際際滷

際際滷Share a Scribd company logo
Opening Remarks  Technical Briefing (21/3/2011)

1. Current Situation
We are seeing some steady improvements, but the overall situation at the Fukushima Daiichi
nuclear power plant remains very serious. High levels of contamination have been measured
in the locality of the plant.
The restoration of electrical power to Unit 2, which we reported yesterday, is good news. AC
power is available and an electrical load check to pumps etc. is currently on-going. Work on
the restoration of off-site power to Units 3 and 4 is also underway.
Seawater is still being injected into the reactor pressure vessels of Units 1, 2 and 3.
Pressure in the reactor pressure vessel and the containment vessel drywell at Unit 3, which
had been rising yesterday, has again fallen.
Water is being sprayed periodically into the spent fuel pools at Units 2, 3 and 4. The Agency
still lacks data on water levels and temperatures in the spent fuel pools at Units 1, 2, 3 and 4.
Following the restoration of cooling at Units 5 and 6, temperatures in the spent fuel pools
continue to decline.


2. Radiation Monitoring
As I reported yesterday, the IAEA radiation monitoring team took measurements at distances
from 56 to 200 km from the Fukushima nuclear power plant. At two locations in Fukushima
Prefecture gamma dose rate and beta-gamma contamination measurements have been
repeated. These measurements showed high beta-gamma contamination levels. Measurements
by the IAEA and the Japanese authorities were taken at the same time and locations. The
Japanese and independent IAEA measurements gave comparable results.
Measurement of gamma dose rate and beta-gamma contamination were taken on 20 March at
more locations. The dose-rate results ranged from 2-160 microsieverts per hour, which
compares to a typical natural background level of around 0.1 microsieverts per hour. High-
levels of beta-gamma contamination have been measured between 16-58 km from the plant.
Available results show contamination ranging from 0.2-0.9 MBq per square metre.
Further measurements are needed to assess possible contamination beyond the area currently
monitored  both closer to the facility and further way. We have no contamination
measurements showing that that contamination levels are high at greater distances than 58 km
from the plant, but this cannot be excluded.
I have no further information available regarding the measurement of alpha radiation. As I
reported yesterday, from the measurements taken within the evacuation zone (20 km), no
significant alpha radiation had been detected at that time.
In the coming days, the IAEA monitoring team will continue to take measurements in the
Fukushima prefecture. We are seeking data from Japan on radioactivity contamination
measurements for the rest of Japan.
Some results on the monitoring of foodstuffs have been made available by Japan to the IAEA
and FAO. Results provided recently by the Japanese authorities range up to 55,000 Bq per kg
of I-131 in samples of Spinach taken in in the Ibaraki Prefecture. These high values are
significantly above Japanese limits for restricting food consumption (i.e. 2,000 Bq/kg). I
understand that the Japanese Government is actively considering relevant precautionary
measures and has instructed four Prefectures (Ibaraki, Totigi, Gunma, Fukushima) to refrain,
for the time being, from distributing two types of vegetables (spinach and kakina) from these
Prefectures and milk from Fukshima.


3. Agency Activities
The Director General briefed the Board of Governors today on the outcome of his visit to
Tokyo.
Unit                        1                       2                        3                       4

Power (MWe /MWth)                  460/1380                 784/2381               784/2381                784/2381
Type of Reactor                    BWR-3                    BWR-4                   BWR-4                     BWR-4

                          In service  auto        In service  auto        In service  auto
Status at time of EQ                                                                                 Outage
                          shutdown                 shutdown                 shutdown

Core and fuel integrity   Damaged                  Damaged                  Damaged                  No fuel in the Reactor

RPV & RCS integrity       Unknown                  Unknown                  Unknown
                                                                                                     Not applicable due to
Containment integrity     Not Damaged              Damage suspected         No information           outage plant status

                                                   AC Power available 
AC Power                  Substation connected                              Not available            Not available
                                                   Load check is ongoing

Building                  Severe damage            Slight damage            Severe damage            Severe damage

