際際滷

際際滷Share a Scribd company logo
Data Centres in Shared Buildings Barry Shambrook RCDD Tuckers Consultancy Ltd
Why locate in a shared building? Server hugging Virtualisation VoIP Thin client Space available Dark fibre 10 miles in London 贈250K per annum Cost of shared facility Energy efficiency
Space example
Monthly colocation costs per rack Source: www.mobilepricing.com
Monthly TCO per rack
Cost and emissions 贈300 per month 1 Tonne CO 2 /Balloon 2 Balloons  per month
Carbon Reduction Commitment
Lurking Vulnerabilities Latent deficiencies can surface at the worst possible moment
How Much Redundancy is Enough?
Uptime Institute tier resilience  car tyres Tier I - no spare wheel.  Stop and wait for AA Tier II -  Four wheels and a spare.  Stop, replace, drive on Tier III - Run Flat tyres.  Drive slower until opportunity to replace the tyre Tier IV  Two sets of wheels on each axle
Tier IV resilience Power Cooling Mains Generator Mains Generator Change Over Change Over UPS UPS Equipment Heat Rejection Heat Rejection (N+N) (N+N) Room Units Room Units (N+N)
Cost of resilience  plant efficiency 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
Shared building challenges Space for data centre Space for plant Size and number of utility supplies Risk limitation Noise restrictions
Case study #1 Large (10,000m 2  plus) office building Bespoke design for single anchor Tenant Sub-tenancies envisaged Requirement for 1000m 2  Data Centre On site processing and storage Remote back-up
CS1 Landlord data centre
CS1 Tenant data centre
CS1  power 2 fully autonomous grid supplies Generators on each supply, redundant shared Building UPS N+1 Redundant distribution
CS1 cooling N+N/N+1 chillers and cooling towers N+N secondary chilled water N+N CRAC units
Water cooling
Heat recovery
CS1 fire protection Pre-action sprinklers  building insurance VESDA  manual intervention Limited fire load in floor void
Pre-action sprinklers Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
Pre-action sprinklers - stage 1 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
Pre-action sprinklers  stage 2 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
Pre-action sprinklers  stage 3 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
Upgrade to water mist?
CS1 redundancy summary Power Cooling Mains Generator Mains Generator Change Over Change Over UPS (N+1) Equipment Heat Rejection (N+1) Room Units (N+1) (N+N) UPS (N+1)
Case study #2 Speculative 8000m 2  office building Multiple tenancies Requirement for 100m 2  Data Centre On site processing and storage option On site development option Remote parallel processing and storage
CS2 data centre plan
CS2  power 2 transformers, same HV ring Single generator, redundant switching Redundant distribution N+N UPS to data centre N UPS to trading floor and TRs Redundant distribution N+1 alternative for higher capacity
Bus bar power
CS2 cooling N+N chillers, free cooling N+N cooling distribution to data centre N+N secondary chilled water N+N in row cooling units N cooling to trading floor and TRs N+1 alternative for higher capacity
 Free cooling Summer Spring/Autumn/Morning/Evening Winter/Night
CS2 fire protection Pre-action sprinklers  building insurance VESDA Oxy-reduct for asset protection
Oxy-reduct Not approved by UK building insurers or Building Regulations so other protection also required. H&S limits exposure to 6 hours per day, otherwise completely safe. Oxygen level equivalent to 2700m above sea level.
CS2 infrastructure network Redundant external links 2 autonomous PoP rooms, 1 shared with data centre DC bypass
CS1 infrastructure network
CS2 4.5 kVA/rack N+N Power Cooling Transformer Generator UPS MER Racks MER Room Units Changeover Heat Rejection Heat Rejection MER Room Units UPS (N+N) SER S SER N 50% traders 50% traders (N+N) Changeover Transformer Mains (N+N)
CS2 8kVA/rack N+1 Power Cooling Transformer Generator N+1 UPS MER Racks N+1 MER Room Units Changeover N+1 Heat Rejection SER S SER N 50% traders 50% traders Changeover Transformer Mains
Summary Resilience compromises Efficiency improvements Added flexibility?
Ad

