Project: GE Compressor Rehabilitation Project
Contract No: SIGUP-12-066A/B Cut-off date: 21 Jun 2015
8 10 11 12 13
03 May 15 07 Jun 15 14 Jun 15 21 Jun 15
CS1A - WO4&WO5 CS1A 49,726 01 Jun 2014 10 Nov 2015 01 Jun 2014 ---- 49.99% 65.32% 68.79% 71.14%
4 - Construction 46,146 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 53.94% 70.43% 74.19% 76.23%
4 - Site office and field work area preparation 1,800 01 Jul 2014 31 Jul 2014 01 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100%
1 - Mechanical 14,850 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 50.27% 67.38% 68.99% 73.85%
1 - Compressor on-skid and Auxiliaries 8,100 13 Mar 2015 05 Oct 2015 13 Mar 2015 ---- 46.32% 63.88% 63.88% 67.05%
1 - Centrifugal Compressor 1,630 15 Mar 2015 05 Oct 2015 15 Mar 2015 ---- 42.33% 42.33% 42.33% 42.33%
2 - Gear box 680 15 Mar 2015 15 Sep 2015 15 Mar 2015 ---- 32.35% 32.35% 32.35% 32.35%
3 - Electrical motor 420 15 Mar 2015 22 Jun 2015 15 Mar 2015 ---- 85.71% 90.48% 90.48% 90.48%
4 - Compressor Auxiliaries 2,270 13 Mar 2015 18 Sep 2015 13 Mar 2015 ---- 56.78% 92.29% 92.29% 92.29%
8 - Seal Oil Overhead Tank (New) 80 23 Apr 2015 17 Sep 2015 23 Apr 2015 ---- 0.00% 0.00% 0.00% 0.00%
2 - Manual valve replacement 750 05 Apr 2015 13 Aug 2015 05 Apr 2015 ---- 96.67% 96.67% 96.67% 96.67%
5 - Heaters 100 11 Apr 2015 23 Apr 2015 11 Apr 2015 23 Apr 2015 0.00% 100.00% 100.00% 100.00%
1 - LO and SO motor and pumps replacement 320 13 Mar 2015 26 Apr 2015 13 Mar 2015 26 Apr 2015 85.00% 100.00% 100.00% 100.00%
3 - Control valves (PCV & DPCV & LCV) 100 10 Apr 2015 27 Jun 2015 10 Apr 2015 ---- 60.00% 60.00% 60.00% 60.00%
7 - Compressor Skid Instrument 220 05 Apr 2015 18 Sep 2015 05 Apr 2015 ---- 67.14% 86.36% 86.36% 86.36%
6 - TCV piping modification and valve installation 600 04 May 2015 21 May 2015 04 May 2015 21 May 2015 100.00% 100.00% 100.00% 100.00%
4 - PSV 100 10 Apr 2015 10 May 2015 10 Apr 2015 10 May 2015 81.82% 100.00% 100.00% 100.00%
6 - Oil flushing preparation and execution 2,840 14 Mar 2015 09 Sep 2015 14 Mar 2015 ---- 36.27% 52.11% 52.11% 65.00%
5 - Oil cooler 260 15 Mar 2015 14 Aug 2015 15 Mar 2015 ---- 53.85% 76.92% 76.92% 76.92%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 0.00% 50.00% 50.00% 50.00%
2 - Pneumatic Test 140 15 Mar 2015 04 Apr 2015 15 Mar 2015 04 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Process system 6,750 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 54.87% 71.47% 74.96% 82.01%
1 - Gas cooler 1,480 22 Apr 2015 09 Sep 2015 22 Apr 2015 ---- 63.70% 50.81% 65.41% 83.78%
2 - Hydraulic test 1,060 22 Apr 2015 16 Jun 2015 22 Apr 2015 16 Jun 2015 85.42% 69.81% 81.13% 100.00%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 33.33% 50.00% 50.00% 50.00%
3 - Process Pipe 2,920 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 33.33% 65.62% 65.62% 72.60%
5 - Process piping cleaning 960 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 55.56% 91.25% 91.25% 100.00%
3 - PSV 480 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 78.95% 33.33% 33.33% 33.33%
4 - MOV and SDV 540 21 Jul 2014 07 Sep 2015 21 Jul 2014 ---- 65.70% 33.33% 33.33% 33.33%
2 - Process Control Valves 180 21 Jul 2014 15 Sep 2015 21 Jul 2014 ---- 77.27% 55.56% 55.56% 55.56%
