of a release (version x.0)
          Sprint 0
                                  Sprint 1                 Sprint 2             Sprint n   End
         Initiation



> Project organized in sprint steps
    Initiating made by Product Owner :
        Defining features embedded in sprints : Product Backlog (to do list)
        Defining priority tasks (user stories)
    Evaluating made by the project team:
        Evaluating tasks duration (planning poker)
        Evaluating criteria defining the end of tasks
        Building the Sprint Backlog (To do list for each sprint)
    End of each sprint (Sprint review) :
        Showing work done through a demo and delivery for CIO
        Reporting problems
        Taking into account CIO feedbacks (bugs, changes)




                                                         7/26
Project methodology         A team working with agile software development methods

> Tools for agile software development
   The Product Backlog shows the entire to do list (user stories)
        some are well defined (forthcoming sprint)
        Other need to be reviewed


   Reporting
        Burn-up (or Burn-down) chart showing process




> Project steering process
   For each sprint review :
        Suggest features included for each sprint : Product Backlog
         (To Do List)
        Defining To do List (user stories)




                                                      8/26
Project methodology     Steering



> Profiles
      Project Director
      Project Leader
      Scrum Master
      Technical Expert (if needed)

> Project supervision
      Initiating
      Steering committee
      Steering committee/sprint review
      workshop/daily scrum

> reporting
    Workload consumption
    Defining roadmap
    Dashboard showing indicators




                                          9/26
Project methodology   Initiating



> Kick-off meeting
    Team presentations
    First roadmap with macro-planning

> Team organization
      Building core team and secondary teams
      Implementing project reports & reviews
      Development & integration platforms
      Tools for reviews

> Quality process
    Project Management Plan
    Risk & compliancy monitoring
    Indicators




                                          10/26
Project methodology      Roadmap



> Roadmap is a key document started during the project initiation meeting


> Roadmap lists the To Do list, the following items :
    Tasks and actions
    List of priority
    Continuous activities (corrective maintenance, support, steering,)
    Complet planning  tasks done by IT&L@bs and stakeholder, project steps


> Roadmap includes :
    MS-Project planning includes the entire list of activities, materials, profiles and reliance
    Budget dash board showing
         Workload used and wahr remains to be done,
         Several indicators for project governance




                                                  11/26
Project methodology      Risk management


> Identifying risks
      id                                  Identify
      Level
      Probality of occurrence
      List actions done to reduce risks                     Estimate              Periodic
                                                               -
                                                            re-estimate            iteration
      trends
                                                                              Defining and updating
> Recognization of probems                                                    actions to reduce risks
  occured et and impact
                                                          Follow efficiency
  analysis on risks in progress                               of actions


> Monitoring risk and actions
  done during the project                   Close risks
  committee.




                                           12/26
Project methodology   Service level management  indicators


> Quality of service is analyzed using indicators defined during
  initialization phase and tracked in reporting

> Indicators evolves depending on project needs & project progress

> Indicators are calculated at least monthly and analyzed during the
  Steering Committee

> Indicators are used by IT&L@bs to highlight through Dashboard
  the quality of service provided on the project




                                         13/26
Project methodology    Global steering process



>   Steering process                                    Steering Committee
       Steering committee
       Project committee                   Steering
                                        Progress meeting
                                     Coordination, monitoring
                                     (action plan, indicators)
                                             Planning
>   Risks management

>   Planning management                                          Project                         Project
                                                                 Manager                        Committee
                                       Synthesis                                 Production
>   Gestion des 辿carts             Visibility on delivery                       Documentation,
                                    Risk Management                                monitoring
                                   Decisions & actions                       Project communication
                                         Planning




                                                            Project team




                                                14/26
Process                 Identify project steps

                              Step 1

                         Initiation
                Staffing / Quality process
                  Risks / requirements




Features                      Step 2
                                                        Step 3
                 specifications / design                                          Step 4
                                                     Integration/                                          Step 5
                                                    Development             Acceptance /
                       Workshop                                               Delivery         Deployment / support
                                                   Setting Magento                                   Go live
                     Specifications
                                                                            Delivery and
                       Technical                   Graphic charter       Acceptance platform
                                                                                                   Production
                      Architecture                   integration             deployment
                                                                                                   deployment
                       Document
                                                      Custom             Internal acceptance       Operational
                                                    developement
                                                                                                   qualification
                      Web design
                                                                          Client acceptance
                                                   Documentations              support           Go live support
                     Validation / tests
                        document




                                             Steering and Quality process management




                                                                 15/26
our approach




               16/26
our approach      why Magento ?