                          Around half of Fuel is   Around half of Fuel is   Around half of Fuel is
Water level of RPV
                          uncovered (Stable)       uncovered (Stable)       uncovered (Stable)

Pressure of RPV           Stabilized               Unreliable Readings      Decreased                Not applicable due to
CV Pressure Drywell       Stable                   Stable                   Decreased                outage plant status

Water injection to RPV    Seawater                 Seawater                 Seawater

Water injection to CV     No information           No information           No information
                                                   Periodic spraying from   Periodic spraying from   Periodic spraying
Spent Fuel Pool Status    No information
                                                   outside                  outside                  from outside
3/21/2011 07:00 AM
Unit                            5                           6
  Power                                 784/2381                    1100/3293

  Type of Reactor                          BWR-4                       BWR-5

  Status at the EQ occurred   Outage                      Outage

  Core and Fuel               Cold Shutdown               Cold Shutdown                   Severe condition
  RPV & RCS integrity         Intact                      Intact

  Containment int.            No damage expected          No damage expected              Concern
  AC Power                    2nd Emergency diesel from   Emergency diesel
                              Unit 6                      Off-site power being restored   No immediate
                                                                                          concern
  Building                    No damage reported          No damage reported

  Water level of RPV          Above fuel                  Above fuel

  Pressure of RPV             Cooling restored            Cooling restored

  Containment Pressure        No information              No information

  Water injection to RPV      Injection in Progress       Injection in Progress

  Water injection to CV       Not needed now              Not needed now

  Spent Fuel Pool Status      Cooling restored            Cooling restored


3/21/2011 07:00 AM
Technical Briefing on the
Radiological Situation in Japan



      21 March 2011




                   IAEA
         International Atomic Energy Agency
Daiichi NPP On-Site gamma dose rate
(updated)




   IAEA
Evolution of gamma dose rates after radioactive releases
surrounding Daiichi NPP since 15 March 2011
(Selected monitoring posts)




      IAEA
                              Information provided by MEXT-Japan
Gamma dose rates North of Daiichi NPP
Japan (microSv/h), 15-20 March




   IAEA
Gamma dose rates between Tokyo and Daiichi
NPP (microSv/h), 15-20 March




   IAEA
Gamma dose rates close to Tokyo, (microSv/h),
15-20 March




   IAEA
Measurements by the IAEA monitoring team on
 20 March 2011
      Location         Distanc   Time,JST   Doserate    Alpha        beta+            Contamination
                         eto      (24h)      micro     (counts     gamma        Becquerelper     Mega
                        NPP                    Sv/h        per     (countsper       cm 2         Becquerel
                        (km)                             second)      second)                         perm2
MiniStopnear
Kawamata Hospital        58       10:32         5.7         0          3440           58.5           0.585
NihonmatsuTowa
cho                      52       10:55         4.2         0          2368           40.3           0.403
Towacho Michino
eki                      49       11:05         3.1         0          1270           21.6           0.216
AtcrossingofRoad
349andRoad50          46       11:30         1.9         0          1973           33.5           0.335
Suichuji busstop        43       11:42         2           0          2260           38.4           0.384
JATamura                39       11:57         2.6         0          2265           38.5           0.385
Borderbetween
Kuzuomura and          34       12:09        11.7         0          3152           53.6           0.536
Tamurashi
Kuzuo villageoffice     29       13:47        11.2         0          4874           82.9           0.829
Road50                  28       15:25         7.2         0          5030           85.5           0.855
Borderbetween
Namie townand          20       14:55        161          0        overload          na              na
Kuzuo village
GateofOgakidam
managementoffice        16       14:31         83          0        overload          na              na

            IAEA                                                                                                 7
Measurements by the IAEA monitoring team on
 19 March 2011
Location          Time, Distance    Dose     Alpha      beta+         Contamination
                   JST     from       rate   (counts   gamma
                  (24h) Fukushim     (micro     per   (countsper
                             a        Sv/h)    second)    second)      Becquerel        Mega
                          Daiichi                                      percm2         Becquerel
                         NPP(km)                                                        perm2

