Granite State Business Park
Project of the Year 2012
TIF District Case Study
Seacoast Leadership Economic Development Day

May 1, 2013
Business Park Development 1989
Howard Katz, Developer
 Phase 1  97 Ac
 Phase 2  55 Ac
 No Access to Phase 2

 Off to a Great Start!
 Prime Tanning 1994
 Salmon Falls Precision
1994
 Techniweave 1999
 Frisbie Hospital Secure
Storage 1999

 Pease International
Tradeport 1992
Granite State Business Park 2010
 62.2% of Phase 1 is
developed
 421,500 sq ft/ 5bldg
 425 Employees
 Assessed for Taxes
$15,740,000
 Payroll $19 MM

 Manufacturing Changes
 Prime Tanning
closed, Rand-Whitney
Corp.
 Salmon Falls Precision
closed, Multi-Tenant
 Techniweave acquired by
Albany International, bldg
expansion in 2007
 Industrial Condos 2006 &
2009

 Still owned by same
developer
Aerial View
Local Economic Challenges
 Great Recession
 Existing Companies
with Unique Products
 Thompson Center Arms
announces relocation to
 Advanced
Manufacturing
MA  INCENTIVES!
 Composite Materials
 Lack of available Capital,
 Developer willing to
increased underwriting
sell @ discount
standards
 Expansion
 Lots of available real
opportunities
estate  CHEAP!
 Transition in required mfg
skills
TIF District & Program Plan
Financing & Development Program Plan:



Defines district, budget, use of funds, etc.
Adopt by public hearing. See RSA 162-K:6 and 162-K:9.

Plans must contain a complete statement as to the
public facilities to be constructed, the open space to
be created, the environmental controls to be
applied, the proposed reuse of private property, and
the proposed operations of the district after the
capital improvements within the district have been
completed.
Important Features!
Multiple TIF Districts are
allowed, HOWEVER:
 Do not exceed 8% of
Assessed Value for
community (or
 16% for all combined with
districts that have
outstanding bonds);
OR,
 5% of total acreage! (or
10% of total acreage for
bonds outstanding)

 Increment only accrues
after date district is
established!
 Values as of April 1.
 Bonds  First payment
must be within 5 years.
 Last payment no later than
30 years.
 Bonds are NOT to be
included when computing
the municipality's net debt
under RSA 33.
TIF Example
Pre-construction or Original value = $1,000,000
Post Construction Value = $50,000,000
 Increment or Captured Value = $49,000,000
 Tax revenue on $1,000,000 Original value =
 $25,000 ($25 / $1,000 A.V. Tax Rate)
 Tax revenue on increment = $1,225,000
 $25,000 to General Fund
 $1,225,000 to TIF for debt service, operating costs,
maintenance & reserves.
Increment Value is based on April 1st each year
Critical Deal Components
 Internationally Competitive
RFPs
 Two Partners
 Incentives - on-site and offsite +$9 M
 blighted location
 RSA 205 never used

 City investment in BIG
infrastructure +$5 Million
 Access to Site
 Wetland mitigation package
 Utilities, relocation of PSNH
transmission lines

 Critical Timing of
Construction

 Collaborative Partnerships






City Staff & Elected Officials
DRED, DES (EPA, Army Corp)
Governor Lynch
NH Northcoast RR
PSNH, Unitil, FairPoint

 Labor availability & cost
 Skills shortfall

 Training program for 20+
years worth of employees
 Great Bay Community College
 Creteau Technology Center
 Advanced programs

 $4 M NH, $19.9 M US
Safran/Albany LEAP Facility
This Albany & Safran
project will create:






343,000 ft2 facility + 90,000 ft2 exp
$100MM CAPEX
55 acres under agreement for exp

689 FT jobs
$41MM Annual Payroll
911 indirect jobs
$27.5MM Payroll
Total Economic Output
(NH) $232,781,044

Tax Increment pledged for
~15 years to debt
service of $9 MM
Granite State Business Park 2013
 Expanded to 252 ac
 Development District
 +$5M Infrastructure

 Incentives





TIF District
ERZ Tax Credits (NH)
R&D Tax Credit (NH)
FTZ (US)

 Anticipated Development
 50 Acres Under Agr.
 Lot #1 Sold  Jan 2013
 Lot #33, 34, 35 Avail.
 102 Addl Acres under
Investigation

2003 Value $5,128,800 330,865 ft2
2012 Curr Value $14,712,207 +186.854% inc
423,666 ft2 Revenue $359,689
2030 Est. Value $34,740,000 +236.13% inc.
1,596,900 ft2 Revenue $892,223
If its happening in NH,
its happening in Rochester!
- Economic Development
- Planning, Zoning
- Code Enforcement
- Building Safety
@RochesterEDC
www.thinkrochester.biz

