A Sustainable Systems Integration Approach to
  the Idyllwild Arts Academy Performing Arts
                  Center (IPAC)



          Escalante Architects
     Ana Escalente, AIA Founder and Principal
          121 South Palm Canyon Drive
            Palm Springs, CA 92262
                  760.323.1925
          www.escalantearchitects.com
                 December 2008
Summary
 1. What we are going to talk about.
 2. What we are talking about.
 3. What we just talked about.
Project Team




   Design Architect: Escalante Architects
   Ana Escalante, AIA - Founding Principal
   Cliff Cortland Partner
   Ivan Ivanov  Designer
   Stan - Designer
   Dicle Bath - Designer
   Ashi Martin - Designer
   Zach Morgan - Designer
   Matias Cena - Designer
   Executive Architects: HMC
   Planning: Green Design Build, Alex
    Meyerhoff
   Structural: J. A. Martin & Associates
   Mechanical, Plumbing, Electrical &
    Sustainability: IBE Consulting Engineers
   Civil Engineer: Sanborn A&E
   Acoustical Engineer: Nagata Engineering
   Landscape Architect: TKD & Associates

                                               Idyllwild Arts Academy , Idyllwild California
Ana Bio
              SUSTAINABILITY & DESIGN PRINCIPLES
                 Creating Community through Design




Architecture is frozen music. - Goethe
Setting: Idyllwild, California
Setting



Location: 33属4444N, 116属4258W
Elevation 5,000 msl
Ave. Temp.: 55.2
    Ave. Min.: 39.7
    Ave. Max.: 70.7
Annual Rainfall: 14.6
Snowfall: 39.3
Pop: 3,504 (2000)
Challenge/Project Objective



   Create a viable educational
    laboratory, with a theater and
    concert hall, which establish the
    Idyllwild Arts Academy as the
    nations preeminent arts
    preparatory school; and

   Provide a creative environment in
    which the next generation of
    musical and dramatic practitioners
    can hone their craft, while also
    providing for a range of artistic
    experiences for diverse audiences
    within both the school and
    community at large.
Concept: A Sustainable Approach to Design



                                      "Sustainability is an economic state
                                      where the demands placed upon the
                                      environment       by   people   and
                                      commerce can be met without
                                      reducing the capacity of the
                                      environment to provide for future
                                      generations.
                                      Leave the world better than you
                                      found it
                                      Take no more than you need
                                      Try not to harm life or the
                                      environment
                                      Make amends if you do
                                      source: www.sustainability.ca
A Green or Sustainable Approach to Design


Team Philosophy: Functionality
 Devise an architectural program
  serving students and faculty as
  well as community members.
 Use high quality materials to
  enhance indoor & out-door
  experiences.
 Create a repertoire of public
  spaces.
 Reinforce pedestrian circulation.
 Maximize efficiency.
Sustainable Design
Creating Community Through Design



Team Philosophy: Integrate
 Systems
 Utilize green or sustainable
  systems to meet program
  requirements.
Balance project solutions into an
 integrated and seamless whole.
 Engineer solutions to specific
  site and climatic challenges.
 Enhance accessibility pursuant
  to   the      Americans  with
  Disabilities Act
 Control variables to ensure
  success: schedule, budget and
  quality.
Site Analysis and Environmental Assessment



    Climate
    Hazards  Wildfire
    Drainage/Vegetation
    Topography (+ 7 feet)
    Vernacular Architecture
    Seismic Requirements
    Circulation, Access and
     Egress
Sustainable System Integration  Designed for Maximum Performance


                                        Integrated Wall and Roof Panel
                                         Structural Systems
                                        Mechanical Systems (HVAC, plumbing,
                                         electrical)
                                        Glazing Systems (High performance
                                         glass, and thermally broken frames)
                                        Acoustic Design Systems
                                        Renewable/Local Resources &
                                         Technology (Budget Driven)
                                        Cladding  Sustainable Harvest Wood
                                        Energy Modeling  Fluid Dynamics
                                         Analysis
Preliminary Design Ideas (SWOT Analysis, We can rephrase
this as a Strength, Weakness Opportunities and Threat
Analysis)


