This document outlines a 27 task, 299 day project schedule to construct a multi-section building. Key tasks include mobilizing on site, clearing the land, digging foundations, placing rebar, pouring concrete slabs and floors, erecting steel framing, installing doors/windows, painting, adding landscaping, and demobilizing. The schedule notes one section is a single story with a garden roof and the other is two stories with solar panels installed above.
1 of 2
Download to read offline
More Related Content
Schedule
1. ######
######
11-Jun
18-Jun
25-Jun
16-Jul
23-Jul
30-Jul
4-Jun
2-Jul
9-Jul
Task No. Tasks Duration Begin Date End Date
1 Mobilize 2 21-May-12 23-May-12
2 Clear Site 4 24-May-12 28-May-12
3 Set Stakes 4 29-May-12 2-Jun-12
4 Dig Foundations 8 3-Jun-12 11-Jun-12
5 Clean up 4 12-Jun-12 16-Jun-12
6 Set Forms 4 17-Jun-12 21-Jun-12
7 Place Rebars 8 22-Jun-12 30-Jun-12
8 *Place Rebar/Forms for Floor Beams System 20 1-Jul-12 21-Jul-12
9 Place Slab 12 22-Jul-12 3-Aug-12
10 Strip Forms 2 4-Aug-12 6-Aug-12
11 Place Steel Anchors 4 7-Aug-12 11-Aug-12
12 Place and Erect Steel Framing 20 12-Aug-12 1-Sep-12
13 *Place Beam and Girder System on 1st level Section A & B 12 2-Sep-12 14-Sep-12
14 Pour Concrete on Roof of Section A 12 15-Sep-12 27-Sep-12
15 *Place Joist system on 2nd level Section B 16 28-Sep-12 14-Oct-12
16 Pour Concrete on 1st and 2nd level of Section B 30 15-Oct-12 14-Nov-12
17 Build Parapet and Drainage System on Section A Roof 15 15-Nov-12 30-Nov-12
*Add Solar Panels on Roof Section B 8 1-Dec-12 9-Dec-12
18 Gutters 4 10-Dec-12 14-Dec-12
19 Walls 14 15-Dec-12 29-Dec-12
20 *Doors & Windows & Other Interior Detail 20 30-Dec-12 19-Jan-13
21 Painting 24 20-Jan-13 13-Feb-13
22 Place Sidewalk Forms and Rebar 14 14-Feb-13 28-Feb-13
23 Pour Sidewalk Concrete 14 1-Mar-13 15-Mar-13
24
Add Asphalt, Sub-base, and Base in Parking Area and Driveway 14 16-Mar-13 30-Mar-13
25 Place Landscaping 4 31-Mar-13 4-Apr-13
26 Clean up 4 5-Apr-13 9-Apr-13
27 Demobilize 2 10-Apr-13 12-Apr-13
Total Time 299
Note:Section A is one story and has a garden on the roof. Section B is two story and has solar panels above.
*Utilities and M&E System addition