    Saitama
   Prefecture
Hasuda            17:00    200       0.04         0         27                     -
     Tochigi
   Prefecture
Sano              17:27    180       0.16        0          150           2.5             0.03
Kamikochi         18:17    140       0.18      0.2*)       240          4.1              0.04
Nasukogem         20:17    220       2.9         0         2300          39.3             0.39
   Fukushimi
   Prefecture
Abukuma           21:05     60        3.5      0.08*)      3750           64              0.64
Gohyakugawa       21:58     56         3          0        3900          66.3             0.66
           IAEA                                                                                      8
Maps with prefectures where foodstuffs
were measured




   IAEA                                  9
Ibaraki: Results from measurements of
radionuclides in foodstuffs
  Name        SamplingDate     Spniach&otherleafyvegs       SpringOnion               Milk(unprocessed)        UNITS
                          JST      I131         Cs137      I131         Cs137   I131           Cs137     Cs134
Kitaibaraki            18Mar    24000           690         350           ND                                     (Bq/kg)
Kamisu                 17Mar      56            ND                                                             (Bq/kg)
Yachiyo                17Mar      78             21                                                            (Bq/kg)
Takahagi               19Mar    11,000          586                                                            (Bq/kg)
Hokota                 19Mar     1900            71                                                            (Bq/kg)
Hokota                 19Mar     480             81                                                            (Bq/kg)
Hitachi
City                   18Mar    54100          1931                                                            (Bq/kg)
Hitachi
City                   18Mar    25200          1105                                                            (Bq/kg)
Hitachi
Omiya                  18Mar    19200          1040                                                            (Bq/kg)
Hitachi
Omiya                  18Mar    17800           908                                                            (Bq/kg)
Naka                   18Mar    16100           911                                                            (Bq/kg)
Naka                   18Mar    13500           966                                                            (Bq/kg)
Hokota                 18Mar    7710            407         356            9                                     (Bq/kg)
Moriya                 18Mar    2100            121         590           21                                     (Bq/kg)
Moriya                 18Mar      26            ND                                                             (Bq/kg)
Moriya                 18Mar     ND             ND                                                             (Bq/kg)
Koga                   18Mar    4200            270                                                            (Bq/kg)
Sakai                  18Mar                              140           ND                                     (Bq/kg)
Sakai
          IAEA         18Mar                              120           ND                                     (Bq/kg)