                                      Framing Views
                                      Existing Campus Vernacular
                                      Sustainability and Systems
                                      Climatic Variation and Temperature
                                      Response to Climate
                                      Solar Orientation
                                      Building Mass
                                      Systems Integration
                                      Outdoor/Indoor Permeability
                                      Landscape Design
                                      Daylight and Night Skies
                                      Loading and Exiting
                                      Circulation
                                      Energy Conservation
                                      Prevailing Winds
                                      Topography
                                      Vegetation
                                      Fire Regime
                                      Ambient Noise
                                      Separation of Functions
                                      Acoustical Design
                                      Structural Integrity
                                      Educational Mission
                                      Community Resource
                                      Exterior Finishes and Cladding
                                      Creating Public Space and Seasonal Courtyards
                                      Rooted in Local Vernacular and Building Function
                                      Life Cycle Costs (Operations and Maintenance)
Theatre Program
Building Area 10,000 sf.
     Seating for 200
     Stage 3,700 sf.
     Green Room 1,500 sf.
     Fly Tower 45
     Proscenium 15 x 30
     Thrust stage
     Restrooms
     Star Gazing Deck
     Lighting and Sound Booths
     Lobby
     Storage
     Dressing Rooms
     Mechanical Room
     Electrical Room
     Elevator
     Circulation, Exiting
     Loading Dock
Concert Hall Program
   Building Area of 10,000 sf
   Indoor Seating 300
   Amphitheater
          300 outdoor seats
       Stage 2,500 sf.
       Green Room 2,500 sf.
       Restrooms
       Lighting Booth
       Sound Booth
       Lobby
       Dressing Rooms
       Storage
       Mechanical Room
       Electrical Room
       Circulation, Exiting
       Loading Dock
Massing Studies
Acoustic and Structural Studies
Context and Planning
Design Approach
Idyllwild Performing Arts Center
Site Plan
Interiors




Philadelphia Theatre Company
Acoustical Design Parameters



                               The acoustic performance of an
                                  interior space is one of the most
                                  crucial and widely debated aspects
                                  of architectural design for the
                                  performing arts.
                                  William Weathersby, AR 05.99

                               Concert Hall Specifications
                                   Reverberation Time (RT60) at
                                     500 Hz is approximately 2.0
                                     seconds (Unoccupied) and 1.9
                                     Seconds (Occupied)
                                   Misc. Acoustic Parameters
                                        EDT, Clarity (C80), D50
                                   Noise Criteria (NC from HVAC)
                                     over the entire auditorium is
                                     below NC-15
Concert Hall
Theater
Sustainable Materials and Systems (USGBC)


   Low Emitting Materials
   Structural Insulated Panels
   High Performance Glazing
   Structural Wood (Glue Laminated Beams)
   High Efficiency Mechanical Systems
   Drought Tolerant Landscape
   Energy Efficient Lighting
   Water Efficient
   Solar Energy
Elevations
Floor Plans
Theater Roof Plan
Perspective Drawings
Idyllwild Performing Arts Center
Idyllwild Performing Arts Center
Idyllwild Performing Arts Center
Idyllwild Performing Arts Center
Construction Budget  Funds Allocation


Permits and Fees          $204,714
General Conditions        $241,000
Site Work               $1,946,000
Concrete                  $584,000
Metal                   $1,906,000
Wood                     2,240,000
Mechanical              $2,100,000
Electrical                $880,000
Systems                   $870,000
Interiors               $1,020,000
Total                  $11,991,714


Total Building Area         20,000 sf
Cost Per Square Foot         $600/sf



                        http://www.constructionphotographs.com/free-stock-photography-questions/index.asp#cost for details.
Design and Construction Timeline




Project Initiation          January 2009
Programming                 Jan 2009 (4 Weeks)
Conceptual Design           Feb 2009 (4 Weeks)
Schematic Design            May 2009 (20 Weeks)
Design Development          Dec 2009 (26 Weeks)
Construction Documents      Jun 2010 (26 Weeks)
Bidding                     Aug 2010 (8 Weeks)
Plan Check                  Sep 2010 (12 Weeks)
Construction Period         Feb 2012 (18 Months)
Project Delivery            March 2012




