際際滷

際際滷Share a Scribd company logo
Unit no.3
Programme Evaluation & Review
Technique
(P.E.R.T)
Mr. Kiran R. Patil
Assistant Professor,
Department of Civil Engineering,
D. Y. Patil College of Engineering & Technology, Kolhapur
 Introduction to PERT
 PERT was developed by U.S. Navy engineers while working on the Polaris Missile
Programme during 1957-58.
 PERT is used for planning and controlling the projects involving uncertainties. This
technique is usually used for non-repetitive project such as launching of satellites, research
and development (R & D) projects, etc. in which correct time estimation for various
activities cannot be made due to lack of past data.
 PERT is an event-oriented technique. This technique uses a network diagram consisting of
events which must be established to reach project objectives.
 More stress is given on time in this technique. The uncertainty in activity times is
measured by using the following three time estimates,
1. The optimistic time estimate
2. The pessimistic time estimate
3. The most likely time estimate
 For computation of critical path, the three-time are converted into a single-time in
network. This single time is called the expected time.
1. The Optimistic time estimate (tO):-
This is the shortest possible time in which an activity can be completed under ideal
conditions. It is possible when all the conditions are favor of project.
2. The Pessimistic time estimate (tP)
This is the maximum time that would be required to complete the activity. It represents
the time it might take to complete a particular activity if everything went wrong
about of project.
3. The Most likely time estimate (tL)
 It is the normal time required to complete an activity. It is in between the position
of optimistic & pessimistic time.
tO + 4tL + tP
 Expected Time, tE =
6
 Comparison between C.P.M. and P.E.R.T.
Sr.No. C.P.M P.E.R.T.
1 CPM is Critical Path Method PERT is Programme Evaluation and Review
Technique
2 CPM is used for repetitive type of projects
where accurate time estimates can be made
and costs can be calculated in advance.
e.g. construction projects
PERT is used for non-repetitive types of projects
where accurate time estimates cannot be calculated
in advance.
e.g. Research and Development projects,
Launching of missile or satellite.
3 In CPM, cost optimization is given prime
importance. The time duration for completion
depends on this cost optimization. The cost is
not directly proportional to time.
i.e. cost is the direct controlling factor.
In PERT, it is assumed that the cost varies directly
with time. Therefore, time minimization is given
more attention.
i.e. time is the controlling factor.
4 CPM uses activity-oriented network diagram.
i.e. importance is given on activities
PERT uses event-oriented network diagram.
i.e. importance is given on events
5 In CPM, critical path is the one which passes
through critical activities.
In PERT, critical path is the one which passes
through critical events.
6 In CPM, the critical path is determined by
activity-oriented float.
In PERT, the critical path is determined by event-
oriented slack.
 Frequency Distribution
 The most likely time (tL) can also be found out by using frequency distribution curve.
 The curve is symmetrical about its apex. Such a curve is known as Normal Distribution
Curve.
 The statistical data for varying time durations for the jobs of particular type consumed in
the past can be expressed in the form of a frequency distribution curve.
 The probability curve which is not symmetrical about its apex is known as Beta
Distribution Curve.
 The beta distribution is used in PERT because it satisfies the following requirements,
1. The distribution should have a small probability of reaching the optimistic time (shortest
time).
2. The distribution should have a small probability of reaching the pessimistic time (longest
time)
3. The distribution should have only one most likely time which would be free to move
between the two limits of to and tp.
 For beta distribution, the standard deviation is given by,
  =
$$
6
 The variance 2 =
$$
6
2
 Ex. 1
 On a construction project, the times required for digging 54 trenches of fixed dimensions
are recorded below. The trenches were excavated by different gangs, each consisting of the
same number of labours. Plot the frequency distribution curve.
Times of completion of trenches (days)
8 10 12 6 9 11 10 13 15 12
11 9 8 10 14 16 12 16 15 10
14 12 7 9 13 10 8 11 17 13
9 11 13 10 14 9 12 15 14 9
10 9 11 10 7 13 11 8 12 11
8 10 9 11
Solution:
 From the above record, we find that the minimum time taken for completion of
trenches is 6 days, which is the optimistic time (tO). The maximum time is 17 days
which is the pessimistic time (tP).
 The following table gives the number of trenches completed in 6, 7, 8, 9, 10, 11, 12,
13, 14, 15, 16 and 17 days respectively.
Days of
completion
No. of trenches
completed during
these days
Days of
completion
No. of trenches
completed during
these days
6 1 12 6
7 2 13 5
8 5 14 4
9 8 15 3
10 9 16 2
11 8 17 1
Program Evaluation & Review Technique for Civil Engineering
 P.E.R.T.: Network Analysis
 Slack:
 Slack means time to spare
 It is the difference between the latest allowable occurrence time and the earliest expected
time of an event
 S = TL  TE
 Slack can be +ve, zero or ve
1. Positive Slack: when TL > TE
It is an indication of an ahead of schedule situation (excess resources)
2. Zero Slack: when TL = TE
It is an indication of on schedule situation (adequate resources)
3. Negative Slack: when TL < TE
It is an indication of a behind schedule situation (lack of resources)
 Critical Path:
 It is the one which consumes maximum time. It is time wise longest path.
 It is time wise longest path who connects the events of zero slack.
 The network for a project is shown below. Determine the expected time for each path.
Which path is critical?
Solution: There are 4 paths
1. Path A: 1-2-7-8
2. Path B: 1-2-6-8
3. Path C: 1-3-6-8
4. Path D: 1-4-5-6-8
 Expected time tE = tO + 4tL + tP
6
Path Activity tO tL tP tE = tE
A
1-2 6 8 11 8.17
26.34
2-7 8 10 12 10.00
7-8 5 8 12 8.17
B
1-2 6 8 11 8.17
26.83
2-6 4 8 14 8.33
6-8 7 10 15 10.33
C
1-3 3 7 9 6.67
27.00
3-6 8 10 12 10.00
6-8 7 10 15 10.33
D
1-4 5 7 10 7.17
28.33
4-5 4 6 8 6.00
5-6 3 5 6 4.83
6-8 7 10 15 10.33
Path D is critical since= tE for this path is maximum.= 28.33
 Finding the probability of meeting the scheduled time of completion of a
project
 Determine the standard deviation () appropriate to the critical path.
  =      
  = 
Where, 2 = variance for the activity i-j along the critical path
 =