Recommended

PDF
Smart Grid Gotland - Wind Power Integration
Daniel A. Brod辿n
PPTX
Resultat fr奪n Smart Grid Gotland
Daniel A. Brod辿n
PDF
Demand-Response in the Smart Grid Gotland project
Daniel A. Brod辿n
PDF
Soft Magnetic Nanocrystalline Materials for Inductors and Shielding Applicati...
Sociedade Brasileira de Pesquisa em Materiais
PDF
Apc cooling solutions
peperoca
PDF
Tier III Data Center for Lease
guest9d585a7
PPT
Energy management 101
Matt Shea
PPTX
Basics of fire sprinkler design ascet meeting 2 5 (1)
Pankaj Soni
PDF
Cost Save Example - Maintenance
Scott VanMetre
PDF
Factsheet off grid generator
Carlos Ramirez
PDF
Portable spectrophotometer Mini Incus
Abengoa
PPTX
High Efficiency technologies for Data Centre Air Conditioning
CAREL Industries S.p.A
PDF
Bacs and water per il condizionamento degli edifici
CAREL Industries S.p.A
PDF
Data Center 2.1
alecroth
PDF
bijb
Chacha Permen
PPTX
CATALAN AIRPORTS NETWORK
rogermelcior
PPT
Airport IT Strategy
Sarmad Ibrahim
PPTX
Tematik wilayah jabar
Mochamad Lokyta
PDF
Smarter Airport Systems Transform Travel - IBM
IBMTransportation
PDF
Integrated ip network for airport terminal
Tuckers Consultancy Ltd
PDF
Transformed Airports: From Physical Touchpoints to Digital Services
Elif Tas
PPTX
Database Project Airport management System
Fahad Chishti
PPTX
POWER POINT PRESENTATION ON DATA CENTER
vivekprajapatiankur
PPTX
Airport planning and Design
srinivas2036
PPTX
07. datacenters
Muhammad Ahad
PPT
Ever Green Dc
Pravin Agarwal
PDF
Telecom argentina datacenters
Mario Lostri
PDF
Data Centre Design Consideration for Bangladesh
Bangladesh Network Operators Group
PDF
Deltalis Factsheet English
MichaelImfeld

More Related Content

What's hot (6)

PDF
Cost Save Example - Maintenance
Scott VanMetre
PDF
Factsheet off grid generator
Carlos Ramirez
PDF
Portable spectrophotometer Mini Incus
Abengoa
PPTX
High Efficiency technologies for Data Centre Air Conditioning
CAREL Industries S.p.A
PDF
Bacs and water per il condizionamento degli edifici
CAREL Industries S.p.A
PDF
Data Center 2.1
alecroth
Cost Save Example - Maintenance
Scott VanMetre
Factsheet off grid generator
Carlos Ramirez
Portable spectrophotometer Mini Incus
Abengoa
High Efficiency technologies for Data Centre Air Conditioning
CAREL Industries S.p.A
Bacs and water per il condizionamento degli edifici
CAREL Industries S.p.A
Data Center 2.1
alecroth

Viewers also liked (11)

PDF
bijb
Chacha Permen
PPTX
CATALAN AIRPORTS NETWORK
rogermelcior
PPT
Airport IT Strategy
Sarmad Ibrahim
PPTX
Tematik wilayah jabar
Mochamad Lokyta
PDF
Smarter Airport Systems Transform Travel - IBM
IBMTransportation
PDF
Integrated ip network for airport terminal
Tuckers Consultancy Ltd
PDF
Transformed Airports: From Physical Touchpoints to Digital Services
Elif Tas
PPTX
Database Project Airport management System
Fahad Chishti
PPTX
POWER POINT PRESENTATION ON DATA CENTER
vivekprajapatiankur
PPTX
Airport planning and Design
srinivas2036
CATALAN AIRPORTS NETWORK
rogermelcior
Airport IT Strategy
Sarmad Ibrahim
Tematik wilayah jabar
Mochamad Lokyta
Smarter Airport Systems Transform Travel - IBM
IBMTransportation
Integrated ip network for airport terminal
Tuckers Consultancy Ltd
Transformed Airports: From Physical Touchpoints to Digital Services
Elif Tas
Database Project Airport management System
Fahad Chishti
POWER POINT PRESENTATION ON DATA CENTER
vivekprajapatiankur
Airport planning and Design
srinivas2036
Ad

Similar to Small Data Centres (20)

