This project summary is for a reef crushing project by Lonmin Eastern Platinum in Marikana, North-West from October 2009 to September 2013 with a value under R40 million. The project involved hard rock crushing of 1 million cubic meters of Merensky Reef for Lonmin Eastern Platinum with no consultants involved on the 48 month project.
1 of 1
Download to read offline
More Related Content
Reef crushing - Lonmin
1. www.construction.murrob.com
REEF CRUSHING - LONMIN
North-West, Marikana
PROJECT TYPE: CRUSHING
CLIENT:
Lonmin, Eastern Platinum
VALUE:
<R40 Million
CONSULTANTS:
None
PROJECT DURATION:
48 Months
DATE OF PROJECT:
1 October 2009
PROJECT DESCRIPTION:
Hard Rock, crushing of Merensky Reef.
Approximate volumes mined for the project :-
Crushing Merensky Reef 1,000,000 m続