際際滷

際際滷Share a Scribd company logo
CRESTMEAD
Breakthrough Improvement
Demonstration
Agenda
 Introduction
 De-Bottlenecking Method
 Summary of what was achieved
 Question and Answer time
DBM
The De-Bottlenecking Method
Rob Tilley
1. Find the throughput bottleneck.
2. Ensure the throughput bottleneck is running at its
current optimum speed.
3. Optimise the accumulation to protect the throughput
bottleneck.
4. Solve and eliminate speed restricting problems on the
throughput bottleneck.
5. Solve and eliminate downtime problems on the
throughput bottleneck.
6. Repeat steps 1 to 5 until the throughput bottleneck is
the capacity bottleneck and it is running at its absolute
maximum speed
7. Improve the availability of the non-bottleneck
processes to minimise their impact on the
bottleneck.
De-Bottlenecking Method (DBM)
Using DBM in the Factory
 The team was introduced to DBM as the
fastest way to determine how to improve
performance for each Line/product
combination run.
Lets Take a look at what they did!
DBM Step 1
Determining the throughput bottleneck
Rob Tilley
Maximum Speed on Winder #2 Re-winder 2 Ply 400
Sheet Product
The bottleneck was found to be the Re-Winder/Log Saw
0
50
100
150
200
250
300
350
400
450
Equipment catagory
RollsPerminuterate
Capacity 305 264 254 180 384 400
Speed 160 130 130 140 140 400
Throughput 97.6 126.1 114.4 91 124.6 400
Rew inder Tail Sealer Log Saw Wrapper Case packer Palletiser
DBM Step 2
Ensure the Bottleneck is running at its current
optimum speed
Glen
Transfer Process
What did we achieve?
 The Geibler folder was being run at 45,000 napkins per
hour on the two occasions the group observed.
 A speed trial was undertaken on the Geibler where the
unit speed was increased under controlled conditions
to 59,000 napkins per hour
 At this speed, the operator could not comfortably keep
up with the product being supplied
 The speed of the Geibler was reduced to 50,000 where
the operator could comfortably handle throughput
A POTENTIAL INCREASE IN THROUGHPUT OF 11%
FROM FREE SPEED!
DBM Step 3
Optimising the state of the
accumulation
Sal & MAX
How does optimising accumulation
work?
 The purpose of accumulation is to protect the
throughput bottleneck from downtime on other
areas of the line.
 Accumulation should be kept full upstream of
the throughput bottleneck and empty
downstream of the throughput bottleneck.
How does optimising accumulation work on
the Perini Line now?
 The Accumulator was 他 - Full on most visits out to the
Perini Line.
 The Downstream processes were not draining the
Accumulator quick enough to protect the throughput
bottleneck.
 The Re-winder would stop frequently as the
Accumulator reached its capacity.
 The packer and Log saw speed would bounce back
and fourth as the line control would stop the units.
Max
What did we do?
 Automated Line control is being progressed along the
Entire Perini line
 This will allow all equipment to communicate with
each other and maintain optimum speeds without the
need for operator input.
DBM Step 4  Winder #2
Solve and eliminate speed restricting problems
on the throughput bottleneck
Wesley Peirce
What did we find?
 The maximum speed (Capacity) for winder #2
was stated as 610m/min on 1000 sheet product
but it was always running below this.
 The operators on the line were running to pre-
determined set points and procedures and were
still unable to obtain optimum speed.
 The timing mechanism (Gemco) controlling the cut off point
of the Log was found to be incorrectly set on each occasion