1 - Manual valve replacement 760 20 Apr 2015 27 Jun 2015 20 Apr 2015 ---- 54.74% 78.95% 78.95% 94.74%
2 - Vessel 2,350 12 Mar 2015 07 Jul 2015 12 Mar 2015 ---- 77.78% 91.74% 92.60% 92.60%
4 - Level control valve & Glass - Klinger 510 17 Apr 2015 07 Jun 2015 17 Apr 2015 07 Jun 2015 40.39% 100.00% 100.00% 100.00%
2 - Manual valve replacement on Vessels V5,V6,V7,V10 1,100 16 Apr 2015 07 Jul 2015 16 Apr 2015 ---- 20.27% 96.36% 96.36% 96.36%
3 - Level Control Valve Replacement 380 14 Apr 2015 07 Jul 2015 14 Apr 2015 ---- 28.30% 80.53% 85.79% 85.79%
1 - Inspection 360 12 Mar 2015 22 Jun 2015 12 Mar 2015 ---- 0.00% 77.78% 77.78% 77.78%
2 - Civil & Structures 15,800 26 Jan 2015 12 Sep 2015 26 Jan 2015 ---- 77.78% 85.03% 87.66% 88.23%
2 - Structures 2,920 26 Jan 2015 27 Aug 2015 26 Jan 2015 ---- 91.78% 91.78% 91.78% 91.78%
1 - Overhead crane replacement 2,680 26 Jan 2015 14 Mar 2015 26 Jan 2015 14 Mar 2015 0.00% 100.00% 100.00% 100.00%
2 - Gratings and platform 240 15 Aug 2015 27 Aug 2015 ---- ---- 100.00% 0.00% 0.00% 0.00%
1 - Civil 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
1 - Excavation & Foundation Works (COMMON TO TRAINS A&B) 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
7 - Fiber opthic/Ethernet from UCP to HMI: (SOK9951893 cable routing plan) 120 30 Mar 2015 09 May 2015 30 Mar 2015 09 May 2015 94.44% 100.00% 100.00% 100.00%
9 - Additional Earthing System 1,080 05 Apr 2015 09 May 2015 05 Apr 2015 09 May 2015 68.33% 100.00% 100.00% 100.00%
3 - Cable routing for compressor area (T7 e T8) 2,700 16 Mar 2015 12 Sep 2015 16 Mar 2015 ---- 86.67% 70.00% 70.00% 73.33%
1 - UCP (ref dwg.SOK2310988) 900 01 Mar 2015 09 May 2015 01 Mar 2015 09 May 2015 93.85% 100.00% 100.00% 100.00%
2 - Cable routing from MCC to UCP (T1, DB1, T2) 2,780 13 Mar 2015 08 Jun 2015 13 Mar 2015 08 Jun 2015 66.67% 85.00% 100.00% 100.00%
6 - Corrugated pipes on BOP [-P6,7,17,19,20,23¡ªfrom C5 to C7, C9, from C1 1,300 30 Mar 2015 16 May 2015 30 Mar 2015 16 May 2015 97.69% 100.00% 100.00% 100.00%
4 - Cable routing for BOP [T5A, DB8A, between gas cooler and V7=T5A/1 e sle 2,700 16 Mar 2015 10 Sep 2015 16 Mar 2015 ---- 65.76% 66.67% 66.67% 66.67%
5 - Corrugate pipe on compressor (SOK 9951893 pag 4/4) P2,3,4 C8, from C 1,300 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 66.67% 100.00% 100.00% 100.00%
3 - Electrical & Instrument 13,696 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 23.61% 52.57% 60.52% 61.84%
8 - Fire Fighting System 1,280 11 May 2015 14 Sep 2015 11 May 2015 ---- 0.00% 51.09% 77.34% 77.34%
10 - MV&LV Cable trays installation (COMMON TO TRAINS A&B) 320 08 Apr 2015 24 Apr 2015 08 Apr 2015 24 Apr 2015 36.36% 100.00% 100.00% 100.00%
14 - Replacement of Instrumentation on Compressor skid 740 13 Apr 2015 10 Sep 2015 13 Apr 2015 ---- 100.00% 37.84% 37.84% 37.84%
3 - UPS (COMMON TO TRAINS A&B) 160 09 Apr 2015 13 Apr 2015 09 Apr 2015 13 Apr 2015 40.54% 100.00% 100.00% 100.00%
16 - Instrument Air 660 30 Apr 2015 25 Jun 2015 30 Apr 2015 ---- 37.84% 94.55% 94.55% 94.55%
15 - Replacement of Instrumentation on BoP and Process 1,480 14 Apr 2015 12 Oct 2015 14 Apr 2015 ---- 100.00% 56.76% 73.78% 77.03%
13 - Lighting system on field 1,900 17 Apr 2015 05 Nov 2015 17 Apr 2015 ---- 21.05% 50.26% 58.95% 60.53%
11 - Instrument Cable trays 1,400 06 Apr 2015 29 Sep 2015 06 Apr 2015 ---- 20.00% 77.00% 88.00% 90.86%
