The document is a bill of materials for temporary pipe supports between turbine building columns. It lists 9 items needed including adjustable clevis hangers, nuts, threaded rod, and clamps to securely support 6" and 8" pipes lacking permanent supports in that location. An engineering evaluation found the pipes were suspended only by cables and needed additional supports to withstand the weight of the pipe, which is calculated in the report. The engineer recommends installing new supports as shown in the attached sketch.
1 of 8
Download to read offline
More Related Content
SI58_SKETCHES_EVAL
7. BILL OF MATERIAL
Evaluator: Kevin Wilson Field Engineer Date: 9/6/11
Unit: 2 Building: Turbine Elevation: 649
Description of Material Order:
Material for temporary support of 6 & 8 pipe between Col. Rows T10 & T11 & D & H.
Materials:
Item No. Reqd Description
1 6 Adjustable Clevis Hanger, Anvil Fig. 260 for 8 Pipe, Plain Finish
2 16 他 Flat Washer, Matl: F436
3 24 他 Heavy Hex Nut, Matl: A563
4 8 他 Fully Threaded Round Bar, 16 Ft. Lg., Matl: A36 (Cut as Required)
5 5 Universal Beam Clamp, Anvil Fig. 292, Size 4 for 他 Rod, Plain Finish
6 3 Universal Beam Clamp, Anvil Fig. 292, Size 5 for 他 Rod, Plain Finish
7 1 Standard Riser Clamp, Anvil Fig. 40 for 8 Pipe, Matl: Carbon Steel, Plain Finish
8 2 Adjustable Clevis Hanger, Anvil Fig. 260 for 6 Pipe, Plain Finish
9 16 Rod Coupling, Anvil Fig. 135, for 他 Rod, Straight, Plain Finish
8. FIELD ENGINEERING EVALUATION SI58
Page 1 of 1
Evaluator: Kevin Wilson Field Engineer Date: 8/24/11
Unit: 2 Building: Turbine Elevation: Floor El. 649
Location: Between Col. Rows D and H and Col. Rows T9 and T11
References:
1. 3BW0404-OO-01 - Mechanical Drains and Vents & Misc. Piping
2. 3BW0404-OO-42 - Mechanical Drains and Vents & Misc. Piping
Problem Description:
There is an 8 Pipe running from condenser at a location approx. 16 West of Col. Row E to the south and
then parallel to Col Row T11 then thru a penetration in the floor to El. 629. The pipe has no permanent or
temporary supports installed. There are only cables and turnbuckles installed. There is also a 6 pipe that
runs parallel to the 8 pipe. The 6 pipe has some permanent supports installed, but it lacks about 3 of them. It
is also suspended by cables.
Evaluation Summary:
The piping is 8 Sch. 120 which weighs 60.63 lbs./lin. ft. The 6 piping is assumed to be Sch. 120 as well and
weighs 36.39 lbs/ lin. ft. The loads are calculated based on those assumptions. The loads calculated for each
support are shown on SI58_Sketch_1. New supports should be installed as shown on the attached sketches.