Verbus Systems produces modular steel building units called Verbus modules. The modules have superior soundproofing and insulation. Example projects using Verbus modules include a 307-bedroom Travelodge hotel constructed in 30 days using 181 modules, and a 120-bedroom Travelodge hotel built in 24 days using 81 modules. Verbus modules allow for faster construction, lower costs, and delivery worldwide for buildings up to 16 stories tall.
1 of 17
Download to read offline
More Related Content
Verbus Systems Quant International Introduction.Pptx
5. The basic Verbus module comprises a shell of high tensile corrosion resistant steel components with composite wall, floor and roof structure that provides superior insulation for sound, thermal & fire performance.
11. Travelodge Heathrow Central 307 Bedroom budget hotel, opened 15 th December 2008. Programme 30 % shorter vs other traditional bidders 181 modular units giving 307 bedrooms. 3 Principal types of bedroom Shower Room Family Room Disabled Room Erection of the modules averaged 30 bedrooms/ day Building is 7 stories high
12. Travelodge Heathrow Central 307 Bedroom budget hotel, opened 15 th December 2008. Cladding made up of Cedar, render panel and aluminium panel. Fastened to the Verbus Units using standard cladding connections Units mounted onto a steel frame , and connected back to steel frame stair and lift cores Major acoustic challenges on the project as the hotel sits under the flight path to Heathrow, no complaints have been received regarding acoustic performance
13. Travelodge Uxbridge Central 120 Bedroom budget hotel, opened 5 th August 2008. 125 bedrooms using 81 modular units Average 24 bedrooms erected each day Site is next to the West London 24 hour bus garage therefore logistics were extremely challenging, but delivered without any issues
14. Premier Inn Fleming Way Gatwick Currently on site 210 bedrooms using 114 modular units 6 stories of Verbus units Program 50 weeks. The contractor believes this could be reduced to less than 40 weeks
15. Premier Inn Citadel Way Hull 125 Bedrooms, in 75 Verbus modules Total development 13 stories Verbus units mounted on top of the steel frame car park
16. > Significantly improved programme times compared to traditional construction. > Improved project costs. > Deliverable anywhere in the world. > Up to 16 stories achievable with a standard module. > Reduced on site project and commercial management requiror. Significantly improved programme times compared to traditional construction. On average 30 bedrooms erected per day Improved project costs. Deliverable anywhere in the world. Up to 16 stories achievable with a standard module Reduced on site project and commercial management required by Main Contractor. Consistent Factory controlled Quality Acoustic performance up to 30% better than Building Control requirements Simple connection method for modules avoiding unnecessary complexity Benefits of using Verbus
17. > Significantly improved programme times compared to traditional construction. > Improved project costs. > Deliverable anywhere in the world. > Up to 16 stories achievable with a standard module. > Reduced on site project and commercial management requiror. Budget Hotels Student Accommodation Key Worker Accommodation Care Homes Prisons Key Market Areas