 Find probability factor Z.
 =
諮諮

=
諮諮

Where, Ts = scheduled time of completion
TE = earliest expected time of completion
 Z can be +ve, 0 or ve.
1. When Z is +ve, the chances of completing the project in scheduled time are
more than 50 %.
2. When Z is 0, the chances of completing the project in scheduled time are fifty-
fifty.
3. When Z is - ve, the chances of completing the project in scheduled time are
less than 50 %.
 Find % probability with respect to the normal deviation Z from the table.
Values of Standard Normal Distribution Function
Problem 1. A project is expected to take 15 months along the critical path, having a
standard deviation of 3 months. What is the probability of completing the project within
(i) 15 months, (ii) 18 months, (iii) 12 months?
 Solution:
 Given Data: TE= 15 months ,  = 3 months
 Probability Factor  =


1) Ts = 15 months;
 =
15  15
3
= 0
 For Z = 0, Probability = 50 % (from the Table)
2) Ts = 18 months;
 =
18  15
3
= 1
For Z = 1, Probability = 84.13 % (from the Table)
3) Ts = 12 months;
 =
12  15
3
= 1
 For Z = -1, Probability = 15.87 % (from the Table)
Problem 2. With the information given in the table draw the network for a construction
project. Determine,
1. Critical path and its standard deviation
2. Probability of completion of project in 40 days.
3. Time duration that will provide 95 % probability of its completion in time.
 Solution:
1. Calculate expected time for each activity,
Activity Optimistic time Most likely time Pessimistic time
1-2 2 5 8
2-3 8 11 20
3-4 0 0 0
2-4 4 7 16
2-5 4 9 20
4-6 7 10 13
5-6 3 7 17
3-7 3 5 13
6-7 2 3 10
7-8 2 4 6
Activity Optimistic
time
tO
Most likely
time
tL
Pessimistic time
tP
Expected Time
tE = tO + 4tL + tP
6
2
=
$  $
6
2
1-2 2 5 8 5 1
2-3 8 11 20 12 4
3-4 0 0 0 0 0
2-4 4 7 16 8 4
2-5 4 9 20 10 7.11
4-6 7 10 13 10 1
5-6 3 7 17 8 5.44
3-7 3 5 13 6 2.78
6-7 2 3 10 4 1.77
7-8 2 4 6 4 0.44
2. Draw the Network with expected time
Critical path: 1-2-3-4-6-7-8
Project duration = 35 days
1. Standard deviation along critical path =  = 2
2
= 1 + 4 + 0 + 1 + 1.77 + 0.44 = 8.2
 = 8.21 = 2.87
 Probability Factor Z= (Ts-TE)/
2. Here, Ts = 40 days and  = 2.87 months
 Z= (40-35)/2.87=1.74
 From the table,
 For Z = 1.7, Pr = 95.54 %, For Z = 1.8, Pr = 96.41 %
 For Z = 1.74, Pr = ?
1.7 = 95.54
1.8 = 96.41
0.1 = 0.87
 0.04 =
0.04  0.87
0.1
= 0.35
 For Z = 1.74, Pr = 95.54 + 0.35 = 95.89 %
3. For Pr = 95 %, Ts =?
 For 95.54 = 1.7
 For 94.52 = 1.6
 For 95, Z=?
Pro. 95.54-94.52= 1.02
Z 1.7-1.6=0.1
(0.54x1.02)/0.1= 0.05
Z = 1.6 + 0.05 = 1.65
  =