experienced at the Re-winder.
 This was only allowing a throughput rate of 319m/min.
 The Gemco, when set correctly by an experienced operator
resulted in a speed increase to 509m/min.
AN INCREASE IN OUTPUT OF 59% FROM THE WINDER
What did we find out
 Set up of the Re-winder required a high
degree of training and was not
instinctive to the operators.
 Set points on the Gemco unit were not
stable at each change over
What we found.
 New procedures have been put in place to
ensure the expected run speeds are achieved
with support from shift leaders
 Operator training across all shifts will
commence to communicate new procedures
and expectations.
 Installation of PLC control on the Re-winder to
simplify the set up process.
What have we done about it?
DBM Step 5
Solve and eliminate significant downtime problems
on the throughput bottleneck.
Martin
Solving a downtime problem
Winder #2 Cookie Monster
Max (Paul)
During Week 3 of the BID, the team moved onto Winder #2.
What did we find?
 Less than 20% of all cookies were being
removed from the process and rolls were
turning over.
 This caused jam ups and downtime on the
line.
 A full time casual was put in place to manage
this problem.
What did we do?
 The team took a closer look at the cookie monster
problem using PCS and came up with the following
results:
 Took conveyor system back to original specification.
 Moved the belts further into the Log saw
 Attached brushes to the Log saw as per original spec
 Set Guide rails to correct height
What did we achieve?
 100% of all Cookies which fall into acceptable
cookie specification are eliminated from the
system.
 All rolls are positioned on their side
 All cookies are dropped onto their bums and
eliminated from the path of travel.
How do make sure this keeps happening?
 Jig manufactured to ensure repeatability in setup of
cookie monster and associated guide railing.
 Operating procedure outlined and put onto machine
DBM Step 7
Solve and eliminate significant downtime problems
on the non bottleneck processes to support the
Capacity/Throughput bottleneck.
Peter
The Mud Press
The Mud Press
 It was discovered that a high percentage of waste in
this process was water.
 Merino currently pay for Mud to be taken away at a
standard cost per bin + a tonnage fee.
What did we find?
 The presses were not running at optimal pressure and
as such the optimal amount of water was not being
removed from the mud.
 The screen wash was leaking a large volume of water
directly into the pressed mud and being dumped.
 The mud bins were exposed to the elements and each
time it rained, the rain water was being absorbed by
the mud
What did we do?
 The group has increased the pressure of the press to
optimise the amount of water being removed from the mud.
 The screen shower has been relocated upstream of the mud
press, eliminating all water re entering the pressed mud
from the process
 The group is in the process of obtaining quotes for a
permanent shelter to cover the bins and protecting them
from rain.
 Identified and reintroduced the operational procedure for
the cleaning of the mud press showers.
 The group is looking into markets for this mud.
What did we achieve?
 The initial testing done on the mud 100%
recycled showed a moisture content of 68%.
 After the completion of all actions on the mud
press, the moisture content now stands at 54%.
 This equates to 2.1 tonnes less water per day
leaving the site or $22,000 per year.
A 26% reduction in moisture content.
Questions and Discussion.
Ad