12 - Cable Laying/Test/Termination 3,642 31 Jul 2014 02 Sep 2015 31 Jul 2014 ---- 2.20% 26.96% 31.27% 38.17%
1 - MV Cable 80 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 0.00% 100.00% 100.00% 100.00%
2 - LV Cable 1,362 12 May 2015 02 Sep 2015 12 May 2015 ---- 100.00% 39.79% 51.32% 69.75%
3 - Instrument Cable 2,200 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 0.00% 16.36% 16.36% 16.36%
4 - Batteries (COMMON TO TRAINS A&B) 180 03 Sep 2015 15 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - F&G (COMMON TO TRAINS A&B) 160 16 Apr 2015 18 Apr 2015 16 Apr 2015 18 Apr 2015 100.00% 100.00% 100.00% 100.00%
7 - Air conditioning system (COMMON TO TRAINS A&B) 80 28 Aug 2015 03 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
1 - Inspections 640 01 Jul 2014 12 Apr 2015 01 Jul 2014 12 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Battery room refurbishment (COMMON TO TRAINS A&B) 490 21 Jun 2015 17 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
18 - UCP 344 01 May 2015 30 May 2015 01 May 2015 30 May 2015 0.00% 100.00% 100.00% 100.00%
5 - Pre-Commissioning & Commissioning 3,580 31 Jul 2014 10 Nov 2015 31 Jul 2014 ---- 3.61% 5.26% 5.26% 5.59%
2 - Electrical and control test 20 09 May 2015 10 May 2015 09 May 2015 10 May 2015 0.00% 100.00% 100.00% 100.00%
3 - MVA Transformer activities 140 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100.00%
4 - MCC Activities 80 18 Sep 2015 23 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Fire fighting system commissioning 420 08 Oct 2015 02 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
7 - DCP Commissioning 320 17 Sep 2015 08 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
8 - UCP activities 640 21 Sep 2015 19 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
9 - Functional test compressor unit and BoP equipment 820 09 Oct 2015 11 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
10 - Motor rotating equipment 360 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 11.11% 11.11% 11.11%
1 - Main and aux lube oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
2 - Main and aux seal oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
3 - #6 gas cooler motor bump test, belt installation and running test 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
4 - #3 main & #3 stand-by Lube Oil cooler motors bump test, coupling installation and run 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - #3 main & #3 stand-by Seal Oil cooler motors bump test, coupling installation and run t 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Seal oil degassing tank agitator and blower motor bump test, coupling installation and ru 60 10 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
11 - MV Motor activities 120 11 Oct 2015 13 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
12 - Alignment and Load Coupling installation 360 13 Oct 2015 16 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
13 - Unit Start-up 300 19 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
Actual %
WO5A CS1A Construction Progress Status Report
CONSTRUCTION PHASES & AREAS
Budgeted
Labour
Units
Start Finish
Actual
Start
Actual Finish

More Related Content

WO5A CS1A Construction Progress Status Report Week #25