 Ts = (  Z) + TE
 = (2.87 x 1.65) + 35
 = 39.7
Ts = 40 days
Problem 3. For the information given in the table determine the critical path and standard
deviation for the network. Determine the probability of completing the project in 35 days.
 ( For Z = 0.9, Pr = 81.59 %. For Z = 1.0, Pr = 84.13 % and For Z = 1.1, Pr = 86.43 %)
Activity Optimistic time
tO
Most likely time
tL
Pessimistic time
tP
1-2 6 9 18
1-3 5 8 17
2-4 4 7 22
3-4 4 7 16
4-5 4 10 22
2-5 4 7 10
3-5 2 5 8
 Solution:
1. Draw the Network
2. Find expected time & Variance
Activity Optimistic
time
tO
Most likely
time
tL
Pessimistic
time
tP
Expected Time
tE = tO + 4tL + tP
6
2
=
$  $
6
2
1-2 6 9 18 10 4
1-3 5 8 17 9 4
2-4 4 7 22 9 9
3-4 4 7 16 8 4
4-5 4 10 22 11 9
2-5 4 7 10 7 1
3-5 2 5 8 5 1
 Standard deviation along critical path =  = 2
 2
= 4 + 9 + 9 = 22
  = 22 = 4.69
 Here, Ts = 35 days and  = 4.69
 Probability Factor  =


  =
3530
4.69
= 1.07
 From the table,
 For Z = 1.0, Pr = 84.13 %
 For Z = 1.1, Pr = 86.43%
 For Z= 1.07, Pr= ?
 0.07= 2.3
 (0.07x 2.3)/0.1= 1.61
 For Z = 1.07, Pr = 84.13 + 1.61 = 85.74 %
Problem 4. For the information given in the table determine the critical path and standard
deviation for the network. Determine the probability of completing the project in 50 days.
( For Z = 0.7, Pr = 75.80 %. For Z = 0.8, Pr = 78.81% and For Z = 0.6, Pr = 72.57 %)
1. Find Expected time and variance
Activity Optimistic time
tO
Most likely time
tL
Pessimistic time
tP
1-2 4 8 18
1-3 4 5 18
2-4 3 7 23
2-5 1 11 33
3-4 6 6 18
3-5 3 9 21
4-5 7 12 35
5-6 9 8 31
Activity Optimistic time
tO
Most likely time
tL
Pessimistic time
tP
Expected Time
TE = tO + 4tL + tP
6
2
=
$  $
6
2
1-2 4 8 18 9 5.44
1-3 4 5 18 7 5.44
2-4 3 7 23 9 11.11
2-5 1 11 33 13 28.44
3-4 6 6 18 8 4
3-5 3 9 21 10 9
4-5 7 12 35 15 21.77
5-6 9 8 31 12 13.44
2. Draw network & find expected time
1
2
3
4
5 6
9
7
9
8
13
10
15
12
0
9
7
18
33 45
45
33
18
10
9
0
 Critical Path 1-2-4-5-6
 Project Duration = TE= 45 days
 Standard deviation along critical path =  = 2
2
= 5.44+11.11+21.77+13.44 = 51.76
 = 51.76 = 7.19
 Probability of project completed in 50 days = Ts
 =
  

 =
5045
7.19
=0.69
 From table
Z= 0.6, Pr.= 72.57 Z= 0.7, Pr.= 75.80
0.6 72.57
0.7 75.80
0.1 3.23
0.09 x
0.1x= 0.09 X 3.23
x= 2.097
 Probability of completing project within 50days= 72.57+2.907= 75.48%
 Precedence Networks :
 In CPM or PERT networks, activities are connected according to the finish-to-start logic,
i.e. an activity starts only after its preceding activity is completed. But in reality, there will
be a certain overlapping of time in between the adjoining activities.
 e.g. In a multi-housing construction project, the CPM network may show the activity of
wall plastering as starting after the completion of masonry work of a particular building.
In practice, however, plastering can start as soon as the first room is complete. It need not
wait for completion of masonry work of all the rooms.
 The precedence network technique keeps the number of activities same as CPM networks
(A-O-A networks) but eliminates the dummies. In the precedence networks nodes
represent the activities and lines represent their interdependencies or precedence
relationships.
 Representation of nodes in Precedence Networks:
Description Code
EST Dur. EFT
LST No. LFT
Steel Fabrication
C
0 5 5
0 3 5
Rebar Transport
D
5 1 6
5 4 6
Rebar Fixing
E
6 3 9
6 5 9
 Logic of Precedence Diagram
1. Finish to Start
Activity B cannot start until activity A has been completed.
2. Start to Start
Activity B can start at the same time A but not before.
3. Finish to Finish
Activity B cannot be finished until activity A has been finished.
4 Start to start & Finish to Finish:
A B
Time lag
A
B
A
B
A
B
Time lag
Time lag
Time lag
Time lag
 Activity B cannot be started and cannot be finished earlier than the stated time lag after the
start and finish of activity A. This sequence is used to define overlapping independent
activities.
 Advantages of Precedence Networks:
 Precedence network can show activities which should be allowed to overlap each other or
must be separated by a time delay.
 Precedence network is self sufficient as it contains the necessary information regarding the
project. Time analysis results are incorporated in the drawing itself. This facilitates efficient
project scheduling and control.
 Revisions and modifications can be carried out easily without affecting most of the
activities
 No arrow is required to show the logical sequence of activities. From the drawings, it is
clear that all activities on the left precede those on the right.
 Precedence network adopts simple notations similar to flow charts and can be easily
understood by any person.