Recommended

Drum-Buffer-Rope
Drum-Buffer-Rope
Craig Paxson
Kanban Pull System
Kanban Pull System
Dorina Grossu
Kanban test
Kanban test
C Kaye Woodard
Schneider Case Study Challenge
Schneider Case Study Challenge
Nikhil Kejriwal
How to Reduce Changeover Time and Increase Throughput
How to Reduce Changeover Time and Increase Throughput
OH!Manufacturing
Presentation kanban
Presentation kanban
Nasir Shakil
Reduce SMT Changeover Time
Reduce SMT Changeover Time
Damian Denis
Rob Tilley Overiew
Rob Tilley Overiew
Robert Tilley
True Efficiency Graphs
True Efficiency Graphs
Robert Tilley
Board report August 07
Board report August 07
Robert Tilley
mud press showers clean
mud press showers clean
Robert Tilley
NRFPRESENTATIONNEWSAIP1finallypresentation13july
NRFPRESENTATIONNEWSAIP1finallypresentation13july
Musa Lonwabo Kwetana
Pp toddler temper tantrums
Pp toddler temper tantrums
Melissa Steinke-Schlachter
Assessment Criteria - Menegatti
Assessment Criteria - Menegatti
Robert Tilley
Hydraulic accumulator
Hydraulic accumulator
Shibi Chakravarthy
Fct
Fct
Shibi Chakravarthy
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
saeedahmad7007
2 stroke cycle engines
2 stroke cycle engines
Shibi Chakravarthy
Pressure die casting
Pressure die casting
Shibi Chakravarthy
QC CIRCLE PRESENTATION (1).pptx
QC CIRCLE PRESENTATION (1).pptx
RajeshGanesan24
Lean consulting
Lean consulting
ssasolutions
Bed Rail Report
Bed Rail Report
Eric Mosley
Chemical process debottlenecking
Chemical process debottlenecking
Stephen (Steve) Galante
Packaging opperations, singapore, ipt west tablet
Packaging opperations, singapore, ipt west tablet
Mark Stevens
Standing on the shoulders of giants
Standing on the shoulders of giants
Yossi Bonomo
5 Steps to implementing Lean
5 Steps to implementing Lean
Julian Kalac P.Eng
Final PPT Presentation
Final PPT Presentation
Adam Lu
SMED
SMED
Rashmi kavya
JC- webinar presentation
JC- webinar presentation
Jim Cox, CPIM