  • 1. Project: GE Compressor Rehabilitation Project Contract No: SIGUP-12-066A/B Cut-off date: 21 Jun 2015 8 10 11 12 13 03 May 15 07 Jun 15 14 Jun 15 21 Jun 15 CS1A - WO4&WO5 CS1A 49,726 01 Jun 2014 10 Nov 2015 01 Jun 2014 ---- 49.99% 65.32% 68.79% 71.14% 4 - Construction 46,146 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 53.94% 70.43% 74.19% 76.23% 4 - Site office and field work area preparation 1,800 01 Jul 2014 31 Jul 2014 01 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100% 1 - Mechanical 14,850 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 50.27% 67.38% 68.99% 73.85% 1 - Compressor on-skid and Auxiliaries 8,100 13 Mar 2015 05 Oct 2015 13 Mar 2015 ---- 46.32% 63.88% 63.88% 67.05% 1 - Centrifugal Compressor 1,630 15 Mar 2015 05 Oct 2015 15 Mar 2015 ---- 42.33% 42.33% 42.33% 42.33% 2 - Gear box 680 15 Mar 2015 15 Sep 2015 15 Mar 2015 ---- 32.35% 32.35% 32.35% 32.35% 3 - Electrical motor 420 15 Mar 2015 22 Jun 2015 15 Mar 2015 ---- 85.71% 90.48% 90.48% 90.48% 4 - Compressor Auxiliaries 2,270 13 Mar 2015 18 Sep 2015 13 Mar 2015 ---- 56.78% 92.29% 92.29% 92.29% 8 - Seal Oil Overhead Tank (New) 80 23 Apr 2015 17 Sep 2015 23 Apr 2015 ---- 0.00% 0.00% 0.00% 0.00% 2 - Manual valve replacement 750 05 Apr 2015 13 Aug 2015 05 Apr 2015 ---- 96.67% 96.67% 96.67% 96.67% 5 - Heaters 100 11 Apr 2015 23 Apr 2015 11 Apr 2015 23 Apr 2015 0.00% 100.00% 100.00% 100.00% 1 - LO and SO motor and pumps replacement 320 13 Mar 2015 26 Apr 2015 13 Mar 2015 26 Apr 2015 85.00% 100.00% 100.00% 100.00% 3 - Control valves (PCV & DPCV & LCV) 100 10 Apr 2015 27 Jun 2015 10 Apr 2015 ---- 60.00% 60.00% 60.00% 60.00% 7 - Compressor Skid Instrument 220 05 Apr 2015 18 Sep 2015 05 Apr 2015 ---- 67.14% 86.36% 86.36% 86.36% 6 - TCV piping modification and valve installation 600 04 May 2015 21 May 2015 04 May 2015 21 May 2015 100.00% 100.00% 100.00% 100.00% 4 - PSV 100 10 Apr 2015 10 May 2015 10 Apr 2015 10 May 2015 81.82% 100.00% 100.00% 100.00% 6 - Oil flushing preparation and execution 2,840 14 Mar 2015 09 Sep 2015 14 Mar 2015 ---- 36.27% 52.11% 52.11% 65.00% 5 - Oil cooler 260 15 Mar 2015 14 Aug 2015 15 Mar 2015 ---- 53.85% 76.92% 76.92% 76.92% 1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 0.00% 50.00% 50.00% 50.00% 2 - Pneumatic Test 140 15 Mar 2015 04 Apr 2015 15 Mar 2015 04 Apr 2015 100.00% 100.00% 100.00% 100.00% 2 - Process system 6,750 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 54.87% 71.47% 74.96% 82.01% 1 - Gas cooler 1,480 22 Apr 2015 09 Sep 2015 22 Apr 2015 ---- 63.70% 50.81% 65.41% 83.78% 2 - Hydraulic test 1,060 22 Apr 2015 16 Jun 2015 22 Apr 2015 16 Jun 2015 85.42% 69.81% 81.13% 100.00% 1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 33.33% 50.00% 50.00% 50.00% 3 - Process Pipe 2,920 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 33.33% 65.62% 65.62% 72.60% 5 - Process piping cleaning 960 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 55.56% 91.25% 91.25% 100.00% 3 - PSV 480 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 78.95% 33.33% 33.33% 33.33% 4 - MOV and SDV 540 21 Jul 2014 07 Sep 2015 21 Jul 2014 ---- 65.70% 33.33% 33.33% 33.33% 2 - Process Control Valves 180 21 Jul 2014 15 Sep 2015 21 Jul 2014 ---- 77.27% 55.56% 55.56% 55.56% 1 - Manual valve replacement 760 20 Apr 2015 27 Jun 2015 20 Apr 2015 ---- 54.74% 78.95% 78.95% 94.74% 2 - Vessel 2,350 12 Mar 2015 07 Jul 2015 12 Mar 2015 ---- 77.78% 91.74% 92.60% 92.60% 4 - Level control valve & Glass - Klinger 510 17 Apr 2015 07 Jun 2015 17 Apr 2015 07 Jun 2015 40.39% 100.00% 100.00% 100.00% 2 - Manual valve replacement on Vessels V5,V6,V7,V10 1,100 16 Apr 2015 07 Jul 2015 16 Apr 2015 ---- 20.27% 96.36% 96.36% 96.36% 3 - Level Control Valve Replacement 380 14 Apr 2015 07 Jul 2015 14 Apr 2015 ---- 28.30% 80.53% 85.79% 85.79% 1 - Inspection 360 12 Mar 2015 22 Jun 2015 12 Mar 2015 ---- 0.00% 77.78% 77.78% 77.78% 2 - Civil & Structures 15,800 26 Jan 2015 12 Sep 2015 26 Jan 2015 ---- 77.78% 85.03% 87.66% 88.23% 2 - Structures 2,920 26 Jan 2015 27 Aug 2015 26 Jan 2015 ---- 91.78% 91.78% 91.78% 91.78% 1 - Overhead crane replacement 2,680 26 Jan 2015 14 Mar 2015 26 Jan 2015 14 Mar 2015 0.00% 100.00% 100.00% 100.00% 2 - Gratings and platform 240 15 Aug 2015 27 Aug 2015 ---- ---- 100.00% 0.00% 0.00% 0.00% 1 - Civil 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42% 1 - Excavation & Foundation Works (COMMON TO TRAINS A&B) 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42% 7 - Fiber opthic/Ethernet from UCP to HMI: (SOK9951893 cable routing plan) 120 30 Mar 2015 09 May 2015 30 Mar 2015 09 May 2015 94.44% 100.00% 100.00% 100.00% 9 - Additional Earthing System 1,080 05 Apr 2015 09 May 2015 05 Apr 2015 09 May 2015 68.33% 100.00% 100.00% 100.00% 3 - Cable routing for compressor area (T7 e T8) 2,700 16 Mar 2015 12 Sep 2015 16 Mar 2015 ---- 86.67% 70.00% 70.00% 73.33% 1 - UCP (ref dwg.SOK2310988) 900 01 Mar 2015 09 May 2015 01 Mar 2015 09 May 2015 93.85% 100.00% 100.00% 100.00% 2 - Cable routing from MCC to UCP (T1, DB1, T2) 2,780 13 Mar 2015 08 Jun 2015 13 Mar 2015 08 Jun 2015 66.67% 85.00% 100.00% 100.00% 6 - Corrugated pipes on BOP [-P6,7,17,19,20,23¡ªfrom C5 to C7, C9, from C1 1,300 30 Mar 2015 16 May 2015 30 Mar 2015 16 May 2015 97.69% 100.00% 100.00% 100.00% 4 - Cable routing for BOP [T5A, DB8A, between gas cooler and V7=T5A/1 e sle 2,700 16 Mar 2015 10 Sep 2015 16 Mar 2015 ---- 65.76% 66.67% 66.67% 66.67% 5 - Corrugate pipe on compressor (SOK 9951893 pag 4/4) P2,3,4 C8, from C 1,300 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 66.67% 100.00% 100.00% 100.00% 3 - Electrical & Instrument 13,696 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 23.61% 52.57% 60.52% 61.84% 8 - Fire Fighting System 1,280 11 May 2015 14 Sep 2015 11 May 2015 ---- 0.00% 51.09% 77.34% 77.34% 10 - MV&LV Cable trays installation (COMMON TO TRAINS A&B) 320 08 Apr 2015 24 Apr 2015 08 Apr 2015 24 Apr 2015 36.36% 100.00% 100.00% 100.00% 14 - Replacement of Instrumentation on Compressor skid 740 13 Apr 2015 10 Sep 2015 13 Apr 2015 ---- 100.00% 37.84% 37.84% 37.84% 3 - UPS (COMMON TO TRAINS A&B) 160 09 Apr 2015 13 Apr 2015 09 Apr 2015 13 Apr 2015 40.54% 100.00% 100.00% 100.00% 16 - Instrument Air 660 30 Apr 2015 25 Jun 2015 30 Apr 2015 ---- 37.84% 94.55% 94.55% 94.55% 15 - Replacement of Instrumentation on BoP and Process 1,480 14 Apr 2015 12 Oct 2015 14 Apr 2015 ---- 100.00% 56.76% 73.78% 77.03% 13 - Lighting system on field 1,900 17 Apr 2015 05 Nov 2015 17 Apr 2015 ---- 21.05% 50.26% 58.95% 60.53% 11 - Instrument