> an industrialized and recognized solution in the market of e-commerce
  software
     - efficient and respectful of standards (security, architecture, ...)
     - a vibrant community,
     - popular solution that facilitates the recovery of activity in-house or by
       a third party.


> an open source software foundation scalable and interoperable
     - open source that allows own customizations to evolve,
     - integration capability with significant third-party products (via web
       services or connectors and Magento internal API).




                                     17/26
our approach                   an appropriate project organization


Technical host
  manager                                                            Customer Project
                                                                         manager

                                                     Reporting




                                                                                        CV
                                                                               CV
                          CV
                     CV


  Project director


                               Project                                             Project manager
  Quality engineer
                               manager

                                                                              Technical expert

                     Technical expert
                                                                                 Developer

                                                                             ERP Provider
       Developer                         Developer


           Integration technical team



                                                      18/26
our approach          methodology and experience appropriate to large project scope


> experience
    -   IT&L@bs has real experience on large projects that require :
              to interface and work with other supplier companies
              organize the site into production in line with the overall project schedule


> approach with Quality Assurance (CMMI 3)
    -   monitoring of a quality permits :
              well reference the different actors and roles
              better track and follow the requirements for the project and its processes
               (via the project dashboard)
              track and share risks
              optimize actions definition and implementation




                                            19/26
IT&L@bs bid




              20/26
Workload               workload total by project steps

    > Workload display bys steps and profiles
                                       Total workload      Project    Project
               Steps                                                            Expert   DEV
                                        (men / day)        Director   Leader
Project Initiation                          10                1         5         3       1
Specifications and technical
                                            32                          3        8,5     20,5
design

Development & unit tests                    76                                   21      55

Technical integration & internal
                                            17                                    7      10
acceptance test
Delivery / client acceptance tests
                                            18                          2         9       7
& deployment

Project steering                            21                3         18

Risks Management                            10                          1        3,5     5,5

3 months guarantee                          12                                    4       8

                               Total        196               4         29       56      107




                                                   21/26
our bid              commercial bid

                                                                                 Total in  (excluding
                       Steps                                 Workload / travel
                                                                                          VAT)
Project Initiation                                                  10                       6 530,00 
Specifications and technical design                                 32                      18 005,00 

Development & unit tests                                            76                      41 750,00 
Technical integration & internal acceptance test                    17                       9 500,00 
Delivery / client acceptance tests & deployment                     18                      10 470,00 
Project steering                                                    21                      14 640,00 
Risks Management                                                    10                       5 695,00 
3 months guarantee                                                  12                       6 640,00 
Options                                                             4                        2 120,00 
Travel expenses                                                  5 travels                   2 731,20 

                                                   Total           196                   115 961,20 

                        Total (including options)                  200                   118 081,20 


  >    General Terms of sales (available in Annex)


                                                     22/26
our bid             billing schedule (without options)


>   Billing terms and conditions and schedule


            Description                   Milestone          Total HTVA

    30% (order validation)                    T0             34 788,00 

    20 % delivery of
    specifications & technical          T0+4,5 weeks         23 192,00 
    design

    25 % delivery for client
                                       T0+ 12,5 weeks        28 990,30 
    acceptance test

    25 % operational                   En of operational
                                                             28 990,90 
    acceptance period ended              acceptance

    Total                                                  115 961,20  HT

>   General Terms of sales (available in Annex)


                                           23/26
our bid             project schedule


> schedule proposal with a T0 at 09/03/2012
   Step                       Marker         Cumulative time   Start date

   Launch                 T0 + 2 weeks      2 weeks            09/03/2012

   Design and
                          T1 + 4,5 weeks    2,5 weeks          09/17/2012
   specifications

   Development            T2 + 10,5 weeks   6 weeks            10/04/2012

   Internal tests (VAU)
                          T3 + 12,5 weeks   2 weeks            11/19/2012
   and delivery
                          T4 + 15 weeks
   End of acceptance
                          acceptance        2,5 weeks          12/03/2012
   support
                          support
                          Operationnal
   End of warranty        tests ended + 3   3 months           12/20/2012
                          month
> proposed dates
      production delivery date : 12/03/2012
      service phase start date : 12/20/2012


