This document provides a progress update for the GE Compressor Rehabilitation Project. It includes information on 18 work packages that make up the project. As of the June 21st cutoff date, overall progress was 71.14%, with Civil & Structures and Process system work being the most complete at around 88% and 82% respectively. Electrical & Instrument work was lagging at around 62% completion. The project involves rehabilitation of compressors and associated equipment to restore and improve functionality.
1 of 1
Downloaded 12 times
More Related Content
WO5A CS1A Construction Progress Status Report Week #25
1. Project: GE Compressor Rehabilitation Project
Contract No: SIGUP-12-066A/B Cut-off date: 21 Jun 2015
8 10 11 12 13
03 May 15 07 Jun 15 14 Jun 15 21 Jun 15
CS1A - WO4&WO5 CS1A 49,726 01 Jun 2014 10 Nov 2015 01 Jun 2014 ---- 49.99% 65.32% 68.79% 71.14%
4 - Construction 46,146 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 53.94% 70.43% 74.19% 76.23%
4 - Site office and field work area preparation 1,800 01 Jul 2014 31 Jul 2014 01 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100%
1 - Mechanical 14,850 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 50.27% 67.38% 68.99% 73.85%
1 - Compressor on-skid and Auxiliaries 8,100 13 Mar 2015 05 Oct 2015 13 Mar 2015 ---- 46.32% 63.88% 63.88% 67.05%
1 - Centrifugal Compressor 1,630 15 Mar 2015 05 Oct 2015 15 Mar 2015 ---- 42.33% 42.33% 42.33% 42.33%
2 - Gear box 680 15 Mar 2015 15 Sep 2015 15 Mar 2015 ---- 32.35% 32.35% 32.35% 32.35%
3 - Electrical motor 420 15 Mar 2015 22 Jun 2015 15 Mar 2015 ---- 85.71% 90.48% 90.48% 90.48%
4 - Compressor Auxiliaries 2,270 13 Mar 2015 18 Sep 2015 13 Mar 2015 ---- 56.78% 92.29% 92.29% 92.29%
8 - Seal Oil Overhead Tank (New) 80 23 Apr 2015 17 Sep 2015 23 Apr 2015 ---- 0.00% 0.00% 0.00% 0.00%
2 - Manual valve replacement 750 05 Apr 2015 13 Aug 2015 05 Apr 2015 ---- 96.67% 96.67% 96.67% 96.67%
5 - Heaters 100 11 Apr 2015 23 Apr 2015 11 Apr 2015 23 Apr 2015 0.00% 100.00% 100.00% 100.00%
1 - LO and SO motor and pumps replacement 320 13 Mar 2015 26 Apr 2015 13 Mar 2015 26 Apr 2015 85.00% 100.00% 100.00% 100.00%
3 - Control valves (PCV & DPCV & LCV) 100 10 Apr 2015 27 Jun 2015 10 Apr 2015 ---- 60.00% 60.00% 60.00% 60.00%
7 - Compressor Skid Instrument 220 05 Apr 2015 18 Sep 2015 05 Apr 2015 ---- 67.14% 86.36% 86.36% 86.36%
6 - TCV piping modification and valve installation 600 04 May 2015 21 May 2015 04 May 2015 21 May 2015 100.00% 100.00% 100.00% 100.00%
4 - PSV 100 10 Apr 2015 10 May 2015 10 Apr 2015 10 May 2015 81.82% 100.00% 100.00% 100.00%
6 - Oil flushing preparation and execution 2,840 14 Mar 2015 09 Sep 2015 14 Mar 2015 ---- 36.27% 52.11% 52.11% 65.00%
5 - Oil cooler 260 15 Mar 2015 14 Aug 2015 15 Mar 2015 ---- 53.85% 76.92% 76.92% 76.92%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 0.00% 50.00% 50.00% 50.00%
2 - Pneumatic Test 140 15 Mar 2015 04 Apr 2015 15 Mar 2015 04 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Process system 6,750 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 54.87% 71.47% 74.96% 82.01%
1 - Gas cooler 1,480 22 Apr 2015 09 Sep 2015 22 Apr 2015 ---- 63.70% 50.81% 65.41% 83.78%
2 - Hydraulic test 1,060 22 Apr 2015 16 Jun 2015 22 Apr 2015 16 Jun 2015 85.42% 69.81% 81.13% 100.00%
1 - Motor and fan replacement 120 09 Apr 2015 14 Aug 2015 09 Apr 2015 ---- 33.33% 50.00% 50.00% 50.00%
3 - Process Pipe 2,920 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 33.33% 65.62% 65.62% 72.60%
