際際滷

際際滷Share a Scribd company logo
Software Project 
Management 
Chapter 8 
4th Edition 
Resource allocation 
1 息The McGraw-Hill Companies,
2 息The McGraw-Hill Companies, Schedules 
 Activity schedule - indicating start and 
completion dates for each activity 
 Resource schedule - indicating dates 
when resources needed + level of 
resources 
 Cost schedule showing accumulative 
expenditure
3 息The McGraw-Hill Companies, Resources 
 These include 
 labour 
 equipment (e.g. workstations) 
 materials 
 space 
 services 
 Time: elapsed time can often be reduced 
by adding more staff 
 Money: used to buy the other resources
Resource allocation 
4 息The McGraw-Hill Companies,  Identify the resources needed for each 
activity 
 Identify resource types - individuals are 
interchangeable within the group (e.g. 
VB programmers as opposed to 
software developers) 
 Allocate resource types to activities and 
examine the resource histogram
Resource histogram: 
systems analysts 
1 2 3 4 5 6 7 
WEEK 
5 息The McGraw-Hill Companies, 5 
REQD. 
4 
STAFF 3 
2 
1
Resource clashes 
6 息The McGraw-Hill Companies, can be resolved by: 
 delaying one of the activities 
 taking advantage of float to change start date 
 delaying start of one activity until finish of the 
other activity that resource is being used on - puts 
back project completion 
 moving resource from a non-critical activity 
 bringing in additional resource - increases 
costs
Prioritizing activities 
7 息The McGraw-Hill Companies, There are two main ways of doing this: 
 Total float priority  those with the 
smallest float have the highest priority 
 Ordered list priority  this takes account 
of the duration of the activity as well as 
the float  see next overhead
Burmans priority list 
8 息The McGraw-Hill Companies, Give priority to: 
 Shortest critical activities 
 Other critical activities 
 Shortest non-critical activities 
 Non-critical activities with least float 
 Non-critical activities
Resource usage 
9 息The McGraw-Hill Companies,  Need to maximise %usage of resources 
i.e. reduce idle periods between tasks 
 Need to balance costs against early 
completion date 
 Need to allow for contingency
Critical path 
10 息The McGraw-Hill Companies,  Scheduling resources can create new 
dependencies between activities  recall 
critical chains 
 It is best not to add dependencies to the 
activity network to reflect resource constraints 
 Makes network very messy 
 A resource constraint may disappear during the 
project, but link remains on network 
 Amend dates on schedule to reflect 
resource constraints
Allocating individuals to 
activities 
11 息The McGraw-Hill Companies, The initial resource types for a task have 
to be replaced by actual individuals. 
Factors to be considered: 
 Availability 
 Criticality 
 Risk 
 Training 
 Team building  and motivation
Cost schedules 
12 息The McGraw-Hill Companies, Cost schedules can now be produced: 
Costs include: 
 Staff costs 
 Overheads 
 Usage charges
Cost profile 
13 息The McGraw-Hill Companies,
Accumulative costs 
14 息The McGraw-Hill Companies,
Balancing concerns 
15 息The McGraw-Hill Companies,

More Related Content

Spm chapter 8

  • 1. Software Project Management Chapter 8 4th Edition Resource allocation 1 息The McGraw-Hill Companies,
  • 2. 2 息The McGraw-Hill Companies, Schedules Activity schedule - indicating start and completion dates for each activity Resource schedule - indicating dates when resources needed + level of resources Cost schedule showing accumulative expenditure
  • 3. 3 息The McGraw-Hill Companies, Resources These include labour equipment (e.g. workstations) materials space services Time: elapsed time can often be reduced by adding more staff Money: used to buy the other resources
  • 4. Resource allocation 4 息The McGraw-Hill Companies, Identify the resources needed for each activity Identify resource types - individuals are interchangeable within the group (e.g. VB programmers as opposed to software developers) Allocate resource types to activities and examine the resource histogram
  • 5. Resource histogram: systems analysts 1 2 3 4 5 6 7 WEEK 5 息The McGraw-Hill Companies, 5 REQD. 4 STAFF 3 2 1
  • 6. Resource clashes 6 息The McGraw-Hill Companies, can be resolved by: delaying one of the activities taking advantage of float to change start date delaying start of one activity until finish of the other activity that resource is being used on - puts back project completion moving resource from a non-critical activity bringing in additional resource - increases costs
  • 7. Prioritizing activities 7 息The McGraw-Hill Companies, There are two main ways of doing this: Total float priority those with the smallest float have the highest priority Ordered list priority this takes account of the duration of the activity as well as the float see next overhead
  • 8. Burmans priority list 8 息The McGraw-Hill Companies, Give priority to: Shortest critical activities Other critical activities Shortest non-critical activities Non-critical activities with least float Non-critical activities
  • 9. Resource usage 9 息The McGraw-Hill Companies, Need to maximise %usage of resources i.e. reduce idle periods between tasks Need to balance costs against early completion date Need to allow for contingency
  • 10. Critical path 10 息The McGraw-Hill Companies, Scheduling resources can create new dependencies between activities recall critical chains It is best not to add dependencies to the activity network to reflect resource constraints Makes network very messy A resource constraint may disappear during the project, but link remains on network Amend dates on schedule to reflect resource constraints
  • 11. Allocating individuals to activities 11 息The McGraw-Hill Companies, The initial resource types for a task have to be replaced by actual individuals. Factors to be considered: Availability Criticality Risk Training Team building and motivation
  • 12. Cost schedules 12 息The McGraw-Hill Companies, Cost schedules can now be produced: Costs include: Staff costs Overheads Usage charges
  • 13. Cost profile 13 息The McGraw-Hill Companies,
  • 14. Accumulative costs 14 息The McGraw-Hill Companies,
  • 15. Balancing concerns 15 息The McGraw-Hill Companies,

