2014 SUMMER INTERNSHIP REPORT ON SCB
MEDICAL PROJECT
Manisha Senapati
ACM
ABOUT THE COMPANY
ECC :
 The Engineering Construction and Contracts Division of L&T is Indias largest
construction organisation with over 60 years of experience and expertise in the
field. ECC figures among the Worlds Top Contractors and ranks 35th among top
global contractors and 60th among international contractors as per the survey
conducted by Engineering News Record magazine, USA (August2008).
 ECC is equipped with the requisite expertise and wide-ranging experience to
undertake Engineering Procurement and Construction (EPC) projects with single
source responsibility. Contracts are executed using state of the art design tools
and project management techniques from concept to commissioning.
MISSION:
 To achieve excellence in the field of Engineering, Procurement and Construction
through world class practice and standards in Quality, Safety and Project
Management.
VISION:
 L&T shall be a professionally-managed Indian Multinational, committed to total
customer satisfaction and enhancing shareholder value.
 L&T-ites shall be an innovative, entrepreneurial and empowered team constantly
creating value and attaining global benchmark.
 L&T shall foster a culture of caring, trust and continuous learning while meeting
expectations of employees, stakeholders and society
PROJECT DETAILS
 Name of the Company : M/S. LARSEN & TOUBRO LTD.
 Name of the project : Infrastructure Development of
SCB MEDICAL COLLEGE, Cuttack.
 Place of Work : CUTTACK,ODISHA
 Project In-Charge : Mr SANDEEP KUMAR GARG
 Company Address : M/S. LARSEN & TOUBRO LTD.
BUILDING & FACTORIES IC
11TH FLOOR, TOWER 2,
GODREJ WATER SITEDP5,
SECTOR 5, SALT LAKE
KOLKATA - 700091.
PROJECT OVERVIEW
SCB MEDICAL PROJECT
 Owner : Works Department,Govt
Of Odisha
 Resident Architect : EDRC
 Structural Consultant : EDRC
 Main Contractor : L&T Construction, B&F IC
 Type of contract : Lumpsum Contract
 Plot Area : 52279 Sq.m
 Total BU : 52279 Sq.m
 Contract Value : 147.4 crores
 Commencement Of Project : Jan 3,2014
 Duration : 24 months
Report
I worked under the following departments each for duration of 15
days starting with safety induction for 3 days.
 SAFETY : 3 day induction by Mr.MOHAMMAD
ASHIQUE
 QUALITY : 15 days by Mr. SATYAJIT DAS
 DRAWING : 10 days by Mr. VINSHNUMURTY
ACHARYA
 EXECUTION : 15 days by Mr. RINTU BAKSI
 PLANNING : 15 days by Mr. SHIBASHISH KAR
DRAWING
WHY TO SWITCH FROM CAD TO BIM?
 BIM Reduces Rework
 BIM Improves Productivity
 BIM Reduces Conflicts and Changes During Construction
 Clash Detection and Avoiding Rework
 BIM Marketing
 Project Outcome
 Reduced Errors
 BIM New Services
 Reducing Rework
CAD BIM
EXECUTION
PILING:
Pile Boring
 The piles shall be installed as accurately as possible to the vertical. The
permissible positional deviation for piles shall not exceed 75 mm or D/6
whichever is less (75 mm or D/10 whichever is more in case of piles having
diameter more than 600 mm) from their designed positions at the working
level. In the case of single pile under a column the positional deviation should
not be more than 50 mm or D/6 whichever is less (10 mm in case of piles
having diameter more than 600 mm) and the deviation from specified
alignment shall not exceed 1.5% of pile length.
 A protective temporary steel guide casing of suitable length, shall be provided
to prevent displacement of earth and for retention of surface water
 Boring operation generally started with bailer and then chisel by adopting
direct mud circulation method, by using Bentonite solution. The size of the
cutting tool should not be less than the diameter of the pile by more than
75mm
 Flushing of borehole shall be done before lowering of reinforcement cage and
then sounding to be taken. The specific gravity of the mud suspension near
about the bottom of the hole should not be more than 1.12, determined by
suitable slurry sampler. The slurry should be maintained at 1.5m above
ground water level.
Report
Reinforcement
o The area of longitudinal reinforcement within the pile shaft should be
as per approved drawing. Lapping for vertical bars to be staggered in
manner as specified in drawing and minimum cover to be maintained
by 50 mm in pile shaft.
Concreting
 Concrete shall be M30 grade unless otherwise called for.
 Diameter of Tremie shall be preferably 150mm for 20mm down
aggregates. Volume of hopper shall be greater than total volume of
Tremies to be used. Tremie pipes should be neat, clean & water
tight.