5 - Process piping cleaning 960 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 55.56% 91.25% 91.25% 100.00%
3 - PSV 480 21 Jul 2014 11 Oct 2015 21 Jul 2014 ---- 78.95% 33.33% 33.33% 33.33%
4 - MOV and SDV 540 21 Jul 2014 07 Sep 2015 21 Jul 2014 ---- 65.70% 33.33% 33.33% 33.33%
2 - Process Control Valves 180 21 Jul 2014 15 Sep 2015 21 Jul 2014 ---- 77.27% 55.56% 55.56% 55.56%
1 - Manual valve replacement 760 20 Apr 2015 27 Jun 2015 20 Apr 2015 ---- 54.74% 78.95% 78.95% 94.74%
2 - Vessel 2,350 12 Mar 2015 07 Jul 2015 12 Mar 2015 ---- 77.78% 91.74% 92.60% 92.60%
4 - Level control valve & Glass - Klinger 510 17 Apr 2015 07 Jun 2015 17 Apr 2015 07 Jun 2015 40.39% 100.00% 100.00% 100.00%
2 - Manual valve replacement on Vessels V5,V6,V7,V10 1,100 16 Apr 2015 07 Jul 2015 16 Apr 2015 ---- 20.27% 96.36% 96.36% 96.36%
3 - Level Control Valve Replacement 380 14 Apr 2015 07 Jul 2015 14 Apr 2015 ---- 28.30% 80.53% 85.79% 85.79%
1 - Inspection 360 12 Mar 2015 22 Jun 2015 12 Mar 2015 ---- 0.00% 77.78% 77.78% 77.78%
2 - Civil & Structures 15,800 26 Jan 2015 12 Sep 2015 26 Jan 2015 ---- 77.78% 85.03% 87.66% 88.23%
2 - Structures 2,920 26 Jan 2015 27 Aug 2015 26 Jan 2015 ---- 91.78% 91.78% 91.78% 91.78%
1 - Overhead crane replacement 2,680 26 Jan 2015 14 Mar 2015 26 Jan 2015 14 Mar 2015 0.00% 100.00% 100.00% 100.00%
2 - Gratings and platform 240 15 Aug 2015 27 Aug 2015 ---- ---- 100.00% 0.00% 0.00% 0.00%
1 - Civil 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
1 - Excavation & Foundation Works (COMMON TO TRAINS A&B) 12,880 01 Mar 2015 12 Sep 2015 01 Mar 2015 ---- 74.61% 83.49% 86.72% 87.42%
7 - Fiber opthic/Ethernet from UCP to HMI: (SOK9951893 cable routing plan) 120 30 Mar 2015 09 May 2015 30 Mar 2015 09 May 2015 94.44% 100.00% 100.00% 100.00%
9 - Additional Earthing System 1,080 05 Apr 2015 09 May 2015 05 Apr 2015 09 May 2015 68.33% 100.00% 100.00% 100.00%
3 - Cable routing for compressor area (T7 e T8) 2,700 16 Mar 2015 12 Sep 2015 16 Mar 2015 ---- 86.67% 70.00% 70.00% 73.33%
1 - UCP (ref dwg.SOK2310988) 900 01 Mar 2015 09 May 2015 01 Mar 2015 09 May 2015 93.85% 100.00% 100.00% 100.00%
2 - Cable routing from MCC to UCP (T1, DB1, T2) 2,780 13 Mar 2015 08 Jun 2015 13 Mar 2015 08 Jun 2015 66.67% 85.00% 100.00% 100.00%
6 - Corrugated pipes on BOP [-P6,7,17,19,20,23¡ªfrom C5 to C7, C9, from C1 1,300 30 Mar 2015 16 May 2015 30 Mar 2015 16 May 2015 97.69% 100.00% 100.00% 100.00%
4 - Cable routing for BOP [T5A, DB8A, between gas cooler and V7=T5A/1 e sle 2,700 16 Mar 2015 10 Sep 2015 16 Mar 2015 ---- 65.76% 66.67% 66.67% 66.67%
5 - Corrugate pipe on compressor (SOK 9951893 pag 4/4) P2,3,4 C8, from C 1,300 28 Mar 2015 16 May 2015 28 Mar 2015 16 May 2015 66.67% 100.00% 100.00% 100.00%
3 - Electrical & Instrument 13,696 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 23.61% 52.57% 60.52% 61.84%
8 - Fire Fighting System 1,280 11 May 2015 14 Sep 2015 11 May 2015 ---- 0.00% 51.09% 77.34% 77.34%
10 - MV&LV Cable trays installation (COMMON TO TRAINS A&B) 320 08 Apr 2015 24 Apr 2015 08 Apr 2015 24 Apr 2015 36.36% 100.00% 100.00% 100.00%
14 - Replacement of Instrumentation on Compressor skid 740 13 Apr 2015 10 Sep 2015 13 Apr 2015 ---- 100.00% 37.84% 37.84% 37.84%
3 - UPS (COMMON TO TRAINS A&B) 160 09 Apr 2015 13 Apr 2015 09 Apr 2015 13 Apr 2015 40.54% 100.00% 100.00% 100.00%
16 - Instrument Air 660 30 Apr 2015 25 Jun 2015 30 Apr 2015 ---- 37.84% 94.55% 94.55% 94.55%
15 - Replacement of Instrumentation on BoP and Process 1,480 14 Apr 2015 12 Oct 2015 14 Apr 2015 ---- 100.00% 56.76% 73.78% 77.03%
