This document is a progress report for a drainage canal construction project in Bengkalis Regency from September 17th to 23rd. It details the work completed this week including excavating 161 cubic meters of material, pouring 62 cubic meters of concrete, and laying pipes and bricks. The project is 93% completed overall based on the scheduled scope of work.