More Related Content

Technical Briefing on Radiological Situation in Japan - 21 March 2011

  • 1. Opening Remarks Technical Briefing (21/3/2011) 1. Current Situation We are seeing some steady improvements, but the overall situation at the Fukushima Daiichi nuclear power plant remains very serious. High levels of contamination have been measured in the locality of the plant. The restoration of electrical power to Unit 2, which we reported yesterday, is good news. AC power is available and an electrical load check to pumps etc. is currently on-going. Work on the restoration of off-site power to Units 3 and 4 is also underway. Seawater is still being injected into the reactor pressure vessels of Units 1, 2 and 3. Pressure in the reactor pressure vessel and the containment vessel drywell at Unit 3, which had been rising yesterday, has again fallen. Water is being sprayed periodically into the spent fuel pools at Units 2, 3 and 4. The Agency still lacks data on water levels and temperatures in the spent fuel pools at Units 1, 2, 3 and 4. Following the restoration of cooling at Units 5 and 6, temperatures in the spent fuel pools continue to decline. 2. Radiation Monitoring As I reported yesterday, the IAEA radiation monitoring team took measurements at distances from 56 to 200 km from the Fukushima nuclear power plant. At two locations in Fukushima Prefecture gamma dose rate and beta-gamma contamination measurements have been repeated. These measurements showed high beta-gamma contamination levels. Measurements by the IAEA and the Japanese authorities were taken at the same time and locations. The Japanese and independent IAEA measurements gave comparable results. Measurement of gamma dose rate and beta-gamma contamination were taken on 20 March at more locations. The dose-rate results ranged from 2-160 microsieverts per hour, which compares to a typical natural background level of around 0.1 microsieverts per hour. High- levels of beta-gamma contamination have been measured between 16-58 km from the plant. Available results show contamination ranging from 0.2-0.9 MBq per square metre. Further measurements are needed to assess possible contamination beyond the area currently monitored both closer to the facility and further way. We have no contamination measurements showing that that contamination levels are high at greater distances than 58 km from the plant, but this cannot be excluded. I have no further information available regarding the measurement of alpha radiation. As I reported yesterday, from the measurements taken within the evacuation zone (20 km), no significant alpha radiation had been detected at that time. In the coming days, the IAEA monitoring team will continue to take measurements in the Fukushima prefecture. We are seeking data from Japan on radioactivity contamination measurements for the rest of Japan.
  • 2. Some results on the monitoring of foodstuffs have been made available by Japan to the IAEA and FAO. Results provided recently by the Japanese authorities range up to 55,000 Bq per kg of I-131 in samples of Spinach taken in in the Ibaraki Prefecture. These high values are significantly above Japanese limits for restricting food consumption (i.e. 2,000 Bq/kg). I understand that the Japanese Government is actively considering relevant precautionary measures and has instructed four Prefectures (Ibaraki, Totigi, Gunma, Fukushima) to refrain, for the time being, from distributing two types of vegetables (spinach and kakina) from these Prefectures and milk from Fukshima. 3. Agency Activities The Director General briefed the Board of Governors today on the outcome of his visit to Tokyo.