 The bottom of the tremie pipe should be kept above the bottom of
the bore by at least 300mm for first pour and should always inside
the concrete after first pour of concrete. First charge of concrete
shall be done using a stopper at the bottom of the funnel.
 In case of withdrawal of tremie out of concrete, either accidentally or
to remove a choke in the tremie,the tremie may be re-introduced by
about 60 to 1OOcmwith plug and introducing a little richer concrete
of about 200mm for easy displacement of the partly set concrete.
Report
 Area:- 322.4Sqm
 Cost:- 20 lakhs
The temporary structure is divided into two main parts:
 Main Office : 114.4sqm
 Temporary Office : 208 sqm
Main Office consists of:
 PM Office
 Planning Department
 Execution Department
 Accounts Department
 QA/QC Office
 Safety
 P&M Office
 Conference Room
 Pantry
 Toilet
Temporary Office Consists Of:
 Cement Godown
 Store
 Dining Hall
TEMPORARY STRUCTURE
Report
PLANNING
In my tenure i went through 3 sections:
 Planning &Contract Documents
 Scheduling
 Billing
CONTRACT CONDITIONS:
 Mobilization advance : 10% of CV
 Liquidated damages : 0.5% of CV
 Contract type : Lumpsum contract
 Retention : 8.09% of revised CV
 Performance bank guarantee : 10% of CV
 Defect liability period : 1 year
CONTRACT VALUE- 147.4 crores
FUNCTION OF PLANNING DEPARTMENT:
 Scheduling
 Resource allocation
 Progress report generation
 Monitoring of the schedule
OVERVIEW PLANNING SCHEDULE:
F:lnt internshipNew Schedule SCB.mpp
PLANNING
MIS BILLING
SUB-CONTRACTOR CLIENT
QUANTITY
SURVEY
MEASUREMENTS
OBSERVATION:
 Unsafe working conditions at site.
 Delay in project due to non-finalisation of vendor
 Wrong selection of contractors.
 Decrease in labour productivity due to bad weather conditions,
political issues, elections and festive season.
 Improper study of drawings leading to cost of rework.
 Lack of coordination between different parties
RECOMMENDATION:
 Proper planning should be done to avoid delay during monsoon
or bad weather.
 There should be proper labor management.
 Quality department should stick to the standards and
specifications to avoid any NCRs.
 If there is any open NCR , it should be closed as soon as
possible.
 Detailed and clear study of drawings should be done before it is
being executed to avoid rework.
 There should be proper communication between the parties.

More Related Content

Report

  • 1. 2014 SUMMER INTERNSHIP REPORT ON SCB MEDICAL PROJECT Manisha Senapati ACM
  • 2. ABOUT THE COMPANY ECC : The Engineering Construction and Contracts Division of L&T is Indias largest construction organisation with over 60 years of experience and expertise in the field. ECC figures among the Worlds Top Contractors and ranks 35th among top global contractors and 60th among international contractors as per the survey conducted by Engineering News Record magazine, USA (August2008). ECC is equipped with the requisite expertise and wide-ranging experience to undertake Engineering Procurement and Construction (EPC) projects with single source responsibility. Contracts are executed using state of the art design tools and project management techniques from concept to commissioning. MISSION: To achieve excellence in the field of Engineering, Procurement and Construction through world class practice and standards in Quality, Safety and Project Management. VISION: L&T shall be a professionally-managed Indian Multinational, committed to total customer satisfaction and enhancing shareholder value. L&T-ites shall be an innovative, entrepreneurial and empowered team constantly creating value and attaining global benchmark. L&T shall foster a culture of caring, trust and continuous learning while meeting expectations of employees, stakeholders and society
  • 3. PROJECT DETAILS Name of the Company : M/S. LARSEN & TOUBRO LTD. Name of the project : Infrastructure Development of SCB MEDICAL COLLEGE, Cuttack. Place of Work : CUTTACK,ODISHA Project In-Charge : Mr SANDEEP KUMAR GARG Company Address : M/S. LARSEN & TOUBRO LTD. BUILDING & FACTORIES IC 11TH FLOOR, TOWER 2, GODREJ WATER SITEDP5, SECTOR 5, SALT LAKE KOLKATA - 700091.