                                            24/26
our resources




                25/26
G辿rald Noc                            Anthony Le Postec
"Portal" segment manager              Presales manager

Phone    : +33 2 51 85 16 35          Phone    : +33 2.51.85.16.21
Fax      : +33 2 51 85 16 58          Fax      : +33 2 51 85 16 58
Mobile   : +33 6 72 79 72 04          Mobile   : +33 6.78.53.18.42
gerald.noc@orange.com                 anthony.lepostec@orange.com

Orange Business Services              Orange Business Services
Europarc La Chantrerie                Europarc La Chantrerie
9, boulevard Nic辿phore Niepce         9, boulevard Nic辿phore Niepce
44300 Nantes                          44300 Nantes




                          IT&Labs Nantes
                                                              26/26
Ad

Recommended

About Mosaic Learning Institute
About Mosaic Learning Institute
MosaicLearningInstitute
10 亶 仄亠亢亟仆舒仂亟仆亶 亟亠从亳亶 亠亳于舒仍 弍仂仍舒
10 亶 仄亠亢亟仆舒仂亟仆亶 亟亠从亳亶 亠亳于舒仍 弍仂仍舒
Sergio Dios
舒仂于亶 仗仂 - 亟亠于舒, 舒亰于亳亳亠 亟于仂仂于仂亞仂 仗仂舒仆于舒
舒仂于亶 仗仂 - 亟亠于舒, 舒亰于亳亳亠 亟于仂仂于仂亞仂 仗仂舒仆于舒
Sergio Dios
Corryn embass bods
Corryn embass bods
NJHolley
Typography assessment for SCA 2.0
Typography assessment for SCA 2.0
NJHolley
Nathan communication plan
Nathan communication plan
NJHolley
Wiki round up
Wiki round up
NJHolley
Teams novaya liga2012
Teams novaya liga2012
Sergio Dios
弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
Sergio Dios
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
Sergio Dios
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
Sergio Dios
"亳亰仆亠 亳亞亠"
"亳亰仆亠 亳亞亠"
Sergio Dios
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
Sergio Dios
Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"
Chris Trottier
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
Sergio Dios
CV_AliceParisis_en1
CV_AliceParisis_en1
Alice Parisis
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
AjayKumar626901
Case tools and modern process of system development
Case tools and modern process of system development
tushar217
Software project management- Software Engineering
Software project management- Software Engineering
Muhammad Yousuf Abdul Qadir
Asap overview
Asap overview
Lawrel Infotech Pvt Ltd
The Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 Talk
Yuval Yeret
SE_Module1new.ppt
SE_Module1new.ppt
ADARSHN40
Examples of projects of the business architecture
Examples of projects of the business architecture
Vasily Korablev
Why Scrum Why Now
Why Scrum Why Now
mtoppa
Agile planning with Rational Team Concert
Agile planning with Rational Team Concert
Reedy Feggins Jr
poss鱈vel medir se um gigante 辿 叩gil?
poss鱈vel medir se um gigante 辿 叩gil?
Alan Braz
Syed Shohaib CV
Syed Shohaib CV
imageologist
Syed Shohaib CV
Syed Shohaib CV
imageologist
SAP sample
SAP sample
cherry1206
I nearshore
I nearshore
Ciprian-Florin Hategan

More Related Content

Viewers also liked (7)

弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
Sergio Dios
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
Sergio Dios
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
Sergio Dios
"亳亰仆亠 亳亞亠"
"亳亰仆亠 亳亞亠"
Sergio Dios
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
Sergio Dios
Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"
Chris Trottier
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
Sergio Dios
弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
弍亳亰仆亠 仍亳亞舒 2014 仂仂舒仍弍仂仄 仂从亳 亳 1 舒
Sergio Dios
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
丕丐弌 仗仂 弍仂仍 亳 仄亳仆亳-弍仂仍 于 亠仍舒亳 (仂仄亠仍从舒 仂弍仍舒)
Sergio Dios
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
个 舒仍舒-个亠亳于舒仍 于 弌仂亳, 29.09-02.10 2016
Sergio Dios
"亳亰仆亠 亳亞亠"
"亳亰仆亠 亳亞亠"
Sergio Dios
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
亠亰亠仆舒亳 仗仂亞舒仄仄 仆亳于亠亳亠舒 "弌亳仆亠亞亳"
Sergio Dios
Designing Games for "the 43-year-old woman"
Designing Games for "the 43-year-old woman"
Chris Trottier
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
丼亠仄仗亳仂仆舒 "亳亰仆亠-仍亳亞舒" 于亠仆舒 2014 亞. 亰于从
Sergio Dios