PPTX
07. datacenters
Muhammad Ahad
PPT
Ever Green Dc
Pravin Agarwal
PDF
Telecom argentina datacenters
Mario Lostri
PDF
Data Centre Design Consideration for Bangladesh
Bangladesh Network Operators Group
PDF
Deltalis Factsheet English
MichaelImfeld
PDF
Datacenter Design Guide UNIQUE Panduit-Cisco
jpjobard
PPT
KJBi Development Example
kjbaudry
PPTX
Us matrix capabilities presentation
Danilo canivel
PDF
Data Centre Hosting Services
InTechnology Managed Services (part of Redcentric)
PDF
In Technology Data Centre Hosting Services
Romzan
PDF
Data Centre Hosting Services
N_Duffield
PDF
Data Centre Hosting Services
Mark Halpin
PDF
InTechnology Data Centre Hosting Services
merlinjenks
PDF
Data center 2.0: Data center built for private cloud by Mr. Cheng Che Hoo of ...
HKISPA
PDF
Viaje al centro de los datos: ingenier鱈a, arquitectura y ecolog鱈a
Facultad de Inform叩tica UCM
PDF
How DreamHost builds a Public Cloud with OpenStack
Carl Perry
PDF
How DreamHost builds a public cloud with OpenStack.pdf
OpenStack Foundation
PPTX
Data center m&e
Jebaraj D.A.L
PDF
Cap and exp data centres
Tuckers Consultancy Ltd
PDF
Geoff Wilmington - Challenge 1 - Virtual Design Master
vdmchallenge
07. datacenters
Muhammad Ahad
Ever Green Dc
Pravin Agarwal
Telecom argentina datacenters
Mario Lostri
Data Centre Design Consideration for Bangladesh
Bangladesh Network Operators Group
Deltalis Factsheet English
MichaelImfeld
Datacenter Design Guide UNIQUE Panduit-Cisco
jpjobard
KJBi Development Example
kjbaudry
Us matrix capabilities presentation
Danilo canivel
In Technology Data Centre Hosting Services
Romzan
Data Centre Hosting Services
N_Duffield
Data Centre Hosting Services
Mark Halpin
InTechnology Data Centre Hosting Services
merlinjenks
Data center 2.0: Data center built for private cloud by Mr. Cheng Che Hoo of ...
HKISPA
Viaje al centro de los datos: ingenier鱈a, arquitectura y ecolog鱈a
Facultad de Inform叩tica UCM
How DreamHost builds a Public Cloud with OpenStack
Carl Perry
How DreamHost builds a public cloud with OpenStack.pdf
OpenStack Foundation
Data center m&e
Jebaraj D.A.L
Cap and exp data centres
Tuckers Consultancy Ltd
Geoff Wilmington - Challenge 1 - Virtual Design Master
vdmchallenge
Ad

More from Tuckers Consultancy Ltd (6)

PDF
Cap and exp sport facilities its
Tuckers Consultancy Ltd
PPTX
10 dos and donts of data centre design
Tuckers Consultancy Ltd
PPTX
Crc Presentation
Tuckers Consultancy Ltd
PPTX
BERi Service Provider Presentation
Tuckers Consultancy Ltd
PPT
The investment case for reduction in building energy consumption
Tuckers Consultancy Ltd
PPT
Bicsi 2010 IP Consolidation
Tuckers Consultancy Ltd
Cap and exp sport facilities its
Tuckers Consultancy Ltd
10 dos and donts of data centre design
Tuckers Consultancy Ltd
Crc Presentation
Tuckers Consultancy Ltd
BERi Service Provider Presentation
Tuckers Consultancy Ltd
The investment case for reduction in building energy consumption
Tuckers Consultancy Ltd
Bicsi 2010 IP Consolidation
Tuckers Consultancy Ltd

