This document outlines a project plan for an Event Concierge project scheduled from April 18th to July 31st. It lists 39 tasks with details on duration, start date, finish date, resource assignment, and percent completion. The tasks include requirements gathering, documentation preparation, architecture and design work, development in .NET, testing, and user acceptance testing, with the overall project currently 45% complete.
1 of 2
Download to read offline
More Related Content
test-Summit summary
1. ID Task Name Duration Start Finish % Complete Resource Names
1 Event Concierge 75 days Wed 4/18/12 Tue 7/31/1245%
2 POC 19 days Wed 4/18/12 Mon 5/14/12 100%
3 IC APP 9 days Wed 4/18/12 Mon 4/30/12 100% Kiran[50%],Shimi,Hari
4 Microsite 10 days Tue 5/1/12 Mon 5/14/12 100% Hari,Shimi,Remya
5 Requirement 13 days Wed 5/2/12 Fri 5/18/12 100%
6 Prepare BRD Document 11 days Wed 5/2/12 Wed 5/16/12 100% Shyam
7 BRD Review 1 day Thu 5/17/12 Thu 5/17/12 100% Bineesh
8 BRD Rework 1 day Fri 5/18/12 Fri 5/18/12 100% Shyam
9 Architecture 4 days Tue 5/15/12 Fri 5/18/12 100%
10 Architecture Document -Update 2 days Tue 5/15/12 Wed 5/16/12 100% Kiran
11 Architecture Document Review 1 day Thu 5/17/12 Thu 5/17/12 100% Bineesh
12 Architecture Document Rework 1 day Fri 5/18/12 Fri 5/18/12 100% Kiran
13 Design 4 days Tue 5/15/12 Fri 5/18/12 75%
14 Database Design 2 days Tue 5/15/12 Wed 5/16/12 100% Shimi
15 HLD document 2 days Thu 5/17/12 Fri 5/18/12 50% Remya,Shimi
16 C & DS Activity 7 days Tue 5/15/12 Wed 5/23/12 100%
17 Wireframe & Images 7 days Tue 5/15/12 Wed 5/23/12 100% Ria Mitra
18 EAS Implementation 55 days Wed 5/16/12 Tue 7/31/1213%
19 Phase 1 55 days Wed 5/16/12 Tue 7/31/1213%
20 Development(Till May25th) 9 days Tue 5/15/12 Fri 5/25/12 75%
21 .NET Development -IC App
(Home ,Agenda,Speaker Info)
9 days Tue 5/15/12 Fri 5/25/12 75% Hari,Bhanupriya
(Catalyst),Sandhya
(Catalyst)22 .NET Development
-WebService
5 days Mon 5/21/12 Fri 5/25/12 75% Shimi,Remya
23 Development(From Jun11) 19 days Mon 6/11/12 Thu 7/5/12 0%
24 .NET Development
-Venue,FAQ,ContactUs,Registration
18 days Mon 6/11/12 Wed 7/4/12 0% Bhanupriya
(Catalyst),Hari,Sandhya
(Catalyst)25 .NET Development
-Webservice
7 days Mon 6/11/12 Tue 6/19/120% Remya,Shimi
26 .NET Development -Microsite 12 days Wed 6/20/12 Thu 7/5/12 0% Shimi,Remya
27 Test Plan 5 days Mon 6/18/12 Fri 6/22/12 0%
28 Test Case Preperation 5 days Mon 6/18/12 Fri 6/22/12 0% Nandini,Subha
29 Test Execution 18 days Fri 7/6/12 Tue 7/31/120%
Page 1
2. ID Task Name Duration Start Finish % Complete Resource Names
30 Event Concierge- Staging
Environment
10 days Fri 7/6/12 Thu 7/19/12 0%
31 Server Set up -1C &
Resource Server
2 days Fri 7/6/12 Mon 7/9/12 0% IC team
32 System Testing 6 days Tue 7/10/12 Tue 7/17/120% Nandini,Subha
33 Peformance Bench
Marking-Dev Team
4 days Tue 7/10/12 Fri 7/13/12 0% Kiran[50%],Shimi,Hari
34 Testing Sign Off 1 day Wed 7/18/12 Wed 7/18/12 0% Nandini
35 Performance Testing Sign off
-IC Sign Off
1 day Thu 7/19/12 Thu 7/19/12 0% IC team
36 Event Concierge-UAT 8 days Fri 7/20/12 Tue 7/31/120%
37 1st Integration Testing 2 days Fri 7/20/12 Mon 7/23/12 0% Nandini,Subha
38 UAT 5 days Tue 7/24/12 Mon 7/30/12 0% Marketing team,Shyam
39 GO/NO GO decision 1 day Tue 7/31/12 Tue 7/31/120% Marketing team