Similar to Ptc saunier duval (20)

CV_AliceParisis_en1
CV_AliceParisis_en1
Alice Parisis
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
AjayKumar626901
Case tools and modern process of system development
Case tools and modern process of system development
tushar217
Software project management- Software Engineering
Software project management- Software Engineering
Muhammad Yousuf Abdul Qadir
Asap overview
Asap overview
Lawrel Infotech Pvt Ltd
The Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 Talk
Yuval Yeret
SE_Module1new.ppt
SE_Module1new.ppt
ADARSHN40
Examples of projects of the business architecture
Examples of projects of the business architecture
Vasily Korablev
Why Scrum Why Now
Why Scrum Why Now
mtoppa
Agile planning with Rational Team Concert
Agile planning with Rational Team Concert
Reedy Feggins Jr
poss鱈vel medir se um gigante 辿 叩gil?
poss鱈vel medir se um gigante 辿 叩gil?
Alan Braz
Syed Shohaib CV
Syed Shohaib CV
imageologist
Syed Shohaib CV
Syed Shohaib CV
imageologist
SAP sample
SAP sample
cherry1206
I nearshore
I nearshore
Ciprian-Florin Hategan
ERP solution architect role, part I
ERP solution architect role, part I
Viacheslav Nefedov
Metodolog鱈as agiles de desarrollo de software
Metodolog鱈as agiles de desarrollo de software
Juan Gomez
SDLC Methodologies
SDLC Methodologies
Ravikanth-BA
ASAP_Methodology.pptx
ASAP_Methodology.pptx
SridharSridhar314797
RTC & Work Item Customization Overview
RTC & Work Item Customization Overview
Bharat Malge
CV_AliceParisis_en1
CV_AliceParisis_en1
Alice Parisis
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
SMART APPLICATION DEVELOPMENT FOR THE RURAL COMMUNITY-c2c-unit-2-ppt.pptx
AjayKumar626901
Case tools and modern process of system development
Case tools and modern process of system development
tushar217
Software project management- Software Engineering
Software project management- Software Engineering
Muhammad Yousuf Abdul Qadir
The Secret of Flow - My AgileIL11 Talk
The Secret of Flow - My AgileIL11 Talk
Yuval Yeret
SE_Module1new.ppt
SE_Module1new.ppt
ADARSHN40
Examples of projects of the business architecture
Examples of projects of the business architecture
Vasily Korablev
Why Scrum Why Now
Why Scrum Why Now
mtoppa
Agile planning with Rational Team Concert
Agile planning with Rational Team Concert
Reedy Feggins Jr
poss鱈vel medir se um gigante 辿 叩gil?
poss鱈vel medir se um gigante 辿 叩gil?
Alan Braz
Syed Shohaib CV
Syed Shohaib CV
imageologist
Syed Shohaib CV
Syed Shohaib CV
imageologist
ERP solution architect role, part I
ERP solution architect role, part I
Viacheslav Nefedov
Metodolog鱈as agiles de desarrollo de software
Metodolog鱈as agiles de desarrollo de software
Juan Gomez
SDLC Methodologies
SDLC Methodologies
Ravikanth-BA
RTC & Work Item Customization Overview
RTC & Work Item Customization Overview
Bharat Malge
Ad