More Related Content

More from D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India (20)

Plastering and plastering methods used in Construction
Plastering and plastering methods used in ConstructionPlastering and plastering methods used in Construction
Plastering and plastering methods used in Construction
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Painting and types of paints used in Construction
Painting and types of paints used in ConstructionPainting and types of paints used in Construction
Painting and types of paints used in Construction
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Floor and its types used in construction
Floor and its types used in constructionFloor and its types used in construction
Floor and its types used in construction
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Unit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdfUnit 6 A Construction Equipments for civil engineering.pdf
Unit 6 A Construction Equipments for civil engineering.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Advance management for civil engineering
Advance management for civil engineeringAdvance management for civil engineering
Advance management for civil engineering
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Construction Equipment used in construction projects
Construction Equipment used in construction projectsConstruction Equipment used in construction projects
Construction Equipment used in construction projects
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Special Concrete.pdf
Special Concrete.pdfSpecial Concrete.pdf
Special Concrete.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Hardened Concrete.pdf
Hardened Concrete.pdfHardened Concrete.pdf
Hardened Concrete.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Concrete Mix Design.pdf
Concrete Mix Design.pdfConcrete Mix Design.pdf
Concrete Mix Design.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Fresh Concrete.pdf
Fresh Concrete.pdfFresh Concrete.pdf
Fresh Concrete.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Introduction of Concrete.pdf
Introduction of Concrete.pdfIntroduction of Concrete.pdf
Introduction of Concrete.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Aggregate.pdf
Aggregate.pdfAggregate.pdf
Aggregate.pdf
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Building construction materials -Tiles
Building construction materials -TilesBuilding construction materials -Tiles
Building construction materials -Tiles
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Building construction materials -Steel
Building construction materials -SteelBuilding construction materials -Steel
Building construction materials -Steel
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India
Building construction materials - brick
Building construction materials  - brick Building construction materials  - brick
Building construction materials - brick
D. Y. Patil College of Engineering & Technology, Kolhapur, Maharastra, India

Recently uploaded (20)

