Seahurst Project Update - March 17 presentation to City Council
Groundbreaking: September 16, 2013
Seahurst Project Update - March 17 presentation to City Council
Construction Phase Contractors
 USACE: Project Partner and Construction Management
 CKY Inc. : Prime Contractor (San Pedro, CA)
 SCI Infrastructure: Grading/Earthwork (SeaTac, WA)
 Cadman Inc.: Materials/Gravel/Sand (Redmond, WA)
 Northwest Lining and Geotextiles: (Kent, WA)
 Pacific Pile and Marine: Barge Services (Seattle, WA)
 Dutton Electrico Co.: (Lynwood, WA)
 Cal Portland: Concrete (Seattle, WA)
 Cherry Valley Logging: Wood materials (Duvall, WA)
 Play Creations: Playground (Burien, WA)
Park Closed: October 28, 2013
Project Footprint
Recap of Project Scope
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Seahurst Project Update - March 17 presentation to City Council
Project Challenges with
Impacts on Schedule and Costs
 Underground cultural resource
conditions
 Unknown utility conditions/
locations in specific areas
 New concrete work related to
future recreational costs
New Concrete Work
Updated
Project Schedule and Cost
 Original estimated date: May 17, 2014
 Revised completion date: July 11, 2014
 Original estimated cost: $7.7M
 Revised construction cost: $8.15M (+5.9%)
Source of Funds
State PSAR and $400,000
ESRP Grants
Burien General Fund $50,000
(addl concrete work)
Project Funding Partners
 Army Corps of Engineers
 Washington Department of Fish and
Wildlife (ESRP)
 Environmental Protection Agency (EPA)
 Salmon Recovery Funding Board (PSAR)
 King Conservation District
 Green-Duwamish Watershed Forum (WRIA-9)
 City of Burien

More Related Content

Seahurst Project Update - March 17 presentation to City Council

  • 4. Construction Phase Contractors USACE: Project Partner and Construction Management CKY Inc. : Prime Contractor (San Pedro, CA) SCI Infrastructure: Grading/Earthwork (SeaTac, WA) Cadman Inc.: Materials/Gravel/Sand (Redmond, WA) Northwest Lining and Geotextiles: (Kent, WA) Pacific Pile and Marine: Barge Services (Seattle, WA) Dutton Electrico Co.: (Lynwood, WA) Cal Portland: Concrete (Seattle, WA) Cherry Valley Logging: Wood materials (Duvall, WA) Play Creations: Playground (Burien, WA)
  • 24. Project Challenges with Impacts on Schedule and Costs Underground cultural resource conditions Unknown utility conditions/ locations in specific areas New concrete work related to future recreational costs
  • 26. Updated Project Schedule and Cost Original estimated date: May 17, 2014 Revised completion date: July 11, 2014 Original estimated cost: $7.7M Revised construction cost: $8.15M (+5.9%)
  • 27. Source of Funds State PSAR and $400,000 ESRP Grants Burien General Fund $50,000 (addl concrete work)
  • 28. Project Funding Partners Army Corps of Engineers Washington Department of Fish and Wildlife (ESRP) Environmental Protection Agency (EPA) Salmon Recovery Funding Board (PSAR) King Conservation District Green-Duwamish Watershed Forum (WRIA-9) City of Burien