Ptc saunier duval

  • 1. Technical and Business Offer e-commerce site 束 ArtCase 損 2012-07-30 ORN186C1 1/26
  • 2. sommaire 1 needs understanding 2 our approach 3 our commercial bid 4 our resources 2/26
  • 3. our understanding of the need 3/26
  • 4. your need our understanding of the need > project ArtCase organized in 3 phases : - phase 1: launch on Sosh.fr through a corner on their accessories shop a personalization module to integrate into the Sosh customer journey planning forecast : November 2012 - phase 2: Artcase standalone site for France with customer journey from A to Z planning forecast : Q1 2013 1st launch on Sosh.fr, then Artcase standalone site - phase 3: replication of Artcase standalone site for Q4 2012 Q1 2013 France in OK and Spain. Corner Artcase on SOSH accessories all sites must be optimized for tablets shop Totally integrated into the Sosh customer journey. Exclusive artists on Sosh. > constraints : Artcase.com eShop (FR then UK tbc) - design, customer experience and visual design Standalone eshop Cross link with Orange Shop will be done by a web agency Mid term opportunity - furniture of templates, zoning and PSD ArtCase corner on Orange accessories eshop? 10 interne France T辿l辿com - Orange 4/26
  • 5. your need the goals > accessible and intuitive > full functional coverage : content management, catalog and products management, customer spaces, order management, ... > exchange security - compliance with norms and standards, best practices, - lock access between servers > ability to interface with your information system > scalable solution to internal processes > reduce your internal load and increase your Marketing chances > respect of project schedule 5/26
  • 7. Project methodology A team working with agile software development methods > Sequence of a release (version x.0) Sprint 0 Sprint 1 Sprint 2 Sprint n End Initiation > Project organized in sprint steps Initiating made by Product Owner : Defining features embedded in sprints : Product Backlog (to do list) Defining priority tasks (user stories) Evaluating made by the project team: Evaluating tasks duration (planning poker) Evaluating criteria defining the end of tasks Building the Sprint Backlog (To do list for each sprint) End of each sprint (Sprint review) : Showing work done through a demo and delivery for CIO Reporting problems Taking into account CIO feedbacks (bugs, changes) 7/26
  • 8. Project methodology A team working with agile software development methods > Tools for agile software development The Product Backlog shows the entire to do list (user stories) some are well defined (forthcoming sprint) Other need to be reviewed Reporting Burn-up (or Burn-down) chart showing process > Project steering process For each sprint review : Suggest features included for each sprint : Product Backlog (To Do List) Defining To do List (user stories) 8/26
  • 9. Project methodology Steering > Profiles Project Director Project Leader Scrum Master Technical Expert (if needed) > Project supervision Initiating Steering committee Steering committee/sprint review workshop/daily scrum > reporting Workload consumption Defining roadmap Dashboard showing indicators 9/26
  • 10. Project methodology Initiating > Kick-off meeting Team presentations First roadmap with macro-planning > Team organization Building core team and secondary teams Implementing project reports & reviews Development & integration platforms Tools for reviews > Quality process Project Management Plan Risk & compliancy monitoring Indicators 10/26
  • 11. Project methodology Roadmap > Roadmap is a key document started during the project initiation meeting > Roadmap lists the To Do list, the following items : Tasks and actions List of priority Continuous activities (corrective maintenance, support, steering,) Complet planning tasks done by IT&L@bs and stakeholder, project steps > Roadmap includes : MS-Project planning includes the entire list of activities, materials, profiles and reliance Budget dash board showing Workload used and wahr remains to be done, Several indicators for project governance 11/26
  • 12. Project methodology Risk management > Identifying risks id Identify Level Probality of occurrence List actions done to reduce risks Estimate Periodic - re-estimate iteration trends Defining and updating > Recognization of probems actions to reduce risks occured et and impact Follow efficiency analysis on risks in progress of actions > Monitoring risk and actions done during the project Close risks committee. 12/26
  • 13. Project methodology Service level management indicators > Quality of service is analyzed using indicators defined during initialization phase and tracked in reporting > Indicators evolves depending on project needs & project progress > Indicators are calculated at least monthly and analyzed during the Steering Committee > Indicators are used by IT&L@bs to highlight through Dashboard the quality of service provided on the project 13/26