Piping-and-pipeline-calculations-manual.pdf
Piping-and-pipeline-calculations-manual.pdfPiping-and-pipeline-calculations-manual.pdf
Piping-and-pipeline-calculations-manual.pdf
OMI0721
Multi objective genetic approach with Ranking
Multi objective genetic approach with RankingMulti objective genetic approach with Ranking
Multi objective genetic approach with Ranking
namisha18
TM-ASP-101-RF_Air Press manual crimping machine.pdf
TM-ASP-101-RF_Air Press manual crimping machine.pdfTM-ASP-101-RF_Air Press manual crimping machine.pdf
TM-ASP-101-RF_Air Press manual crimping machine.pdf
ChungLe60
Indian Soil Classification System in Geotechnical Engineering
Indian Soil Classification System in Geotechnical EngineeringIndian Soil Classification System in Geotechnical Engineering
Indian Soil Classification System in Geotechnical Engineering
Rajani Vyawahare
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
ASHISHDESAI85
Engineering at Lovely Professional University (LPU).pdf
Engineering at Lovely Professional University (LPU).pdfEngineering at Lovely Professional University (LPU).pdf
Engineering at Lovely Professional University (LPU).pdf
Sona
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVName.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
MerijimArsedelPalmad1
Taykon-Kalite belgeleri
Taykon-Kalite belgeleriTaykon-Kalite belgeleri
Taykon-Kalite belgeleri
TAYKON
Mathematics_behind_machine_learning_INT255.pptx
Mathematics_behind_machine_learning_INT255.pptxMathematics_behind_machine_learning_INT255.pptx
Mathematics_behind_machine_learning_INT255.pptx
ppkmurthy2006
Equipment for Gas Metal Arc Welding Process
Equipment for Gas Metal Arc Welding ProcessEquipment for Gas Metal Arc Welding Process
Equipment for Gas Metal Arc Welding Process
AhmadKamil87
Embedded System intro Embedded System intro.ppt
Embedded System intro Embedded System intro.pptEmbedded System intro Embedded System intro.ppt
Embedded System intro Embedded System intro.ppt
23ucc580
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
J. Agricultural Machinery
04 MAINTENANCE OF CONCRETE PAVEMENTS.ppt
04  MAINTENANCE OF CONCRETE PAVEMENTS.ppt04  MAINTENANCE OF CONCRETE PAVEMENTS.ppt
04 MAINTENANCE OF CONCRETE PAVEMENTS.ppt
sreenath seenu
only history of java.pptx real bihind the name java
only history of java.pptx real bihind the name javaonly history of java.pptx real bihind the name java
only history of java.pptx real bihind the name java
mushtaqsaliq9
decarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptxdecarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptx
gonzalezolabarriaped
decarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptxdecarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptx
gonzalezolabarriaped
CFOT Fiber Optics FOA CERTIFICATION.pptx
CFOT Fiber Optics FOA CERTIFICATION.pptxCFOT Fiber Optics FOA CERTIFICATION.pptx
CFOT Fiber Optics FOA CERTIFICATION.pptx
MohamedShabana37
Frankfurt University of Applied Science urkunde
Frankfurt University of Applied Science urkundeFrankfurt University of Applied Science urkunde
Frankfurt University of Applied Science urkunde
Lisa Emerson
How to Build a Maze Solving Robot Using Arduino
How to Build a Maze Solving Robot Using ArduinoHow to Build a Maze Solving Robot Using Arduino
How to Build a Maze Solving Robot Using Arduino
CircuitDigest
GREEN BULIDING PPT FOR THE REFRENACE.PPT
GREEN BULIDING PPT FOR THE REFRENACE.PPTGREEN BULIDING PPT FOR THE REFRENACE.PPT
GREEN BULIDING PPT FOR THE REFRENACE.PPT
kamalkeerthan61
Piping-and-pipeline-calculations-manual.pdf
Piping-and-pipeline-calculations-manual.pdfPiping-and-pipeline-calculations-manual.pdf
Piping-and-pipeline-calculations-manual.pdf
OMI0721
Multi objective genetic approach with Ranking
Multi objective genetic approach with RankingMulti objective genetic approach with Ranking
Multi objective genetic approach with Ranking
namisha18
TM-ASP-101-RF_Air Press manual crimping machine.pdf
TM-ASP-101-RF_Air Press manual crimping machine.pdfTM-ASP-101-RF_Air Press manual crimping machine.pdf
TM-ASP-101-RF_Air Press manual crimping machine.pdf
ChungLe60
Indian Soil Classification System in Geotechnical Engineering
Indian Soil Classification System in Geotechnical EngineeringIndian Soil Classification System in Geotechnical Engineering
Indian Soil Classification System in Geotechnical Engineering
Rajani Vyawahare
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
Integration of Additive Manufacturing (AM) with IoT : A Smart Manufacturing A...
ASHISHDESAI85
Engineering at Lovely Professional University (LPU).pdf
Engineering at Lovely Professional University (LPU).pdfEngineering at Lovely Professional University (LPU).pdf
Engineering at Lovely Professional University (LPU).pdf
Sona
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVName.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
Name.docxVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVVV
MerijimArsedelPalmad1
Taykon-Kalite belgeleri
Taykon-Kalite belgeleriTaykon-Kalite belgeleri
Taykon-Kalite belgeleri
TAYKON
Mathematics_behind_machine_learning_INT255.pptx
Mathematics_behind_machine_learning_INT255.pptxMathematics_behind_machine_learning_INT255.pptx
Mathematics_behind_machine_learning_INT255.pptx
ppkmurthy2006
Equipment for Gas Metal Arc Welding Process
Equipment for Gas Metal Arc Welding ProcessEquipment for Gas Metal Arc Welding Process
Equipment for Gas Metal Arc Welding Process
AhmadKamil87
Embedded System intro Embedded System intro.ppt
Embedded System intro Embedded System intro.pptEmbedded System intro Embedded System intro.ppt
Embedded System intro Embedded System intro.ppt
23ucc580
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
Optimization of Cumulative Energy, Exergy Consumption and Environmental Life ...
J. Agricultural Machinery
04 MAINTENANCE OF CONCRETE PAVEMENTS.ppt
04  MAINTENANCE OF CONCRETE PAVEMENTS.ppt04  MAINTENANCE OF CONCRETE PAVEMENTS.ppt
04 MAINTENANCE OF CONCRETE PAVEMENTS.ppt
sreenath seenu
only history of java.pptx real bihind the name java
only history of java.pptx real bihind the name javaonly history of java.pptx real bihind the name java
only history of java.pptx real bihind the name java
mushtaqsaliq9
decarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptxdecarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptx
gonzalezolabarriaped
decarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptxdecarbonization steel industry rev1.pptx
decarbonization steel industry rev1.pptx
gonzalezolabarriaped
CFOT Fiber Optics FOA CERTIFICATION.pptx
CFOT Fiber Optics FOA CERTIFICATION.pptxCFOT Fiber Optics FOA CERTIFICATION.pptx
CFOT Fiber Optics FOA CERTIFICATION.pptx
MohamedShabana37
Frankfurt University of Applied Science urkunde
Frankfurt University of Applied Science urkundeFrankfurt University of Applied Science urkunde
Frankfurt University of Applied Science urkunde
Lisa Emerson
How to Build a Maze Solving Robot Using Arduino
How to Build a Maze Solving Robot Using ArduinoHow to Build a Maze Solving Robot Using Arduino
How to Build a Maze Solving Robot Using Arduino
CircuitDigest
GREEN BULIDING PPT FOR THE REFRENACE.PPT
GREEN BULIDING PPT FOR THE REFRENACE.PPTGREEN BULIDING PPT FOR THE REFRENACE.PPT
GREEN BULIDING PPT FOR THE REFRENACE.PPT
kamalkeerthan61