Small Data Centres

  • 1. Data Centres in Shared Buildings Barry Shambrook RCDD Tuckers Consultancy Ltd
  • 2. Why locate in a shared building? Server hugging Virtualisation VoIP Thin client Space available Dark fibre 10 miles in London 贈250K per annum Cost of shared facility Energy efficiency
  • 4. Monthly colocation costs per rack Source: www.mobilepricing.com
  • 6. Cost and emissions 贈300 per month 1 Tonne CO 2 /Balloon 2 Balloons per month
  • 8. Lurking Vulnerabilities Latent deficiencies can surface at the worst possible moment
  • 9. How Much Redundancy is Enough?
  • 10. Uptime Institute tier resilience car tyres Tier I - no spare wheel. Stop and wait for AA Tier II - Four wheels and a spare. Stop, replace, drive on Tier III - Run Flat tyres. Drive slower until opportunity to replace the tyre Tier IV Two sets of wheels on each axle
  • 11. Tier IV resilience Power Cooling Mains Generator Mains Generator Change Over Change Over UPS UPS Equipment Heat Rejection Heat Rejection (N+N) (N+N) Room Units Room Units (N+N)
  • 12. Cost of resilience plant efficiency 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0%
  • 13. Shared building challenges Space for data centre Space for plant Size and number of utility supplies Risk limitation Noise restrictions
  • 14. Case study #1 Large (10,000m 2 plus) office building Bespoke design for single anchor Tenant Sub-tenancies envisaged Requirement for 1000m 2 Data Centre On site processing and storage Remote back-up
  • 16. CS1 Tenant data centre
  • 17. CS1 power 2 fully autonomous grid supplies Generators on each supply, redundant shared Building UPS N+1 Redundant distribution
  • 18. CS1 cooling N+N/N+1 chillers and cooling towers N+N secondary chilled water N+N CRAC units
  • 21. CS1 fire protection Pre-action sprinklers building insurance VESDA manual intervention Limited fire load in floor void
  • 22. Pre-action sprinklers Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
  • 23. Pre-action sprinklers - stage 1 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve
  • 24. Pre-action sprinklers stage 2 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
  • 25. Pre-action sprinklers stage 3 Smoke detector 1 Smoke detector 2 Alarm Bell Sprinkler head 67 deg C Water Compressed air Automatic valve Water
  • 27. CS1 redundancy summary Power Cooling Mains Generator Mains Generator Change Over Change Over UPS (N+1) Equipment Heat Rejection (N+1) Room Units (N+1) (N+N) UPS (N+1)
  • 28. Case study #2 Speculative 8000m 2 office building Multiple tenancies Requirement for 100m 2 Data Centre On site processing and storage option On site development option Remote parallel processing and storage
  • 30. CS2 power 2 transformers, same HV ring Single generator, redundant switching Redundant distribution N+N UPS to data centre N UPS to trading floor and TRs Redundant distribution N+1 alternative for higher capacity
  • 32. CS2 cooling N+N chillers, free cooling N+N cooling distribution to data centre N+N secondary chilled water N+N in row cooling units N cooling to trading floor and TRs N+1 alternative for higher capacity
  • 33. Free cooling Summer Spring/Autumn/Morning/Evening Winter/Night
  • 34. CS2 fire protection Pre-action sprinklers building insurance VESDA Oxy-reduct for asset protection
  • 35. Oxy-reduct Not approved by UK building insurers or Building Regulations so other protection also required. H&S limits exposure to 6 hours per day, otherwise completely safe. Oxygen level equivalent to 2700m above sea level.
  • 36. CS2 infrastructure network Redundant external links 2 autonomous PoP rooms, 1 shared with data centre DC bypass
  • 38. CS2 4.5 kVA/rack N+N Power Cooling Transformer Generator UPS MER Racks MER Room Units Changeover Heat Rejection Heat Rejection MER Room Units UPS (N+N) SER S SER N 50% traders 50% traders (N+N) Changeover Transformer Mains (N+N)
  • 39. CS2 8kVA/rack N+1 Power Cooling Transformer Generator N+1 UPS MER Racks N+1 MER Room Units Changeover N+1 Heat Rejection SER S SER N 50% traders 50% traders Changeover Transformer Mains
  • 40. Summary Resilience compromises Efficiency improvements Added flexibility?

Editor's Notes

  • #6: ENERGY COST IS LARGE PROPORTION BUILD COST GET IT RIGHT!
  • #9: Future Proofing - Optimizing Tier-IV Data Centers You are most vulnerable to what you dont see or didnt anticipate. FUTURE PROOFING collaboration and cross-pollination Where will it fail vs will it work? Investing in strategic planning
  • #10: Future Proofing - Optimizing Tier-IV Data Centers Fault tolerance = Mean Time Between Failures MTBF MTTR = Mean time to restore Critical Infrastructure must be intuitively operable Simplicity = Reliability
  • #32: Allows additional supplies and enhanced capacity N+1 INSERT PICTURES
  • #36: INSERT VIDEO AND OXYGEN CHART
  • #39: INSERT SUMMARY DIAGRAM