  • 14. Project methodology Global steering process > Steering process Steering Committee Steering committee Project committee Steering Progress meeting Coordination, monitoring (action plan, indicators) Planning > Risks management > Planning management Project Project Manager Committee Synthesis Production > Gestion des 辿carts Visibility on delivery Documentation, Risk Management monitoring Decisions & actions Project communication Planning Project team 14/26
  • 15. Process Identify project steps Step 1 Initiation Staffing / Quality process Risks / requirements Features Step 2 Step 3 specifications / design Step 4 Integration/ Step 5 Development Acceptance / Workshop Delivery Deployment / support Setting Magento Go live Specifications Delivery and Technical Graphic charter Acceptance platform Production Architecture integration deployment deployment Document Custom Internal acceptance Operational developement qualification Web design Client acceptance Documentations support Go live support Validation / tests document Steering and Quality process management 15/26
  • 16. our approach 16/26
  • 17. our approach why Magento ? > an industrialized and recognized solution in the market of e-commerce software - efficient and respectful of standards (security, architecture, ...) - a vibrant community, - popular solution that facilitates the recovery of activity in-house or by a third party. > an open source software foundation scalable and interoperable - open source that allows own customizations to evolve, - integration capability with significant third-party products (via web services or connectors and Magento internal API). 17/26
  • 18. our approach an appropriate project organization Technical host manager Customer Project manager Reporting CV CV CV CV Project director Project Project manager Quality engineer manager Technical expert Technical expert Developer ERP Provider Developer Developer Integration technical team 18/26
  • 19. our approach methodology and experience appropriate to large project scope > experience - IT&L@bs has real experience on large projects that require : to interface and work with other supplier companies organize the site into production in line with the overall project schedule > approach with Quality Assurance (CMMI 3) - monitoring of a quality permits : well reference the different actors and roles better track and follow the requirements for the project and its processes (via the project dashboard) track and share risks optimize actions definition and implementation 19/26
  • 20. IT&L@bs bid 20/26
  • 21. Workload workload total by project steps > Workload display bys steps and profiles Total workload Project Project Steps Expert DEV (men / day) Director Leader Project Initiation 10 1 5 3 1 Specifications and technical 32 3 8,5 20,5 design Development & unit tests 76 21 55 Technical integration & internal 17 7 10 acceptance test Delivery / client acceptance tests 18 2 9 7 & deployment Project steering 21 3 18 Risks Management 10 1 3,5 5,5 3 months guarantee 12 4 8 Total 196 4 29 56 107 21/26
  • 22. our bid commercial bid Total in (excluding Steps Workload / travel VAT) Project Initiation 10 6 530,00 Specifications and technical design 32 18 005,00 Development & unit tests 76 41 750,00 Technical integration & internal acceptance test 17 9 500,00 Delivery / client acceptance tests & deployment 18 10 470,00 Project steering 21 14 640,00 Risks Management 10 5 695,00 3 months guarantee 12 6 640,00 Options 4 2 120,00 Travel expenses 5 travels 2 731,20 Total 196 115 961,20 Total (including options) 200 118 081,20 > General Terms of sales (available in Annex) 22/26
  • 23. our bid billing schedule (without options) > Billing terms and conditions and schedule Description Milestone Total HTVA 30% (order validation) T0 34 788,00 20 % delivery of specifications & technical T0+4,5 weeks 23 192,00 design 25 % delivery for client T0+ 12,5 weeks 28 990,30 acceptance test 25 % operational En of operational 28 990,90 acceptance period ended acceptance Total 115 961,20 HT > General Terms of sales (available in Annex) 23/26
  • 24. our bid project schedule > schedule proposal with a T0 at 09/03/2012 Step Marker Cumulative time Start date Launch T0 + 2 weeks 2 weeks 09/03/2012 Design and T1 + 4,5 weeks 2,5 weeks 09/17/2012 specifications Development T2 + 10,5 weeks 6 weeks 10/04/2012 Internal tests (VAU) T3 + 12,5 weeks 2 weeks 11/19/2012 and delivery T4 + 15 weeks End of acceptance acceptance 2,5 weeks 12/03/2012 support support Operationnal End of warranty tests ended + 3 3 months 12/20/2012 month > proposed dates production delivery date : 12/03/2012 service phase start date : 12/20/2012 24/26
  • 25. our resources 25/26
  • 26. G辿rald Noc Anthony Le Postec "Portal" segment manager Presales manager Phone : +33 2 51 85 16 35 Phone : +33 2.51.85.16.21 Fax : +33 2 51 85 16 58 Fax : +33 2 51 85 16 58 Mobile : +33 6 72 79 72 04 Mobile : +33 6.78.53.18.42 gerald.noc@orange.com anthony.lepostec@orange.com Orange Business Services Orange Business Services Europarc La Chantrerie Europarc La Chantrerie 9, boulevard Nic辿phore Niepce 9, boulevard Nic辿phore Niepce 44300 Nantes 44300 Nantes IT&Labs Nantes 26/26