Karen Pollard, CEcD, EDP
Deputy City Manager/Director
Community Development Division
Karen.pollard@rochesternh.net

More Related Content

Seacoast Leadership 2013 TIF Case Study

  • 1. Granite State Business Park Project of the Year 2012 TIF District Case Study Seacoast Leadership Economic Development Day May 1, 2013
  • 2. Business Park Development 1989 Howard Katz, Developer Phase 1 97 Ac Phase 2 55 Ac No Access to Phase 2 Off to a Great Start! Prime Tanning 1994 Salmon Falls Precision 1994 Techniweave 1999 Frisbie Hospital Secure Storage 1999 Pease International Tradeport 1992
  • 3. Granite State Business Park 2010 62.2% of Phase 1 is developed 421,500 sq ft/ 5bldg 425 Employees Assessed for Taxes $15,740,000 Payroll $19 MM Manufacturing Changes Prime Tanning closed, Rand-Whitney Corp. Salmon Falls Precision closed, Multi-Tenant Techniweave acquired by Albany International, bldg expansion in 2007 Industrial Condos 2006 & 2009 Still owned by same developer
  • 5. Local Economic Challenges Great Recession Existing Companies with Unique Products Thompson Center Arms announces relocation to Advanced Manufacturing MA INCENTIVES! Composite Materials Lack of available Capital, Developer willing to increased underwriting sell @ discount standards Expansion Lots of available real opportunities estate CHEAP! Transition in required mfg skills
  • 6. TIF District & Program Plan Financing & Development Program Plan: Defines district, budget, use of funds, etc. Adopt by public hearing. See RSA 162-K:6 and 162-K:9. Plans must contain a complete statement as to the public facilities to be constructed, the open space to be created, the environmental controls to be applied, the proposed reuse of private property, and the proposed operations of the district after the capital improvements within the district have been completed.
  • 7. Important Features! Multiple TIF Districts are allowed, HOWEVER: Do not exceed 8% of Assessed Value for community (or 16% for all combined with districts that have outstanding bonds); OR, 5% of total acreage! (or 10% of total acreage for bonds outstanding) Increment only accrues after date district is established! Values as of April 1. Bonds First payment must be within 5 years. Last payment no later than 30 years. Bonds are NOT to be included when computing the municipality's net debt under RSA 33.
  • 8. TIF Example Pre-construction or Original value = $1,000,000 Post Construction Value = $50,000,000 Increment or Captured Value = $49,000,000 Tax revenue on $1,000,000 Original value = $25,000 ($25 / $1,000 A.V. Tax Rate) Tax revenue on increment = $1,225,000 $25,000 to General Fund $1,225,000 to TIF for debt service, operating costs, maintenance & reserves. Increment Value is based on April 1st each year
  • 9. Critical Deal Components Internationally Competitive RFPs Two Partners Incentives - on-site and offsite +$9 M blighted location RSA 205 never used City investment in BIG infrastructure +$5 Million Access to Site Wetland mitigation package Utilities, relocation of PSNH transmission lines Critical Timing of Construction Collaborative Partnerships City Staff & Elected Officials DRED, DES (EPA, Army Corp) Governor Lynch NH Northcoast RR PSNH, Unitil, FairPoint Labor availability & cost Skills shortfall Training program for 20+ years worth of employees Great Bay Community College Creteau Technology Center Advanced programs $4 M NH, $19.9 M US
  • 10. Safran/Albany LEAP Facility This Albany & Safran project will create: 343,000 ft2 facility + 90,000 ft2 exp $100MM CAPEX 55 acres under agreement for exp 689 FT jobs $41MM Annual Payroll 911 indirect jobs $27.5MM Payroll Total Economic Output (NH) $232,781,044 Tax Increment pledged for ~15 years to debt service of $9 MM
  • 11. Granite State Business Park 2013 Expanded to 252 ac Development District +$5M Infrastructure Incentives TIF District ERZ Tax Credits (NH) R&D Tax Credit (NH) FTZ (US) Anticipated Development 50 Acres Under Agr. Lot #1 Sold Jan 2013 Lot #33, 34, 35 Avail. 102 Addl Acres under Investigation 2003 Value $5,128,800 330,865 ft2 2012 Curr Value $14,712,207 +186.854% inc 423,666 ft2 Revenue $359,689 2030 Est. Value $34,740,000 +236.13% inc. 1,596,900 ft2 Revenue $892,223
  • 12. If its happening in NH, its happening in Rochester! - Economic Development - Planning, Zoning - Code Enforcement - Building Safety @RochesterEDC www.thinkrochester.biz Karen Pollard, CEcD, EDP Deputy City Manager/Director Community Development Division Karen.pollard@rochesternh.net