Program Evaluation & Review Technique for Civil Engineering

  • 1. Unit no.3 Programme Evaluation & Review Technique (P.E.R.T) Mr. Kiran R. Patil Assistant Professor, Department of Civil Engineering, D. Y. Patil College of Engineering & Technology, Kolhapur
  • 2. Introduction to PERT PERT was developed by U.S. Navy engineers while working on the Polaris Missile Programme during 1957-58. PERT is used for planning and controlling the projects involving uncertainties. This technique is usually used for non-repetitive project such as launching of satellites, research and development (R & D) projects, etc. in which correct time estimation for various activities cannot be made due to lack of past data. PERT is an event-oriented technique. This technique uses a network diagram consisting of events which must be established to reach project objectives. More stress is given on time in this technique. The uncertainty in activity times is measured by using the following three time estimates, 1. The optimistic time estimate 2. The pessimistic time estimate 3. The most likely time estimate For computation of critical path, the three-time are converted into a single-time in network. This single time is called the expected time. 1. The Optimistic time estimate (tO):- This is the shortest possible time in which an activity can be completed under ideal conditions. It is possible when all the conditions are favor of project. 2. The Pessimistic time estimate (tP) This is the maximum time that would be required to complete the activity. It represents
  • 3. the time it might take to complete a particular activity if everything went wrong about of project. 3. The Most likely time estimate (tL) It is the normal time required to complete an activity. It is in between the position of optimistic & pessimistic time. tO + 4tL + tP Expected Time, tE = 6
  • 4. Comparison between C.P.M. and P.E.R.T. Sr.No. C.P.M P.E.R.T. 1 CPM is Critical Path Method PERT is Programme Evaluation and Review Technique 2 CPM is used for repetitive type of projects where accurate time estimates can be made and costs can be calculated in advance. e.g. construction projects PERT is used for non-repetitive types of projects where accurate time estimates cannot be calculated in advance. e.g. Research and Development projects, Launching of missile or satellite. 3 In CPM, cost optimization is given prime importance. The time duration for completion depends on this cost optimization. The cost is not directly proportional to time. i.e. cost is the direct controlling factor. In PERT, it is assumed that the cost varies directly with time. Therefore, time minimization is given more attention. i.e. time is the controlling factor. 4 CPM uses activity-oriented network diagram. i.e. importance is given on activities PERT uses event-oriented network diagram. i.e. importance is given on events 5 In CPM, critical path is the one which passes through critical activities. In PERT, critical path is the one which passes through critical events. 6 In CPM, the critical path is determined by activity-oriented float. In PERT, the critical path is determined by event- oriented slack.
  • 5. Frequency Distribution The most likely time (tL) can also be found out by using frequency distribution curve. The curve is symmetrical about its apex. Such a curve is known as Normal Distribution Curve. The statistical data for varying time durations for the jobs of particular type consumed in the past can be expressed in the form of a frequency distribution curve. The probability curve which is not symmetrical about its apex is known as Beta Distribution Curve.
  • 6. The beta distribution is used in PERT because it satisfies the following requirements, 1. The distribution should have a small probability of reaching the optimistic time (shortest time). 2. The distribution should have a small probability of reaching the pessimistic time (longest time) 3. The distribution should have only one most likely time which would be free to move between the two limits of to and tp. For beta distribution, the standard deviation is given by, = $$ 6 The variance 2 = $$ 6 2 Ex. 1 On a construction project, the times required for digging 54 trenches of fixed dimensions are recorded below. The trenches were excavated by different gangs, each consisting of the same number of labours. Plot the frequency distribution curve. Times of completion of trenches (days) 8 10 12 6 9 11 10 13 15 12 11 9 8 10 14 16 12 16 15 10 14 12 7 9 13 10 8 11 17 13 9 11 13 10 14 9 12 15 14 9 10 9 11 10 7 13 11 8 12 11 8 10 9 11