  • 3. Unit 1 2 3 4 Power (MWe /MWth) 460/1380 784/2381 784/2381 784/2381 Type of Reactor BWR-3 BWR-4 BWR-4 BWR-4 In service auto In service auto In service auto Status at time of EQ Outage shutdown shutdown shutdown Core and fuel integrity Damaged Damaged Damaged No fuel in the Reactor RPV & RCS integrity Unknown Unknown Unknown Not applicable due to Containment integrity Not Damaged Damage suspected No information outage plant status AC Power available AC Power Substation connected Not available Not available Load check is ongoing Building Severe damage Slight damage Severe damage Severe damage Around half of Fuel is Around half of Fuel is Around half of Fuel is Water level of RPV uncovered (Stable) uncovered (Stable) uncovered (Stable) Pressure of RPV Stabilized Unreliable Readings Decreased Not applicable due to CV Pressure Drywell Stable Stable Decreased outage plant status Water injection to RPV Seawater Seawater Seawater Water injection to CV No information No information No information Periodic spraying from Periodic spraying from Periodic spraying Spent Fuel Pool Status No information outside outside from outside 3/21/2011 07:00 AM
  • 4. Unit 5 6 Power 784/2381 1100/3293 Type of Reactor BWR-4 BWR-5 Status at the EQ occurred Outage Outage Core and Fuel Cold Shutdown Cold Shutdown Severe condition RPV & RCS integrity Intact Intact Containment int. No damage expected No damage expected Concern AC Power 2nd Emergency diesel from Emergency diesel Unit 6 Off-site power being restored No immediate concern Building No damage reported No damage reported Water level of RPV Above fuel Above fuel Pressure of RPV Cooling restored Cooling restored Containment Pressure No information No information Water injection to RPV Injection in Progress Injection in Progress Water injection to CV Not needed now Not needed now Spent Fuel Pool Status Cooling restored Cooling restored 3/21/2011 07:00 AM
  • 5. Technical Briefing on the Radiological Situation in Japan 21 March 2011 IAEA International Atomic Energy Agency
  • 6. Daiichi NPP On-Site gamma dose rate (updated) IAEA
  • 7. Evolution of gamma dose rates after radioactive releases surrounding Daiichi NPP since 15 March 2011 (Selected monitoring posts) IAEA Information provided by MEXT-Japan
  • 8. Gamma dose rates North of Daiichi NPP Japan (microSv/h), 15-20 March IAEA
  • 9. Gamma dose rates between Tokyo and Daiichi NPP (microSv/h), 15-20 March IAEA
  • 10. Gamma dose rates close to Tokyo, (microSv/h), 15-20 March IAEA
  • 11. Measurements by the IAEA monitoring team on 20 March 2011 Location Distanc Time,JST Doserate Alpha beta+ Contamination eto (24h) micro (counts gamma Becquerelper Mega NPP Sv/h per (countsper cm 2 Becquerel (km) second) second) perm2 MiniStopnear Kawamata Hospital 58 10:32 5.7 0 3440 58.5 0.585 NihonmatsuTowa cho 52 10:55 4.2 0 2368 40.3 0.403 Towacho Michino eki 49 11:05 3.1 0 1270 21.6 0.216 AtcrossingofRoad 349andRoad50 46 11:30 1.9 0 1973 33.5 0.335 Suichuji busstop 43 11:42 2 0 2260 38.4 0.384 JATamura 39 11:57 2.6 0 2265 38.5 0.385 Borderbetween Kuzuomura and 34 12:09 11.7 0 3152 53.6 0.536 Tamurashi Kuzuo villageoffice 29 13:47 11.2 0 4874 82.9 0.829 Road50 28 15:25 7.2 0 5030 85.5 0.855 Borderbetween Namie townand 20 14:55 161 0 overload na na Kuzuo village GateofOgakidam managementoffice 16 14:31 83 0 overload na na IAEA 7
  • 12. Measurements by the IAEA monitoring team on 19 March 2011 Location Time, Distance Dose Alpha beta+ Contamination JST from rate (counts gamma (24h) Fukushim (micro per (countsper a Sv/h) second) second) Becquerel Mega Daiichi percm2 Becquerel NPP(km) perm2 Saitama Prefecture Hasuda 17:00 200 0.04 0 27 - Tochigi Prefecture Sano 17:27 180 0.16 0 150 2.5 0.03 Kamikochi 18:17 140 0.18 0.2*) 240 4.1 0.04 Nasukogem 20:17 220 2.9 0 2300 39.3 0.39 Fukushimi Prefecture Abukuma 21:05 60 3.5 0.08*) 3750 64 0.64 Gohyakugawa 21:58 56 3 0 3900 66.3 0.66 IAEA 8
  • 13. Maps with prefectures where foodstuffs were measured IAEA 9
  • 14. Ibaraki: Results from measurements of radionuclides in foodstuffs Name SamplingDate Spniach&otherleafyvegs SpringOnion Milk(unprocessed) UNITS JST I131 Cs137 I131 Cs137 I131 Cs137 Cs134 Kitaibaraki 18Mar 24000 690 350 ND (Bq/kg) Kamisu 17Mar 56 ND (Bq/kg) Yachiyo 17Mar 78 21 (Bq/kg) Takahagi 19Mar 11,000 586 (Bq/kg) Hokota 19Mar 1900 71 (Bq/kg) Hokota 19Mar 480 81 (Bq/kg) Hitachi City 18Mar 54100 1931 (Bq/kg) Hitachi City 18Mar 25200 1105 (Bq/kg) Hitachi Omiya 18Mar 19200 1040 (Bq/kg) Hitachi Omiya 18Mar 17800 908 (Bq/kg) Naka 18Mar 16100 911 (Bq/kg) Naka 18Mar 13500 966 (Bq/kg) Hokota 18Mar 7710 407 356 9 (Bq/kg) Moriya 18Mar 2100 121 590 21 (Bq/kg) Moriya 18Mar 26 ND (Bq/kg) Moriya 18Mar ND ND (Bq/kg) Koga 18Mar 4200 270 (Bq/kg) Sakai 18Mar 140 ND (Bq/kg) Sakai IAEA 18Mar 120 ND (Bq/kg)