                         http://www.constructionphotographs.com/free-stock-photography-questions/index.asp#cost for details.
END
Idyllwild Performing Arts Center
Ad

Recommended

ENAC Powerp
ENAC Powerp
Kellekab
My Portfolio
My Portfolio
Perla Arquieta
Jill - Maglin PP 2012
Jill - Maglin PP 2012
jillroberts99
Maglin Overview
Maglin Overview
kbettridge
Sands Cotai Central
Sands Cotai Central
Walter Bone, RLA ASLA
COMPANY PROFILE
COMPANY PROFILE
Morgan Kisali
Bcil towns end dossier
Bcil towns end dossier
ZEDhabitats
Total Environment Company Profile
Total Environment Company Profile
Total Environment
Benefits of good design ct (22.02.12)
Benefits of good design ct (22.02.12)
OPUNArch
Design Portfolio
Design Portfolio
rdillon6
Naranjo portfolio 2010_
Naranjo portfolio 2010_
NaranjoT
M.Arch Thesis - Process Compilation
M.Arch Thesis - Process Compilation
mengelmn
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Morgan
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Galala University
James Learning Center | LEED-Gold
James Learning Center | LEED-Gold
matthewba
Joseph A. Schettino\s Portfolio
Joseph A. Schettino\s Portfolio
sublime1486
Architecture Portfolio 2013
Architecture Portfolio 2013
Devin Engle
GN02 ADM presentation
GN02 ADM presentation
michiefishie
Site Analysis
Site Analysis
Khaled Almusa
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
the Environment Centre (tEC)
The greener facility
The greener facility
Ian Garrett
Portfolio Krystal Kellermann
Portfolio Krystal Kellermann
Krystal_Kellermann
Export Final
Export Final
TICHINDER0905
Implication of Sustainable Development in Site Planning in Composite Climate ...
Implication of Sustainable Development in Site Planning in Composite Climate ...
IRJET Journal
Portfolio
Portfolio
JGT238
Susd0001 Nicolas Carbone Individual Assignment (2)
Susd0001 Nicolas Carbone Individual Assignment (2)
Nicolas Carbone Gamarra
Norman Glavas Architects Catalog
Norman Glavas Architects Catalog
nglavas
The Greening Curve
The Greening Curve
Sustainable Performance Institute

More Related Content

Similar to Idyllwild Performing Arts Center (20)

Benefits of good design ct (22.02.12)
Benefits of good design ct (22.02.12)
OPUNArch
Design Portfolio
Design Portfolio
rdillon6
Naranjo portfolio 2010_
Naranjo portfolio 2010_
NaranjoT
M.Arch Thesis - Process Compilation
M.Arch Thesis - Process Compilation
mengelmn
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Morgan
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Galala University
James Learning Center | LEED-Gold
James Learning Center | LEED-Gold
matthewba
Joseph A. Schettino\s Portfolio
Joseph A. Schettino\s Portfolio
sublime1486
Architecture Portfolio 2013
Architecture Portfolio 2013
Devin Engle
GN02 ADM presentation
GN02 ADM presentation
michiefishie
Site Analysis
Site Analysis
Khaled Almusa
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
the Environment Centre (tEC)
The greener facility
The greener facility
Ian Garrett
Portfolio Krystal Kellermann
Portfolio Krystal Kellermann
Krystal_Kellermann
Export Final
Export Final
TICHINDER0905
Implication of Sustainable Development in Site Planning in Composite Climate ...
Implication of Sustainable Development in Site Planning in Composite Climate ...
IRJET Journal
Portfolio
Portfolio
JGT238
Susd0001 Nicolas Carbone Individual Assignment (2)
Susd0001 Nicolas Carbone Individual Assignment (2)
Nicolas Carbone Gamarra
Norman Glavas Architects Catalog
Norman Glavas Architects Catalog
nglavas
The Greening Curve
The Greening Curve
Sustainable Performance Institute
Benefits of good design ct (22.02.12)
Benefits of good design ct (22.02.12)
OPUNArch
Design Portfolio
Design Portfolio
rdillon6
Naranjo portfolio 2010_
Naranjo portfolio 2010_
NaranjoT
M.Arch Thesis - Process Compilation
M.Arch Thesis - Process Compilation
mengelmn
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Lapthorn Construction green breakfast - 5th Studio presentation - 20 Ma...
Blake Morgan
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Integrating Sustainability油Strategies in Design and Practice - 悋惆悋悴 悋愕惠惘悋惠悴...
Galala University
James Learning Center | LEED-Gold
James Learning Center | LEED-Gold
matthewba
Joseph A. Schettino\s Portfolio
Joseph A. Schettino\s Portfolio
sublime1486
Architecture Portfolio 2013
Architecture Portfolio 2013
Devin Engle
GN02 ADM presentation
GN02 ADM presentation
michiefishie
Achieving good quality carbon reduction schemes through planning - Steve Char...
Achieving good quality carbon reduction schemes through planning - Steve Char...
the Environment Centre (tEC)
The greener facility
The greener facility
Ian Garrett
Portfolio Krystal Kellermann
Portfolio Krystal Kellermann
Krystal_Kellermann
Implication of Sustainable Development in Site Planning in Composite Climate ...
Implication of Sustainable Development in Site Planning in Composite Climate ...
IRJET Journal
Portfolio
Portfolio
JGT238
Susd0001 Nicolas Carbone Individual Assignment (2)
Susd0001 Nicolas Carbone Individual Assignment (2)
Nicolas Carbone Gamarra
Norman Glavas Architects Catalog
Norman Glavas Architects Catalog
nglavas