  • 7. Solution: From the above record, we find that the minimum time taken for completion of trenches is 6 days, which is the optimistic time (tO). The maximum time is 17 days which is the pessimistic time (tP). The following table gives the number of trenches completed in 6, 7, 8, 9, 10, 11, 12, 13, 14, 15, 16 and 17 days respectively. Days of completion No. of trenches completed during these days Days of completion No. of trenches completed during these days 6 1 12 6 7 2 13 5 8 5 14 4 9 8 15 3 10 9 16 2 11 8 17 1
  • 9. P.E.R.T.: Network Analysis Slack: Slack means time to spare It is the difference between the latest allowable occurrence time and the earliest expected time of an event S = TL TE Slack can be +ve, zero or ve 1. Positive Slack: when TL > TE It is an indication of an ahead of schedule situation (excess resources) 2. Zero Slack: when TL = TE It is an indication of on schedule situation (adequate resources) 3. Negative Slack: when TL < TE It is an indication of a behind schedule situation (lack of resources) Critical Path: It is the one which consumes maximum time. It is time wise longest path. It is time wise longest path who connects the events of zero slack.
  • 10. The network for a project is shown below. Determine the expected time for each path. Which path is critical? Solution: There are 4 paths 1. Path A: 1-2-7-8 2. Path B: 1-2-6-8 3. Path C: 1-3-6-8 4. Path D: 1-4-5-6-8 Expected time tE = tO + 4tL + tP 6
  • 11. Path Activity tO tL tP tE = tE A 1-2 6 8 11 8.17 26.34 2-7 8 10 12 10.00 7-8 5 8 12 8.17 B 1-2 6 8 11 8.17 26.83 2-6 4 8 14 8.33 6-8 7 10 15 10.33 C 1-3 3 7 9 6.67 27.00 3-6 8 10 12 10.00 6-8 7 10 15 10.33 D 1-4 5 7 10 7.17 28.33 4-5 4 6 8 6.00 5-6 3 5 6 4.83 6-8 7 10 15 10.33 Path D is critical since= tE for this path is maximum.= 28.33
  • 12. Finding the probability of meeting the scheduled time of completion of a project Determine the standard deviation () appropriate to the critical path. = = Where, 2 = variance for the activity i-j along the critical path = Find probability factor Z. = 諮諮 = 諮諮 Where, Ts = scheduled time of completion TE = earliest expected time of completion Z can be +ve, 0 or ve. 1. When Z is +ve, the chances of completing the project in scheduled time are more than 50 %. 2. When Z is 0, the chances of completing the project in scheduled time are fifty- fifty. 3. When Z is - ve, the chances of completing the project in scheduled time are less than 50 %. Find % probability with respect to the normal deviation Z from the table.
  • 13. Values of Standard Normal Distribution Function
  • 14. Problem 1. A project is expected to take 15 months along the critical path, having a standard deviation of 3 months. What is the probability of completing the project within (i) 15 months, (ii) 18 months, (iii) 12 months? Solution: Given Data: TE= 15 months , = 3 months Probability Factor = 1) Ts = 15 months; = 15 15 3 = 0 For Z = 0, Probability = 50 % (from the Table) 2) Ts = 18 months; = 18 15 3 = 1 For Z = 1, Probability = 84.13 % (from the Table) 3) Ts = 12 months; = 12 15 3 = 1 For Z = -1, Probability = 15.87 % (from the Table)
  • 15. Problem 2. With the information given in the table draw the network for a construction project. Determine, 1. Critical path and its standard deviation 2. Probability of completion of project in 40 days. 3. Time duration that will provide 95 % probability of its completion in time. Solution: 1. Calculate expected time for each activity, Activity Optimistic time Most likely time Pessimistic time 1-2 2 5 8 2-3 8 11 20 3-4 0 0 0 2-4 4 7 16 2-5 4 9 20 4-6 7 10 13 5-6 3 7 17 3-7 3 5 13 6-7 2 3 10 7-8 2 4 6
  • 16. Activity Optimistic time tO Most likely time tL Pessimistic time tP Expected Time tE = tO + 4tL + tP 6 2 = $ $ 6 2 1-2 2 5 8 5 1 2-3 8 11 20 12 4 3-4 0 0 0 0 0 2-4 4 7 16 8 4 2-5 4 9 20 10 7.11 4-6 7 10 13 10 1 5-6 3 7 17 8 5.44 3-7 3 5 13 6 2.78 6-7 2 3 10 4 1.77 7-8 2 4 6 4 0.44 2. Draw the Network with expected time Critical path: 1-2-3-4-6-7-8 Project duration = 35 days
  • 17. 1. Standard deviation along critical path = = 2 2 = 1 + 4 + 0 + 1 + 1.77 + 0.44 = 8.2 = 8.21 = 2.87 Probability Factor Z= (Ts-TE)/ 2. Here, Ts = 40 days and = 2.87 months Z= (40-35)/2.87=1.74 From the table, For Z = 1.7, Pr = 95.54 %, For Z = 1.8, Pr = 96.41 % For Z = 1.74, Pr = ? 1.7 = 95.54 1.8 = 96.41 0.1 = 0.87 0.04 = 0.04 0.87 0.1 = 0.35 For Z = 1.74, Pr = 95.54 + 0.35 = 95.89 % 3. For Pr = 95 %, Ts =? For 95.54 = 1.7 For 94.52 = 1.6 For 95, Z=? Pro. 95.54-94.52= 1.02 Z 1.7-1.6=0.1 (0.54x1.02)/0.1= 0.05 Z = 1.6 + 0.05 = 1.65