Cable trays 1,400 06 Apr 2015 29 Sep 2015 06 Apr 2015 ---- 20.00% 77.00% 88.00% 90.86% 12 - Cable Laying/Test/Termination 3,642 31 Jul 2014 02 Sep 2015 31 Jul 2014 ---- 2.20% 26.96% 31.27% 38.17% 1 - MV Cable 80 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 0.00% 100.00% 100.00% 100.00% 2 - LV Cable 1,362 12 May 2015 02 Sep 2015 12 May 2015 ---- 100.00% 39.79% 51.32% 69.75% 3 - Instrument Cable 2,200 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 0.00% 16.36% 16.36% 16.36% 4 - Batteries (COMMON TO TRAINS A&B) 180 03 Sep 2015 15 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 5 - F&G (COMMON TO TRAINS A&B) 160 16 Apr 2015 18 Apr 2015 16 Apr 2015 18 Apr 2015 100.00% 100.00% 100.00% 100.00% 7 - Air conditioning system (COMMON TO TRAINS A&B) 80 28 Aug 2015 03 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 1 - Inspections 640 01 Jul 2014 12 Apr 2015 01 Jul 2014 12 Apr 2015 100.00% 100.00% 100.00% 100.00% 2 - Battery room refurbishment (COMMON TO TRAINS A&B) 490 21 Jun 2015 17 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 18 - UCP 344 01 May 2015 30 May 2015 01 May 2015 30 May 2015 0.00% 100.00% 100.00% 100.00% 5 - Pre-Commissioning & Commissioning 3,580 31 Jul 2014 10 Nov 2015 31 Jul 2014 ---- 3.61% 5.26% 5.26% 5.59% 2 - Electrical and control test 20 09 May 2015 10 May 2015 09 May 2015 10 May 2015 0.00% 100.00% 100.00% 100.00% 3 - MVA Transformer activities 140 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100.00% 4 - MCC Activities 80 18 Sep 2015 23 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 6 - Fire fighting system commissioning 420 08 Oct 2015 02 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 7 - DCP Commissioning 320 17 Sep 2015 08 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 8 - UCP activities 640 21 Sep 2015 19 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 9 - Functional test compressor unit and BoP equipment 820 09 Oct 2015 11 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 10 - Motor rotating equipment 360 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 11.11% 11.11% 11.11% 1 - Main and aux lube oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33% 2 - Main and aux seal oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33% 3 - #6 gas cooler motor bump test, belt installation and running test 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 4 - #3 main & #3 stand-by Lube Oil cooler motors bump test, coupling installation and run 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 5 - #3 main & #3 stand-by Seal Oil cooler motors bump test, coupling installation and run t 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 6 - Seal oil degassing tank agitator and blower motor bump test, coupling installation and ru 60 10 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 11 - MV Motor activities 120 11 Oct 2015 13 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 12 - Alignment and Load Coupling installation 360 13 Oct 2015 16 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% 13 - Unit Start-up 300 19 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00% Actual % WO5A CS1A Construction Progress Status Report CONSTRUCTION PHASES & AREAS Budgeted Labour Units Start Finish Actual Start Actual Finish