Idyllwild Performing Arts Center

  • 1. A Sustainable Systems Integration Approach to the Idyllwild Arts Academy Performing Arts Center (IPAC) Escalante Architects Ana Escalente, AIA Founder and Principal 121 South Palm Canyon Drive Palm Springs, CA 92262 760.323.1925 www.escalantearchitects.com December 2008
  • 2. Summary 1. What we are going to talk about. 2. What we are talking about. 3. What we just talked about.
  • 3. Project Team Design Architect: Escalante Architects Ana Escalante, AIA - Founding Principal Cliff Cortland Partner Ivan Ivanov Designer Stan - Designer Dicle Bath - Designer Ashi Martin - Designer Zach Morgan - Designer Matias Cena - Designer Executive Architects: HMC Planning: Green Design Build, Alex Meyerhoff Structural: J. A. Martin & Associates Mechanical, Plumbing, Electrical & Sustainability: IBE Consulting Engineers Civil Engineer: Sanborn A&E Acoustical Engineer: Nagata Engineering Landscape Architect: TKD & Associates Idyllwild Arts Academy , Idyllwild California
  • 4. Ana Bio SUSTAINABILITY & DESIGN PRINCIPLES Creating Community through Design Architecture is frozen music. - Goethe
  • 5. Setting: Idyllwild, California Setting Location: 33属4444N, 116属4258W Elevation 5,000 msl Ave. Temp.: 55.2 Ave. Min.: 39.7 Ave. Max.: 70.7 Annual Rainfall: 14.6 Snowfall: 39.3 Pop: 3,504 (2000)
  • 6. Challenge/Project Objective Create a viable educational laboratory, with a theater and concert hall, which establish the Idyllwild Arts Academy as the nations preeminent arts preparatory school; and Provide a creative environment in which the next generation of musical and dramatic practitioners can hone their craft, while also providing for a range of artistic experiences for diverse audiences within both the school and community at large.
  • 7. Concept: A Sustainable Approach to Design "Sustainability is an economic state where the demands placed upon the environment by people and commerce can be met without reducing the capacity of the environment to provide for future generations. Leave the world better than you found it Take no more than you need Try not to harm life or the environment Make amends if you do source: www.sustainability.ca
  • 8. A Green or Sustainable Approach to Design Team Philosophy: Functionality Devise an architectural program serving students and faculty as well as community members. Use high quality materials to enhance indoor & out-door experiences. Create a repertoire of public spaces. Reinforce pedestrian circulation. Maximize efficiency.
  • 9. Sustainable Design Creating Community Through Design Team Philosophy: Integrate Systems Utilize green or sustainable systems to meet program requirements. Balance project solutions into an integrated and seamless whole. Engineer solutions to specific site and climatic challenges. Enhance accessibility pursuant to the Americans with Disabilities Act Control variables to ensure success: schedule, budget and quality.
  • 10. Site Analysis and Environmental Assessment Climate Hazards Wildfire Drainage/Vegetation Topography (+ 7 feet) Vernacular Architecture Seismic Requirements Circulation, Access and Egress