13 - Lighting system on field 1,900 17 Apr 2015 05 Nov 2015 17 Apr 2015 ---- 21.05% 50.26% 58.95% 60.53%
11 - Instrument Cable trays 1,400 06 Apr 2015 29 Sep 2015 06 Apr 2015 ---- 20.00% 77.00% 88.00% 90.86%
12 - Cable Laying/Test/Termination 3,642 31 Jul 2014 02 Sep 2015 31 Jul 2014 ---- 2.20% 26.96% 31.27% 38.17%
1 - MV Cable 80 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 0.00% 100.00% 100.00% 100.00%
2 - LV Cable 1,362 12 May 2015 02 Sep 2015 12 May 2015 ---- 100.00% 39.79% 51.32% 69.75%
3 - Instrument Cable 2,200 01 Jul 2014 10 Nov 2015 01 Jul 2014 ---- 0.00% 16.36% 16.36% 16.36%
4 - Batteries (COMMON TO TRAINS A&B) 180 03 Sep 2015 15 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - F&G (COMMON TO TRAINS A&B) 160 16 Apr 2015 18 Apr 2015 16 Apr 2015 18 Apr 2015 100.00% 100.00% 100.00% 100.00%
7 - Air conditioning system (COMMON TO TRAINS A&B) 80 28 Aug 2015 03 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
1 - Inspections 640 01 Jul 2014 12 Apr 2015 01 Jul 2014 12 Apr 2015 100.00% 100.00% 100.00% 100.00%
2 - Battery room refurbishment (COMMON TO TRAINS A&B) 490 21 Jun 2015 17 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
18 - UCP 344 01 May 2015 30 May 2015 01 May 2015 30 May 2015 0.00% 100.00% 100.00% 100.00%
5 - Pre-Commissioning & Commissioning 3,580 31 Jul 2014 10 Nov 2015 31 Jul 2014 ---- 3.61% 5.26% 5.26% 5.59%
2 - Electrical and control test 20 09 May 2015 10 May 2015 09 May 2015 10 May 2015 0.00% 100.00% 100.00% 100.00%
3 - MVA Transformer activities 140 31 Jul 2014 31 Jul 2014 31 Jul 2014 31 Jul 2014 100.00% 100.00% 100.00% 100.00%
4 - MCC Activities 80 18 Sep 2015 23 Sep 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Fire fighting system commissioning 420 08 Oct 2015 02 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
7 - DCP Commissioning 320 17 Sep 2015 08 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
8 - UCP activities 640 21 Sep 2015 19 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
9 - Functional test compressor unit and BoP equipment 820 09 Oct 2015 11 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
10 - Motor rotating equipment 360 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 11.11% 11.11% 11.11%
1 - Main and aux lube oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
2 - Main and aux seal oil motor bump test, coupling installation and coupled run test 60 01 Jun 2015 12 Oct 2015 01 Jun 2015 ---- 0.00% 33.33% 33.33% 33.33%
3 - #6 gas cooler motor bump test, belt installation and running test 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
4 - #3 main & #3 stand-by Lube Oil cooler motors bump test, coupling installation and run 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
5 - #3 main & #3 stand-by Seal Oil cooler motors bump test, coupling installation and run t 60 10 Oct 2015 12 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
6 - Seal oil degassing tank agitator and blower motor bump test, coupling installation and ru 60 10 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
11 - MV Motor activities 120 11 Oct 2015 13 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
12 - Alignment and Load Coupling installation 360 13 Oct 2015 16 Oct 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
13 - Unit Start-up 300 19 Oct 2015 10 Nov 2015 ---- ---- 0.00% 0.00% 0.00% 0.00%
Actual %
WO5A CS1A Construction Progress Status Report
CONSTRUCTION PHASES & AREAS
Budgeted
Labour
Units
Start Finish
Actual
Start
Actual Finish