More Related Content

Viewers also liked (12)

True Efficiency Graphs
True Efficiency Graphs
Robert Tilley
Board report August 07
Board report August 07
Robert Tilley
mud press showers clean
mud press showers clean
Robert Tilley
NRFPRESENTATIONNEWSAIP1finallypresentation13july
NRFPRESENTATIONNEWSAIP1finallypresentation13july
Musa Lonwabo Kwetana
Pp toddler temper tantrums
Pp toddler temper tantrums
Melissa Steinke-Schlachter
Assessment Criteria - Menegatti
Assessment Criteria - Menegatti
Robert Tilley
Hydraulic accumulator
Hydraulic accumulator
Shibi Chakravarthy
Fct
Fct
Shibi Chakravarthy
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
SUPERCRITICAL FUEL INJECTION-A PROMISING TECHNOLOGY FOR IMPROVED FUEL EFFICIE...
saeedahmad7007
2 stroke cycle engines
2 stroke cycle engines
Shibi Chakravarthy
Pressure die casting
Pressure die casting
Shibi Chakravarthy

Similar to BID Final Presentation Creastmead V2.6 crews (20)

QC CIRCLE PRESENTATION (1).pptx
QC CIRCLE PRESENTATION (1).pptx
RajeshGanesan24
Lean consulting
Lean consulting
ssasolutions
Bed Rail Report
Bed Rail Report
Eric Mosley
Chemical process debottlenecking
Chemical process debottlenecking
Stephen (Steve) Galante
Packaging opperations, singapore, ipt west tablet
Packaging opperations, singapore, ipt west tablet
Mark Stevens
Standing on the shoulders of giants
Standing on the shoulders of giants
Yossi Bonomo
5 Steps to implementing Lean
5 Steps to implementing Lean
Julian Kalac P.Eng
Final PPT Presentation
Final PPT Presentation
Adam Lu
SMED
SMED
Rashmi kavya
JC- webinar presentation
JC- webinar presentation
Jim Cox, CPIM
Flexco Belt Conveyor Product Overview
Flexco Belt Conveyor Product Overview
James Wood (4000+ Connections in Nigeria)
Flexco Belt Conveyor Product overview
Flexco Belt Conveyor Product overview
James Wood (4000+ Connections in Nigeria)
Final Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and Gamble
Elaine Mau
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
Julian Kalac P.Eng
X4047_enAU_3881_BCPIntroGuide_1215
X4047_enAU_3881_BCPIntroGuide_1215
alan kusuma
Siemens Innovation Tools2010
Siemens Innovation Tools2010
Kirkdx
21 st Century Manufacturing Not Without The Basic
21 st Century Manufacturing Not Without The Basic
Marino Associates, LLC
Tps overview
Tps overview
Jeslou Yag
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Hamza Nasir
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3
Julien Lecadou,MSc.
QC CIRCLE PRESENTATION (1).pptx
QC CIRCLE PRESENTATION (1).pptx
RajeshGanesan24
Lean consulting
Lean consulting
ssasolutions
Bed Rail Report
Bed Rail Report
Eric Mosley
Packaging opperations, singapore, ipt west tablet
Packaging opperations, singapore, ipt west tablet
Mark Stevens
Standing on the shoulders of giants
Standing on the shoulders of giants
Yossi Bonomo
5 Steps to implementing Lean
5 Steps to implementing Lean
Julian Kalac P.Eng
Final PPT Presentation
Final PPT Presentation
Adam Lu
JC- webinar presentation
JC- webinar presentation
Jim Cox, CPIM
Final Review Elaine Mau Procter and Gamble
Final Review Elaine Mau Procter and Gamble
Elaine Mau
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
LEAN SMED TRAINING FOR SUPERVISORS AND OPERATORS
Julian Kalac P.Eng
X4047_enAU_3881_BCPIntroGuide_1215
X4047_enAU_3881_BCPIntroGuide_1215
alan kusuma
Siemens Innovation Tools2010
Siemens Innovation Tools2010
Kirkdx
21 st Century Manufacturing Not Without The Basic
21 st Century Manufacturing Not Without The Basic
Marino Associates, LLC
Tps overview
Tps overview
Jeslou Yag
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Internship Presentation_Hamza-Nasir-Mechatronics-CEME_NUST
Hamza Nasir
Customizing job shop scheduling using microsoft dynamics ax part2 3
Customizing job shop scheduling using microsoft dynamics ax part2 3
Julien Lecadou,MSc.
Ad