  • 11. Sustainable System Integration Designed for Maximum Performance Integrated Wall and Roof Panel Structural Systems Mechanical Systems (HVAC, plumbing, electrical) Glazing Systems (High performance glass, and thermally broken frames) Acoustic Design Systems Renewable/Local Resources & Technology (Budget Driven) Cladding Sustainable Harvest Wood Energy Modeling Fluid Dynamics Analysis
  • 12. Preliminary Design Ideas (SWOT Analysis, We can rephrase this as a Strength, Weakness Opportunities and Threat Analysis) Framing Views Existing Campus Vernacular Sustainability and Systems Climatic Variation and Temperature Response to Climate Solar Orientation Building Mass Systems Integration Outdoor/Indoor Permeability Landscape Design Daylight and Night Skies Loading and Exiting Circulation Energy Conservation Prevailing Winds Topography Vegetation Fire Regime Ambient Noise Separation of Functions Acoustical Design Structural Integrity Educational Mission Community Resource Exterior Finishes and Cladding Creating Public Space and Seasonal Courtyards Rooted in Local Vernacular and Building Function Life Cycle Costs (Operations and Maintenance)
  • 13. Theatre Program Building Area 10,000 sf. Seating for 200 Stage 3,700 sf. Green Room 1,500 sf. Fly Tower 45 Proscenium 15 x 30 Thrust stage Restrooms Star Gazing Deck Lighting and Sound Booths Lobby Storage Dressing Rooms Mechanical Room Electrical Room Elevator Circulation, Exiting Loading Dock
  • 14. Concert Hall Program Building Area of 10,000 sf Indoor Seating 300 Amphitheater 300 outdoor seats Stage 2,500 sf. Green Room 2,500 sf. Restrooms Lighting Booth Sound Booth Lobby Dressing Rooms Storage Mechanical Room Electrical Room Circulation, Exiting Loading Dock
  • 22. Acoustical Design Parameters The acoustic performance of an interior space is one of the most crucial and widely debated aspects of architectural design for the performing arts. William Weathersby, AR 05.99 Concert Hall Specifications Reverberation Time (RT60) at 500 Hz is approximately 2.0 seconds (Unoccupied) and 1.9 Seconds (Occupied) Misc. Acoustic Parameters EDT, Clarity (C80), D50 Noise Criteria (NC from HVAC) over the entire auditorium is below NC-15
  • 25. Sustainable Materials and Systems (USGBC) Low Emitting Materials Structural Insulated Panels High Performance Glazing Structural Wood (Glue Laminated Beams) High Efficiency Mechanical Systems Drought Tolerant Landscape Energy Efficient Lighting Water Efficient Solar Energy
  • 34. Construction Budget Funds Allocation Permits and Fees $204,714 General Conditions $241,000 Site Work $1,946,000 Concrete $584,000 Metal $1,906,000 Wood 2,240,000 Mechanical $2,100,000 Electrical $880,000 Systems $870,000 Interiors $1,020,000 Total $11,991,714 Total Building Area 20,000 sf Cost Per Square Foot $600/sf http://www.constructionphotographs.com/free-stock-photography-questions/index.asp#cost for details.
  • 35. Design and Construction Timeline Project Initiation January 2009 Programming Jan 2009 (4 Weeks) Conceptual Design Feb 2009 (4 Weeks) Schematic Design May 2009 (20 Weeks) Design Development Dec 2009 (26 Weeks) Construction Documents Jun 2010 (26 Weeks) Bidding Aug 2010 (8 Weeks) Plan Check Sep 2010 (12 Weeks) Construction Period Feb 2012 (18 Months) Project Delivery March 2012 http://www.constructionphotographs.com/free-stock-photography-questions/index.asp#cost for details.