  • 18. = Ts = ( Z) + TE = (2.87 x 1.65) + 35 = 39.7 Ts = 40 days Problem 3. For the information given in the table determine the critical path and standard deviation for the network. Determine the probability of completing the project in 35 days. ( For Z = 0.9, Pr = 81.59 %. For Z = 1.0, Pr = 84.13 % and For Z = 1.1, Pr = 86.43 %) Activity Optimistic time tO Most likely time tL Pessimistic time tP 1-2 6 9 18 1-3 5 8 17 2-4 4 7 22 3-4 4 7 16 4-5 4 10 22 2-5 4 7 10 3-5 2 5 8
  • 19. Solution: 1. Draw the Network 2. Find expected time & Variance Activity Optimistic time tO Most likely time tL Pessimistic time tP Expected Time tE = tO + 4tL + tP 6 2 = $ $ 6 2 1-2 6 9 18 10 4 1-3 5 8 17 9 4 2-4 4 7 22 9 9 3-4 4 7 16 8 4 4-5 4 10 22 11 9 2-5 4 7 10 7 1 3-5 2 5 8 5 1
  • 20. Standard deviation along critical path = = 2 2 = 4 + 9 + 9 = 22 = 22 = 4.69 Here, Ts = 35 days and = 4.69 Probability Factor = = 3530 4.69 = 1.07 From the table, For Z = 1.0, Pr = 84.13 % For Z = 1.1, Pr = 86.43% For Z= 1.07, Pr= ? 0.07= 2.3 (0.07x 2.3)/0.1= 1.61 For Z = 1.07, Pr = 84.13 + 1.61 = 85.74 %
  • 21. Problem 4. For the information given in the table determine the critical path and standard deviation for the network. Determine the probability of completing the project in 50 days. ( For Z = 0.7, Pr = 75.80 %. For Z = 0.8, Pr = 78.81% and For Z = 0.6, Pr = 72.57 %) 1. Find Expected time and variance Activity Optimistic time tO Most likely time tL Pessimistic time tP 1-2 4 8 18 1-3 4 5 18 2-4 3 7 23 2-5 1 11 33 3-4 6 6 18 3-5 3 9 21 4-5 7 12 35 5-6 9 8 31
  • 22. Activity Optimistic time tO Most likely time tL Pessimistic time tP Expected Time TE = tO + 4tL + tP 6 2 = $ $ 6 2 1-2 4 8 18 9 5.44 1-3 4 5 18 7 5.44 2-4 3 7 23 9 11.11 2-5 1 11 33 13 28.44 3-4 6 6 18 8 4 3-5 3 9 21 10 9 4-5 7 12 35 15 21.77 5-6 9 8 31 12 13.44 2. Draw network & find expected time 1 2 3 4 5 6 9 7 9 8 13 10 15 12 0 9 7 18 33 45 45 33 18 10 9 0 Critical Path 1-2-4-5-6 Project Duration = TE= 45 days
  • 23. Standard deviation along critical path = = 2 2 = 5.44+11.11+21.77+13.44 = 51.76 = 51.76 = 7.19 Probability of project completed in 50 days = Ts = = 5045 7.19 =0.69 From table Z= 0.6, Pr.= 72.57 Z= 0.7, Pr.= 75.80 0.6 72.57 0.7 75.80 0.1 3.23 0.09 x 0.1x= 0.09 X 3.23 x= 2.097 Probability of completing project within 50days= 72.57+2.907= 75.48%
  • 24. Precedence Networks : In CPM or PERT networks, activities are connected according to the finish-to-start logic, i.e. an activity starts only after its preceding activity is completed. But in reality, there will be a certain overlapping of time in between the adjoining activities. e.g. In a multi-housing construction project, the CPM network may show the activity of wall plastering as starting after the completion of masonry work of a particular building. In practice, however, plastering can start as soon as the first room is complete. It need not wait for completion of masonry work of all the rooms. The precedence network technique keeps the number of activities same as CPM networks (A-O-A networks) but eliminates the dummies. In the precedence networks nodes represent the activities and lines represent their interdependencies or precedence relationships. Representation of nodes in Precedence Networks: Description Code EST Dur. EFT LST No. LFT Steel Fabrication C 0 5 5 0 3 5 Rebar Transport D 5 1 6 5 4 6 Rebar Fixing E 6 3 9 6 5 9
  • 25. Logic of Precedence Diagram 1. Finish to Start Activity B cannot start until activity A has been completed. 2. Start to Start Activity B can start at the same time A but not before. 3. Finish to Finish Activity B cannot be finished until activity A has been finished. 4 Start to start & Finish to Finish: A B Time lag A B A B A B Time lag Time lag Time lag Time lag
  • 26. Activity B cannot be started and cannot be finished earlier than the stated time lag after the start and finish of activity A. This sequence is used to define overlapping independent activities. Advantages of Precedence Networks: Precedence network can show activities which should be allowed to overlap each other or must be separated by a time delay. Precedence network is self sufficient as it contains the necessary information regarding the project. Time analysis results are incorporated in the drawing itself. This facilitates efficient project scheduling and control. Revisions and modifications can be carried out easily without affecting most of the activities No arrow is required to show the logical sequence of activities. From the drawings, it is clear that all activities on the left precede those on the right. Precedence network adopts simple notations similar to flow charts and can be easily understood by any person.