The document provides instructions for ATP train testing on the Down Main line between Gosford and Wyong on specified nights in May 2017. It summarizes that:
1) A Qualified Worker must obtain a Local Possession Authority and communicate the possession limits and test requirements to the Train Crew.
2) During the possession, only the special test train can use the Down Main line; no fixed worksites, work trains or track vehicles are permitted on the line.
3) Pilot staff working will be introduced on the Up Main line between Wyong and Gosford signals, and any work on track in the pilot staff section must follow Network Rules and Procedures.
1 of 2
Download to read offline
More Related Content
Safe notice 146 152 165
1. F O R T H E I N F O R M A T I O N O F E M P L O Y E E S A N D N O T F O R P U B L I C A T I O N
2017SAFE Notice
SAFE Notice No. 152 – 2017 Page 1
ATP – TESTING
Approval is given for ATP train testing on the
Down Main line between Gosford and Wyong
in accordance with the possession arrangements
detailed in Special Train Notice No. 0601 – 2017.
A Qualified Worker must be provided to carry out
the following:
• Obtain a Local Possession Authority in
accordance with the procedures shown in NWT 302
for the defined portion of track as shown in Special
Train Notice No. 0601 – 2017.
• Come to a clear and proper understanding with
the Train Crew in regards to the possession
limits, the test area limits and all train
operational requirements to carry out the
testing.
• For any wrong direction movements, any facing
points must be secured with a point clip and be
locked unless the signal protecting the points
can be cleared.
• Authorise the special train to run in both the Up
and Down directions within the possession area
as required.
During this working, the Driver must operate the
train from the leading carriage in the direction of
travel at ALL times.
ENGINEERING WORK
During the possession NO fixed worksites, work
trains or track vehicles will be permitted to traverse
or occupy the Down Main line (except for the
passage of the special train to be used for testing)
within the possession area.
No persons other than those associated with the
train testing are permitted within the possession
area.
152
GOSFORD – WYONG
On Monday night/Tuesday morning, 15 – 16 May 2017
On Tuesday night/Wednesday morning, 16 – 17 May 2017
On Wednesday night/Thursday morning, 17 – 18 May 2017
On Thursday night/Friday morning, 18 – 19 May 2017
In conjunction with Special Train Notice No. 0601 – 2017, the following Safeworking arrangements will apply:
PILOT STAFF WORKING
(UP MAIN LINE): WYONG –
GOSFORD
Pilot staff working in accordance with the procedures
shown in NSY 516 will be introduced on the Up
Main line between Signal No. WG8 and WG6 at
Wyong and Signal No. GF112 at Gosford.
WORK ON TRACK
Any work on track to be performed in the Pilot Staff
Working section must be in accordance with the
Network Rules and Network Procedures.
2. 
F O R T H E I N F O R M A T I O N O F E M P L O Y E E S A N D N O T F O R P U B L I C A T I O N
SYDNEY, 4 MAY 2017 GROUP MANAGER SAFETY AND STANDARDS SYDNEY TRAINS
Returned to Controlling Manager: Date: .................................... Signed: ................................................................
(Cut along this line and forward the detached receipt to your Controlling Manager)
To Controlling Manager: ...................................................................................................................................................
Received SAFE Notice No. 152 – 2017 Date: ................................ Signed: .............................................................
Name (print): .................................................................. Location: .............................................................................
(Controlling Manager to retain this Acknowledgment of Receipt of the SAFE Notice for record purposes for 90 days.)
SAFE Notice No. 152 – 2017 Page 2