  • 4. PROJECT OVERVIEW SCB MEDICAL PROJECT Owner : Works Department,Govt Of Odisha Resident Architect : EDRC Structural Consultant : EDRC Main Contractor : L&T Construction, B&F IC Type of contract : Lumpsum Contract Plot Area : 52279 Sq.m Total BU : 52279 Sq.m Contract Value : 147.4 crores Commencement Of Project : Jan 3,2014 Duration : 24 months
  • 6. I worked under the following departments each for duration of 15 days starting with safety induction for 3 days. SAFETY : 3 day induction by Mr.MOHAMMAD ASHIQUE QUALITY : 15 days by Mr. SATYAJIT DAS DRAWING : 10 days by Mr. VINSHNUMURTY ACHARYA EXECUTION : 15 days by Mr. RINTU BAKSI PLANNING : 15 days by Mr. SHIBASHISH KAR
  • 7. DRAWING WHY TO SWITCH FROM CAD TO BIM? BIM Reduces Rework BIM Improves Productivity BIM Reduces Conflicts and Changes During Construction Clash Detection and Avoiding Rework BIM Marketing Project Outcome Reduced Errors BIM New Services Reducing Rework
  • 9. EXECUTION PILING: Pile Boring The piles shall be installed as accurately as possible to the vertical. The permissible positional deviation for piles shall not exceed 75 mm or D/6 whichever is less (75 mm or D/10 whichever is more in case of piles having diameter more than 600 mm) from their designed positions at the working level. In the case of single pile under a column the positional deviation should not be more than 50 mm or D/6 whichever is less (10 mm in case of piles having diameter more than 600 mm) and the deviation from specified alignment shall not exceed 1.5% of pile length. A protective temporary steel guide casing of suitable length, shall be provided to prevent displacement of earth and for retention of surface water Boring operation generally started with bailer and then chisel by adopting direct mud circulation method, by using Bentonite solution. The size of the cutting tool should not be less than the diameter of the pile by more than 75mm Flushing of borehole shall be done before lowering of reinforcement cage and then sounding to be taken. The specific gravity of the mud suspension near about the bottom of the hole should not be more than 1.12, determined by suitable slurry sampler. The slurry should be maintained at 1.5m above ground water level.
  • 11. Reinforcement o The area of longitudinal reinforcement within the pile shaft should be as per approved drawing. Lapping for vertical bars to be staggered in manner as specified in drawing and minimum cover to be maintained by 50 mm in pile shaft. Concreting Concrete shall be M30 grade unless otherwise called for. Diameter of Tremie shall be preferably 150mm for 20mm down aggregates. Volume of hopper shall be greater than total volume of Tremies to be used. Tremie pipes should be neat, clean & water tight. The bottom of the tremie pipe should be kept above the bottom of the bore by at least 300mm for first pour and should always inside the concrete after first pour of concrete. First charge of concrete shall be done using a stopper at the bottom of the funnel. In case of withdrawal of tremie out of concrete, either accidentally or to remove a choke in the tremie,the tremie may be re-introduced by about 60 to 1OOcmwith plug and introducing a little richer concrete of about 200mm for easy displacement of the partly set concrete.
  • 13. Area:- 322.4Sqm Cost:- 20 lakhs The temporary structure is divided into two main parts: Main Office : 114.4sqm Temporary Office : 208 sqm Main Office consists of: PM Office Planning Department Execution Department Accounts Department QA/QC Office Safety P&M Office Conference Room Pantry Toilet Temporary Office Consists Of: Cement Godown Store Dining Hall TEMPORARY STRUCTURE
  • 15. PLANNING In my tenure i went through 3 sections: Planning &Contract Documents Scheduling Billing CONTRACT CONDITIONS: Mobilization advance : 10% of CV Liquidated damages : 0.5% of CV Contract type : Lumpsum contract Retention : 8.09% of revised CV Performance bank guarantee : 10% of CV Defect liability period : 1 year CONTRACT VALUE- 147.4 crores
  • 16. FUNCTION OF PLANNING DEPARTMENT: Scheduling Resource allocation Progress report generation Monitoring of the schedule OVERVIEW PLANNING SCHEDULE: F:lnt internshipNew Schedule SCB.mpp PLANNING MIS BILLING SUB-CONTRACTOR CLIENT QUANTITY SURVEY MEASUREMENTS
  • 17. OBSERVATION: Unsafe working conditions at site. Delay in project due to non-finalisation of vendor Wrong selection of contractors. Decrease in labour productivity due to bad weather conditions, political issues, elections and festive season. Improper study of drawings leading to cost of rework. Lack of coordination between different parties RECOMMENDATION: Proper planning should be done to avoid delay during monsoon or bad weather. There should be proper labor management. Quality department should stick to the standards and specifications to avoid any NCRs. If there is any open NCR , it should be closed as soon as possible. Detailed and clear study of drawings should be done before it is being executed to avoid rework. There should be proper communication between the parties.