Editor's Notes

  • #2: This talk provides an overview of the basic steps needed to produce a project plan. The framework provided should allow students to identify where some of the particular issues discussed in other chapters are applied to the planning process. As the focus is on project planning, techniques to do with project control are not explicitly described. However, in practice, one element of project planning will be to decide what project control procedures need to be in place.
  • #3: We have already described the creation of the activity schedule in Lecture/activity 6.
  • #4: Section 8.2 in the main text discusses this in a little more detail. A key point is that money (by definition) is the means by which one resource can be converted to another. However in practice this may be problematic because of resource constraints e.g. staff need time to become expert in a new technology regardless of the amount of money that might be available to buy expertise.
  • #5: This is covered in Section 8.3 of the text. Note that at this point we have to assume that we are dealing with, for example, standard software developers who have an average productivity. When we allocate actual people we may find that we have a trainee or a super-expert and this will affect productivity. A short-coming in productivity in an individual might be compensated for by a lower cost (as would be expected with trainees). In the example in the text we start by scheduling every activity to start at the earliest possible date. However in Lecture/Chapter 7, in the section on the critical chain technique it was suggested that we plan to start activities as late as possible. Whatever the starting procedure, we then need to deal with resource clashes.
  • #6: The resource histogram helps us identify where the demand for a resource exceeds the supply. If we use a tool such as MS Project, the tool will generate the resource histograms for us.
  • #7: Exercise 8.1 in the text gives some practice in the resolution of resource clashes.
  • #8: Where more than one activity is competing for the same limited resource at the same time then those activities need to be prioritized.
  • #11: In Lecture/chapter 7 the concept of critical chains was introduced which took account of resource constraints. The point about not adding links to the network to deal with resource constraints is not in the text, but is based on practical experience. The notation for activity networks does not tell you why one activity might be dependent on the completion of another.
  • #12: Availability who is free? Note that this will change during the course of the project as some tasks are completed earlier or later than planned Criticality You would want to put your more experienced, safer, staff on the critical activities Risk this is similar to the point above, but some activities could be off the critical path but still have risks e.g. to the quality of subsequent products Training despite concerns about minimizing risk, it is healthy to take some risks in order to develop staff capabilities by allocating challenging tasks to relatively inexperienced stafff Team-building identifying people who work well together can pay dividends; chopping and changing plans all the time may in theory optimize project performance, but can in practice be demotivating for staff
  • #13: Section 8.9 covers this in more depth. Staff costs includes not just salary, but also social security contributions by the employer, holiday pay etc. Timesheets are often used to record actual hours spent on each project by an individual. One issue can be how time when a staff member is allocated and available to the project, but is not actually working on the project, is dealt with. Overheads e.g. space rental, service charges etc. Some overheads might be directly attributable to the project; in other cases a percentage of departmental overheads may be allocated to project costs. Usage charges some charges can be on a pay as you go basis e.g. telephone charges, postage, car mileage at the planning stage an estimate of these may have to be made
  • #14: This shows how much is going to be spent in each week. This could be important where an organization allocates project budgets by financial year or quarter and the project straddles more than one of these financial periods
  • #15: The project manager will also be concerned about planned accumulative costs. This chart can be compared to the actual accumulative costs when controlling the project to assess whether the project is likely to meet its cost targets.
  • #16: Successful project scheduling is not a simple sequence. Because of the inter-linking of different concerns project planning will need to be iterative. The consequences of decisions will need to carefully assessed and plans adjusted accordingly.