BID Final Presentation Creastmead V2.6 crews

  • 2. Agenda Introduction De-Bottlenecking Method Summary of what was achieved Question and Answer time
  • 4. 1. Find the throughput bottleneck. 2. Ensure the throughput bottleneck is running at its current optimum speed. 3. Optimise the accumulation to protect the throughput bottleneck. 4. Solve and eliminate speed restricting problems on the throughput bottleneck. 5. Solve and eliminate downtime problems on the throughput bottleneck. 6. Repeat steps 1 to 5 until the throughput bottleneck is the capacity bottleneck and it is running at its absolute maximum speed 7. Improve the availability of the non-bottleneck processes to minimise their impact on the bottleneck. De-Bottlenecking Method (DBM)
  • 5. Using DBM in the Factory The team was introduced to DBM as the fastest way to determine how to improve performance for each Line/product combination run. Lets Take a look at what they did!
  • 6. DBM Step 1 Determining the throughput bottleneck Rob Tilley
  • 7. Maximum Speed on Winder #2 Re-winder 2 Ply 400 Sheet Product The bottleneck was found to be the Re-Winder/Log Saw 0 50 100 150 200 250 300 350 400 450 Equipment catagory RollsPerminuterate Capacity 305 264 254 180 384 400 Speed 160 130 130 140 140 400 Throughput 97.6 126.1 114.4 91 124.6 400 Rew inder Tail Sealer Log Saw Wrapper Case packer Palletiser
  • 8. DBM Step 2 Ensure the Bottleneck is running at its current optimum speed Glen
  • 10. What did we achieve? The Geibler folder was being run at 45,000 napkins per hour on the two occasions the group observed. A speed trial was undertaken on the Geibler where the unit speed was increased under controlled conditions to 59,000 napkins per hour At this speed, the operator could not comfortably keep up with the product being supplied The speed of the Geibler was reduced to 50,000 where the operator could comfortably handle throughput A POTENTIAL INCREASE IN THROUGHPUT OF 11% FROM FREE SPEED!
  • 11. DBM Step 3 Optimising the state of the accumulation Sal & MAX
  • 12. How does optimising accumulation work? The purpose of accumulation is to protect the throughput bottleneck from downtime on other areas of the line. Accumulation should be kept full upstream of the throughput bottleneck and empty downstream of the throughput bottleneck.
  • 13. How does optimising accumulation work on the Perini Line now? The Accumulator was 他 - Full on most visits out to the Perini Line. The Downstream processes were not draining the Accumulator quick enough to protect the throughput bottleneck. The Re-winder would stop frequently as the Accumulator reached its capacity. The packer and Log saw speed would bounce back and fourth as the line control would stop the units. Max
  • 14. What did we do? Automated Line control is being progressed along the Entire Perini line This will allow all equipment to communicate with each other and maintain optimum speeds without the need for operator input.
  • 15. DBM Step 4 Winder #2 Solve and eliminate speed restricting problems on the throughput bottleneck Wesley Peirce
  • 16. What did we find? The maximum speed (Capacity) for winder #2 was stated as 610m/min on 1000 sheet product but it was always running below this. The operators on the line were running to pre- determined set points and procedures and were still unable to obtain optimum speed.
  • 17. The timing mechanism (Gemco) controlling the cut off point of the Log was found to be incorrectly set on each occasion experienced at the Re-winder. This was only allowing a throughput rate of 319m/min. The Gemco, when set correctly by an experienced operator resulted in a speed increase to 509m/min. AN INCREASE IN OUTPUT OF 59% FROM THE WINDER What did we find out
  • 18. Set up of the Re-winder required a high degree of training and was not instinctive to the operators. Set points on the Gemco unit were not stable at each change over What we found.
  • 19. New procedures have been put in place to ensure the expected run speeds are achieved with support from shift leaders Operator training across all shifts will commence to communicate new procedures and expectations. Installation of PLC control on the Re-winder to simplify the set up process. What have we done about it?
  • 20. DBM Step 5 Solve and eliminate significant downtime problems on the throughput bottleneck. Martin
  • 21. Solving a downtime problem Winder #2 Cookie Monster Max (Paul) During Week 3 of the BID, the team moved onto Winder #2.
  • 22. What did we find? Less than 20% of all cookies were being removed from the process and rolls were turning over. This caused jam ups and downtime on the line. A full time casual was put in place to manage this problem.
  • 23. What did we do? The team took a closer look at the cookie monster problem using PCS and came up with the following results: Took conveyor system back to original specification. Moved the belts further into the Log saw Attached brushes to the Log saw as per original spec Set Guide rails to correct height
  • 24. What did we achieve? 100% of all Cookies which fall into acceptable cookie specification are eliminated from the system. All rolls are positioned on their side All cookies are dropped onto their bums and eliminated from the path of travel.
  • 25. How do make sure this keeps happening? Jig manufactured to ensure repeatability in setup of cookie monster and associated guide railing. Operating procedure outlined and put onto machine
  • 26. DBM Step 7 Solve and eliminate significant downtime problems on the non bottleneck processes to support the Capacity/Throughput bottleneck. Peter
  • 28. The Mud Press It was discovered that a high percentage of waste in this process was water. Merino currently pay for Mud to be taken away at a standard cost per bin + a tonnage fee.
  • 29. What did we find? The presses were not running at optimal pressure and as such the optimal amount of water was not being removed from the mud. The screen wash was leaking a large volume of water directly into the pressed mud and being dumped. The mud bins were exposed to the elements and each time it rained, the rain water was being absorbed by the mud
  • 30. What did we do? The group has increased the pressure of the press to optimise the amount of water being removed from the mud. The screen shower has been relocated upstream of the mud press, eliminating all water re entering the pressed mud from the process The group is in the process of obtaining quotes for a permanent shelter to cover the bins and protecting them from rain. Identified and reintroduced the operational procedure for the cleaning of the mud press showers. The group is looking into markets for this mud.
  • 31. What did we achieve? The initial testing done on the mud 100% recycled showed a moisture content of 68%. After the completion of all actions on the mud press, the moisture content now stands at 54%. This equates to 2.1 tonnes less water per day leaving the site or $22,000 per year. A 26% reduction in moisture content.