The document outlines a development plan for TheExtraAEdge with two phases of feature development from October 2012 to December 2012. Phase 1 includes 13 activities related to core functionality, forums, messaging, and feeds. Phase 2 includes 10 additional activities focused on user profiles, events, subscriptions, and social integration. The plan schedules pre-launch testing from December 29-31 and public launch on January 1, followed by a week of post-launch testing and updates.
1 of 1
Download to read offline
More Related Content
TheExtraAEdge+Development+Plan.pdf
1. TheExtraAEdge Development Plan
Sr. No Activities Start Date End Date Status
FR 0.0 Core Framework, Complete
Global Settings, Complete
UI 1.4 User Registration & Login via DB, Complete
FR 1.1 Blog, Complete
FR 1.2 - Standard Forum, Complete
FR 1.6 - Private Message, Complete
PHASE - 1 FR 1.5 - Document Management Core Framework 1-Oct-12 26-Nov-12 Complete
FR1.12 Latest activity feeds In progress
FR 1.10 Admin Control Panel Partial complete
FR 1.7 RSS (Blog/Forum are RSS Ready) Complete
FR 1.10 Moderator Control (Tread/Forum) Partial complete
FR 3.1 Opinion Poll Complete
FR1.18 SEO In progress
Total Count 13
FR1.9 Photos & Videos
UI 1.3 User Pofile
FR 1.10 User Control Panel
FR 1.3 - Events 27-Nov-12 27-Dec-12
PHASE - 2
FR 1.8 Subscription
FR 1.11 Social Network Integration via ShareThis Complete
UI 1.1 and UI 1.2 Design
FR 1.4 User Groups
Total Count 10
PRE-LAUNCH www.theextraaedge.com 29-Dec-12 31-Dec-12
LAUNCH of Website 1-Jan-13
Live Web Testing & Critical issue analysis/schedule patch/fixes 2-Jan-13 5-Jan-13
Update to Live 6-Jan-13